48 Mich. 612 | Mich. | 1882
In July, 1881, -one Frederick Speier «entered into a written contract with the defendant Dinan that he would erect three specified frame dwellings for Dinan and would “ well and sufficiently perform, finish and •complete all the work, included in the excavation, drain ■brick work, concreting, plastering, and all work included in and implied by mason’s specifications to plans ; also all carpenter and joiner work, iron and tin work, all plumbing and gas-fitting and painting and glazing, and all work indicated on and implied by plans and specifications for completion and entire finishing” of the buddings, “ and in strict accordance to and with the plans, specifications, conditions, «ste., furnished said contractor by W. G-. Malcomson, architect.” The contract provided that Speier should fully perform on or before the first day of November, 1881, and that Dinan' should pay therefor $4972.
It was also agreed that the round price so stipulated to be paid for the entire work and materials should be “ payable in manner following, viz., (when drains are in and brick work off::)
3881. August 18. 1. Cellars and foundation are completed, the sum of.........$500
August 18. 2. Frames up and sheaths, the sum of . . 700
September 7. 3. Roofs and cornices on, the sum of . 600
September 7. 4. Building enclosed, the sum of . . . 700
October 26. 5. Ready for lath, the sum of .... 800
•December 9. 6. Outside finished complete,building ready to plaster..........800
7. All completed and' accepted, . , . . 872 ”
There were other provisions which need not be quoted. According to one of them it was stipulated that Dinan should have $3 for each day the job should remain unfinished after November first.
The plaintiff brought assumpsit against Speier before a justice of the peace and in November, 1881, garnished JDinan as Speier’s debtor, and on the 2d of December he
In January, 1882, he was summoned to show cause why judgment should not go against him. It appeared that' the-job was now cojnpleted. The justice rendered judgment in his favor but the circuit court reversed it with costs of both, courts.
’Whether Dinan was liable to be held or not depended'on. whether he was shown to be Speier’s debtor at the timer the proceeding was instituted. He was bound then, if at all; unless he was Speier’s debtor at that date it was not competent to hold him. His becoming debtor afterwardswould not avail. And there was no proof that a state of indebtedness existed at the time the writ was commenced,. An indebtedness might arise and might not.
Whether the job would be completed was uncertain,’ and unless it should be it did not appear that Speier would have-a right to claim anything more. It was not certain that what would be necessary to fix Dinan with' liability to pay Speier something more on the express contract would everoccur; and it was impossible to say that' a state of things-would arise in future to create a liability for anything outside the express contract on the theory of implied contract or liability.
The judgment of the justice was correct and that of the-circuit court wrong.
The judgment of the circuit court will be reversed and that of the justice affirmed, and the defendant will recover." his costs of this Court and of the circuit court.