176 P. 124 | Or. | 1918
At the hearing before the Circuit Court it was agreed that the following items of the plaintiff’s claim were the only ones disputed:
Excavation and placing earth in the embankment for reservoir dam, 32,691 cubic yards, at 35^ per yard................11,441.85
"Work and labor for August, 1916, in addition to above .................... 123.44
The defendants admit $121.95 of this last item, challenging thereof only $1.49, but dispute the following:
For work, labor and material furnished for
September, 1916, in addition to the above. $899.81 Work and labor for October, 1916, in addition to the above ......................... 460.32
Work and labor and material furnished for November, 1916, in addition to the above 416.75
“No extra work shall be done without written orders from W. A. Steward or his engineer. Extra work or material of a character not provided for in the specifications if ordered in writing by the engineer,*222 will be paid for at actual necessary cost, as determined by the engineer, plus 10 per cent for profit, superintendence, and general expenses. The cost of extra work shall include all materials, labor and fuel furnished by the contractor; but shall not include use ' of tools or machinery, office expenses, general superintendence, or other general expenses. Demand for payment must be made in writing by the contractor promptly upon the completion of the extra work or furnishing of the extra material. The account including the same must be accompanied by the certificate of the engineer stating that such work has been satisfactorily performed or such material furnished, and stating the amount to be allowed therefor. The contractor shall, when requested by the engineer, furnish itemized statements of the cost of the work ordered, and give the engineer access to accounts, bills, and vouchers relating thereto.”
If ,the work mentioned in the third modification, as pleaded, related to the erection of the dam in any way, it was already provided for in the excerpt just quoted from the written contract, so that the allegation does not amount to a modification. As to the expense for powder, caps and the clearing and grubbing of the borrow-pits, the consideration for the alleged agreement of Steward to pay for the same as averred in the complaint is that:
“The plaintiff thereupon agreed to and with said Steward, agent for defendant * * to proceed with the construction of the said reservoir and dam and to finish and complete the same as soon as possible, and without unnecessary delay. ’J
Recalling that at that very time the plaintiff was under contract to finish the identical dam, we read from 13 C. J. 351:
“A promise to do what the promisor is already bound to do cannot be a consideration, for if a person gets nothing in return for his promise but that to*223 which he is already legally entitled, the consideration • is unreal. Therefore, as a general rule, the performance of, or promise to perform, an existing legal obligation is not a valid consideration. This legal obligation may arise from the law independent of contract, or it may arise from a subsisting contract»1’
After discussion of the obligation at law, the author, speaking of subsisting contractual obligations, continues on page 353:
“The promise of a person to carry out a subsisting contract with the promisee or the performance of such contractual duty is clearly no consideration, as he is doing no more than he was already obliged to do, and hence has sustained no detriment, nor has the other party to the contract obtained any benefit. Thus a promise to pay additional compensation for the performance by the -promisee of a contract which the promisee is already under obligation to the promisor to perform is without consideration.”
See, also, Nine v. Starr, 8 Or. 49; Myers v. Livesley, 56 Or. 383, 389 (107 Pac. 476, 108 Pac. 121); Hillman v. Young, 64 Or. 73 (127 Pac. 793, 129 Pac. 124); Muir v. Morris, 80 Or. 378 (154 Pac. 117, 157 Pac. 785).
The testimony of the plaintiff in this connection is in substance that after he had entered upon the performance of the undertaking he saw that he would be unible to complete the contract except at a loss, and therefore went to Steward and offered him $1,000 if the latter would release the plaintiff from the work, but that Steward declined the offer, whereupon it was agreed that Steward should pay the plaintiff for clearing the borrow-pits and the like, as stated, in consideration of which the plaintiff agreed to complete the dam. The reason he avowed for thus approaching Steward was that he was compelled to haul earth to make the fill of the dam farther than he had
“The party of the first part hereby agrees that he has, in person, or by his agent, examined the premises and line'of dam on which the work is to be performed, and his knowledge of the conditions surrounding the same is gained firmn such observations and not from representations of the engineer or - the party of the second part.”
In the specifications attached to and made a part of the contract and introduee'd into evidence by the plaintiff appears the following:
“Borrow-pits and classification of material: — The engineer will designate the borrow-pits from which all materials for the fills shall be obtained. The contractor shall strip the borrow-pits to the satisfaction of the engineer and the cost of such stripping shall be included in the price bid for the fill. , The classification of the materials from the borrow-pits shall be under the supervision of the engineer who will, at all times, direct at what points it shall be placed on the dam. The price per cubic yard, bid by the 'Contractor, for fill shall include all plowing or loosening in the borrow-pits, loading, hauling, unloading, spreading, wetting and rolling, and no allowance whatever will be made for overhaul. The average length of haul will be approximately one thousand (1,000) feet from the borrow-pits to the dam. All payments for materials placed in the fill shall be on the basis of actual volume measured in the dam after settlement of the fill has ceased.” • \
There is no pretense of stating in the complaint that the plaintiff was induced to execute the contract by reason of any fraud or deceit upon the part of the defendants or their agent. It is plain, therefore, from the authorities and from the evidence of the plaintiff himself that the supplementary agreement as stated in the complaint concerning the clearing and grubbing
“It is competent for parties to stipulate in a contract of the nature of the one here in controversy that the contractor shall procure the certificate of an architect that the work has been performed or the building completed in accordance with his undertaking, as a condition precedent to the payment of any installment or the amount finally to become due. Generally speaking, no action or suit can be maintained therefor against the owner until the condition is performed or its requirements waived. The contract becomes a law between the parties in this respect, as they expressly agree that the amount due for the service shall be established by the certificate of the architect; and it throws upon the contractor the burden of producing the particular kind of evidence required by the mutual stipulations of the parties concerning it, unless the circumstances are such * * that the contractor is unable to produce it through no fault of his. Were it otherwise the law would take from the owner the particular kind of protection against defective and lax performance that he has ex*226 pressly stipulated for: Hanley v. Walker, 79 Mich. 607 (45 N. W. 57, 8 L. R. A. 207); Clarke v. Watson, 18 Com. B. (N. S.) 278; United States v. Robeson, 34 U. S. (9 Pet.) 319 (9 L. Ed. 142); Martinsburg & P. R. Co. v. March, 114 U. S. 549 (29 L. Ed. 255, 5 Sup. Ct. Rep. 1035); Hudson v. McCartney, 33 Wis. 331; Smith v. Brady, 17 N. Y. 173 (72 Am. Dec. 442); Michaelis v. Wolf, 136 Ill. 68 (26 N. E. 384). A salutary rule of practice also requires that where there is au excuse, or sufficient reason exists why the contractor has been unable to secure or produce such a certificate — as that it has been waived, or the like — it should be averred in the pleadings, so as to lay a foundation for the admission of the proofs to establish the condition.”
See, also, Hart v. Carsley Mfg. Co., 221 Ill. 444 (77 N. E. 897, 112 Am. St. Rep. 189, 5 Ann. Cas. 720), and Korbly v. Loomis, 172 Ind. 352 (88 N. E. 698, 139 Am. St. Rep. 379, 19 Ann. Cas. 905).
This disposes, adversely to the plaintiff, of the following disputed items in his claim of lien:
Deduction from work for July and August. .$ 1.49'
Work for September...................... 899.81
Work for October.................’....... 460.32
Work for November...................... 416.75
$1,778.37
“To prevent all disputes and misunderstandings in relation to any of the stipulations contained in this agreement or performance by either of said parties, the said engineer'shall be and hereby is made umpire to decide all controversies arising or growing out of this contract and his decision on any point or matter touch*227 ing this agreement shall be final and conclusive between the parties hereto. And it is further agreed between said parties that wherever the word ‘engineer’ is used it shall be taken and construed to mean chief engineer employed by said second party.”
Further, in the specifications, we find:
“Where the word ‘engineer’ is used in the general conditions or detail specifications, or in the contract, it shall be and is mutually understood to refer to the engineer employed by W. A. Steward to supervise the construction of all or any part of the work contemplated in these specifications. The engineer will give the locations and the grades for the work, and no work depending on such locations and grades will be commenced until these have been established, and the contractor shall provide such materials and give such assistance as may be required by the engineer. Upon all questions concerning the execution of the work, the classification of the material in accordance with the specifications, and the determination of costs, the decision of said engineer shall be binding on both parties. ”
As said by Mr. Justice Eakin in Williams v. Mt. Hood Ry. & P. Co., 57 Or. 251, 257 (110 Pac. 490, 492, Ann. Cas. 1913A, 177):
“Parties to a contract may stipulate that the estimate of the work done, and the amount due under the contract shall be made by a third party, and shall be "final and conclusive. There are a multitude of cases so holding. ’ ’
In a copious note to Mercantile Trust Co. v. Hensey, 205 U. S. 298 (27 Sup. Ct. Rep. 535, 51 L. Ed. 811, 10 Ann. Cas. 572), a wealth of precedent is collated on this point. Of course the decision of the engineer could be impeached for fraud or on other equitable grounds, but there is no question of that kind embodied in the pleadings in the instant case.
The complaint did state sufficient to support part of the claim and hence the general demurrer was properly overruled, but the principle was not waived when it came to the proof of the plaintiff’s allegations. It is unnecessary to discuss the other questions raised by the answer. The result is that the decree of the Circuit Court is reversed and the suit is dismissed.
Reversed and Suit Dismissed.