*420 OPINION
STATEMENT OF THE CASE
Hopper Resources, Inc., Construction Division (“Hopper”), appeals the trial court’s order denying judgment to Hopper on its claim asserted against Wendell Webster in a complaint seeking the foreclosure of a mechanic’s lien and additional damages.
We affirm.
ISSUE
Whether the trial court erred in denying judgment to Hopper.
FACTS
John Shamo is a geologist and president of Hopper Resources, Inc., which undertakes construction projects through its Construction Division. Shamo learned that Wendell Webster wanted to have an addition built on his home. After meeting with Webster, Shamo presented Webster with a proposal dated September 27, 2003, from “Hopper Construction, Inc., A Division of Hopper Resources, Inc.,” as “Contractor,” to “furnish all equipment, material and labor necessary” to add a finished bathroom, pour a concrete patio adjoining the finished bathroom and the back of Webster’s house, and extend the house roof over both. (Ex. 7). The total cost for the proposed work was $15,900.00. The proposal was signed by Shamo, as President; and reflects that on October 8, 2003, Webster signed his “acceptance of proposal” and “authorized” Hopper “to do the work as specified.” Id. Webster gave Sha-mo $8,000.00 as a down payment.
Hopper directed John Claspell, Tony Dorris, and James Clark to perform the contracted project at Webster’s home. “Half way [sic] through the project, Mr. Webster requested that the room [added for the bathroom] be divided and an exterior bathroom access” be installed, such that the addition would also contain a half-bath that could be reached from the newly poured adjoining patio. (Tr. 29). An “addendum” from Hopper, dated November 3, 2003, proposed to “furnish all equipment, materials and labor necessary to” add a wall, and install and finish the requested half-bath for an additional cost of $2,100.00. (Ex. 11). Webster signed his acceptance on November 5, 2003.
Sometime thereafter, Shamo learned that there had been no building permit obtained for the work being done at Webster’s home. On November 25, 2003, Sha-mo went to the Building Commission office and obtained an Improvement Location Permit for the addition of a bathroom and a porch to Webster’s residence. Shamo completed a “Homeowner Affidavit” stating that ‘Wendel [sic] Webster” thereby swore that “either [he] or a member of [his] immediate family” would “perform the ... work” of adding the room and porch at his residence, “for which Building Permit # 106771E” was being issued, and that he would not be “subcontracting out any of the work” thereon. (Ex. A). Sha-mo signed Webster’s name on the affidavit. The Commission then issued to “applicant Wendel [sic] Webster” building permit # 106771E authorizing the “bathroom & porch addition” at Webster’s residence. (Ex. 10). The permit in Webster’s name for the work at the residence was thereafter posted on the site.
The Hopper workers proceeded to complete most of the work specified in the contracts. According to John Claspell, on March 10, 2004 (Shamo believed it was at a later date in March but could not identify an exact date), he and other Hopper workers went to the Webster home to install a vapor barrier and pea gravel under the *421 addition as ordered by “Code Enforcement” to “bring everything into [C]ode (Tr. 32, 25). Claspell testified that the workers were told that Webster wanted them off the property and not to return.
On April 19, 2004, Shamo sent Webster an invoice from Hopper demanding $7,500.00 in payment for the work completed. On May 13, 2004, Shamo signed and recorded a notice asserting Hopper’s entitlement to a lien of $7,500.00 for Hopper’s “labor or ... materials or machinery for improvements to” Webster’s property, and that Hopper “performed labor on the 23rd day of March, 2004.” (Ex. 15).
On October 19, 2004, Hopper filed a complaint on mechanic’s lien, asserting that Webster had refused to pay $7,500.00 for home improvements and seeking judgment of foreclosure of the mechanic’s lien in the amount of $7,500.00, plus pre-judgment interest, attorney fees, and costs. On December 9, 2004, Webster filed an answer that also asserted the affirmative defense of “fraud.” (App.14). On August 31, 2005, Webster filed a counter-claim, asserting Hopper’s breach of contract — by performing “unworkmanlike” and “inferi- or” work that “need[ed] to be razed” and rebuilt. (App.16). On September 8, 2005, Hopper filed a motion to strike both Webster’s counterclaim and affirmative defense. Hopper asserted that the counterclaim was untimely, and was filed without leave of the court; and that the affirmative defense failed to comply with Indiana Trial Rule 9(B)’s requirement that the circumstances constituting fraud be specifically pled. On January 13, 2006, the trial court ruled that Webster would be allowed to file a more specific pleading of his affirmative defense. On January 24, 2006, Webster filed a more specific affirmative defense, asserting that Hopper had “held [itjself out to be a licensed and bonded contractor,” that Hopper obtained a building permit by “pullfing] a homeowner’s permit” and “forg[ing] [Webster]’s name on the homeowner’s affidavit,” and that Hopper was “not a licensed and bonded contractor and his [sic] forging of [Webster]’s name on an affidavit constituted fraud.” (App.24).
At the outset of trial on February 8, 2007, the motion to strike Webster’s counterclaim was discussed. The trial court ruled that the late filed counterclaim was denied and stated, “[T]here is no Counterclaim.” (Tr. 58). Hopper then presented its case, with Claspell and Shamo as the only witnesses. Webster did not call witnesses but did introduce as an exhibit the Homeowner Affidavit (during its cross examination of Shamo). On May 9, 2007, the trial court issued its judgment order, which includes sua sponte findings and conclusions. Therein, the trial court found inter alia that “a lawful permit was a necessary condition precedent to” Hopper’s performance of work “and any recovery for the value thereof’; that because Hopper “had no legal permit to perform the work” on Webster’s residence, Webster “was justified in refusing to allow” Hopper’s workers “to return to the job site and perform any further illegal operations”; and that Hopper could “not benefit from its/his own wrongdoing.” (App.37). The trial court concluded that Hopper was not “entitled to recover any further compensatory damages” and entered “final judgment against [Hopper] on [Hopper]’s claim.” Id.
DECISION
We note at the outset, that Webster has not filed a brief in response to Hopper’s appeal. When the appellee does not file a brief, the “appellant may prevail by establishing a
prima facie
case of error.”
Trinity Homes, LLC v. Fang,
The standard for the appellate review of claims tried to the bench provides that the reviewing court shall not set aside the judgment unless clearly erroneous, and due regard shall be given to the opportunity of the trial court to judge the credibility of the witnesses.
Bennett v. Broderick
We begin with the observation that Hopper’s action — which was styled “Complaint to Foreclose Mechanic’s Lien,” (App.9)— sought relief in equity.
See Brighton v. White,
First, “one who comes into equity must come with clean hands”; a principle that denies “relief to one whose conduct concerning the matter in controversy has been fraudulent, illegal, or unconscionable” as to another such that the other party is harmed.
Id.
at § 24;
see also Traylor v. By-Pass 46 Steak House, Inc.,
Another maxim provides that “whomever seeks equity must do equity”; a principle whereby “relief which involves perpetration of an injustice will be denied.” 12 I.L.E.
Equity
§ 25. Thus, “he who would invoke the aid of a court of equity ‘must show that he has done equity to him of whom he complains.’ ”
Shaw v. Meyer-Kiser Bank,
Yet another maxim provides that “equity follows the law,” 12 I.L.E.
Equity
§ 22. In application, this means that “an equitable right cannot be founded on a violation of law.”
Noble v. Davison,
The trial court found Hopper “obtained the requisite building permit by applying for and obtaining a homeowner’s permit”; that the application therefor was a “Homeowner’s Affidavit” on which Shamo signed Webster’s name as homeowner; and this affidavit led to the Building Commission *423 er’s issuance of “the requisite permit for performing the work in question.” (App.36, 37). The trial court concluded that a “lawful permit was a condition precedent” to Hopper’s “performance of work and any recovery for the value thereof’; that Hopper could “not benefit from its/his own wrongdoing”; and that Hopper “had no valid permit to perform the work in question.” (App.36, 37).
Hopper did not introduce into evidence, and in its arguments to the trial court it did not reference, the requirements of the Evansville Zoning Ordinance concerning building permits. However, the contents of the exhibits introduced support the inference that a building permit is a prerequisite for work such as the addition to Webster’s house, and that only a homeowner may obtain a permit based on a Homeowner’s Affidavit. 1 The Affidavit states that the homeowner or an immediate family member will perform the work on the residence in which the homeowner resides. The Affidavit also includes a requirement that the homeowner disclose the “subcontracting out of any work outlined in the permit issued to [the homeowner],” and further states in bold print that “all subcontractors must be licensed in Vanderburgh County.” (Ex. A). Moreover, Shamo admitted that he was the person who went to the Building Commission office and signed Webster’s name on the Homeowner Affidavit.
Thus, the evidence supports the trial court’s findings that a building permit was necessary to perform the work, that the permit obtained was one issued based on a Homeowner Affidavit signed by Shamo— not Webster, the homeowner. Accordingly, the trial court’s conclusion that Hopper had no valid permit to perform the work on Webster’s residence is supported by the findings. Moreover, given that Hopper’s complaint sought relief based on the trial court’s equity jurisdiction, and the trial court’s express conclusion that Hopper could not profit from its own wrongdoing, the trial court’s judgment denying relief to Hopper is not clearly erroneous.
Hopper presents a series of challenges to the trial court judgment, but all seek to persuade us to reverse the trial court’s judgment and remand for judgment in favor of Hopper on its claim to foreclose mechanic’s lien or breach of contract. However, we find those arguments unavailing.
Hopper argues that the trial court committed reversible error “in failing to apply an adverse inference against Webster based upon his failure to testify and failure to call any witnesses.” Hopper’s Br. at 9. However, Hopper presents no authority for the proposition that such shifts the burden of proof. As the plaintiff, Hopper bore the burden of proof: to establish its claim by a preponderance of the evidence. The trial court concluded that it had failed to satisfy its burden, and we agree.
Hopper next argues that the evidence does not support the trial court’s “conclusion that the work was being performed illegality [sic],” and that even if that were so, recovery may be had.
Id.
We have already found that the evidence supports the trial court’s findings and conclusion that the addition to Webster’s house required a building permit, and that the permit Shamo obtained for Hopper was not a valid permit,
ie.,
the work was being performed illegally. Hopper cites
Phend v. Midwest Engineering and Equip. Co.,
Hopper cites
Greenhaven Corp. v. Hutchcraft & Assocs., Inc.,
Throughout its brief, Hopper argues that Shamo’s signature of Webster’s name was with Webster’s acquiescence and at Webster’s request. However, the credibility of witnesses is a matter for the trial court.
See Bennett,
Hopper also argues that the trial court erred in finding that Hopper could not recover under the contract “based upon the principle of illegality” because Webster failed to expressly plead “illegality” as an affirmative defense. Hopper’s Br. at 16. We again return to the fact that by the nature of its complaint, Hopper sought equitable relief and that it bore the burden of proving its entitlement to relief. Therefore, this argument fails.
In a similar vein, Hopper argues that Webster “failed to meet his burden of proof on his affirmative defense of fraud” by not establishing all of the elements of fraud.
Id.
at 17.
Inter alia,
he asserts the lack of any “intent to deceive” on the part of Shamo, citing Shamo’s testimony that the staff of the Building Commission office were aware “that he was not Wendell Webster but John Shamo” and “directed” him “to execute the homeowner’s affidavit on behalf of Mr. Webster” and to sign Webster’s name.
Id.
at 19. Again, we note that whether this testimony was credible was a matter for the trial court.
Bennett,
Next, Hopper argues that the evidence fails to support the trial court’s finding that Hopper’s “work was performed in a defective manner and caused the Building Inspector to require additional corrective work.” Hopper’s Br. at 22. As recounted in FACTS, Hopper’s workers were at Webster’s residence in mid-March to in *425 stall a vapor barrier and pea gravel under the addition as ordered by “Code Enforcement” to “bring everything into [C]ode.” (Tr. 32.25). This evidence supports the reasonable inference that construction work which fails to meet the construction code is defective work.
Hopper argues that he “is entitled to recover on the mechanic’s lien” because it “substantially conforme[ed] with statutory requirements.” Hopper’s Br. at 24. Hopper cites
Premier Investments v. Suites of America,
Next, Hopper argues that it “was entitled to recover on breach of contract,” citing “unrefuted evidence” that it “was owed and ha[d] incurred damages” in the amount of $7,500.00 “as a result of Webster breaching the parties’ contract by running Hopper off the job and refusing to pay.” Hopper’s Br. at 29, 30. The evidence was that Webster refused to allow further work by Webster after the inspector found that the work failed to comply with Code. The Homeowner Affidavit expressly provides that “if the Inspector should find the work in the violation of the Code, then [the homeowner] shall employ a master installer of the required trade or craft to change, alter, or repair the work that is in violation.” (Ex. A). Hopper offered no evidence to establish that it held such credentials. The only evidence as to licensing was Shamo’s testimony that on other projects, Hopper had “worked under somebody else’s license ... many times.” (Tr. 53). Absent a showing that Hopper held credentials to perform the corrective work required by the Homeowner Affidavit, the circumstances here did not require that Webster allow Hopper workers to perform further work. Therefore, Hopper’s breach of contract claims must fail.
Affirmed.
Notes
. The Affidavit refers to provisions of “Article 15.3140 of the Vanderburgh County Building Code or Article 15.150.134 of the Municipal Code of Evansville” regarding the consequences “if the inspector should find work in violation of the Code.” (Ex. A).
