19 Tex. 400 | Tex. | 1857
The plaintiff, C. B. Raines, alleges, in substance, that he employed the defendants, Hood and Jones, to ceil and weatherboard his dwelling-house, make some additional rooms and other work, the extent, dimensions and finish of which, are very minutely described, and that this work was to be done by defendants, with reasonable dispatch, whenever plaintiff could procure and have in readiness the lumber for the same ; that the work was commenced and continued at intervals, by the defendants, until in Jan’y, 1852, they ceased working, with the express promise by them to the plaintiff, that they
On the trial the defendants attempted to prove by a witness, that the plaintiff did not have, at the time of his notification to the defendants in Nov. 1852, a sufficiency of lumber to complete the contract; but this was refused, on the ground that such proof was not admissible under the pleadings.
It appears, from the evidence, that the work left uncompleted by the defendants, would cost about two hundred and fifty dollars, according to the common rule of charge ; that the price of the whole work by the contract, was six hundred dollars, and that the plaintiff had paid five hundred and ninety-seven dollars. The jury found for the plaintiff one hundred and twelve dollars and fifty cents.
The above are some of the most material of the pleadings and facts, and will enable the opinion to be understood.
It appears that the first default was on the part of the plaintiff, in not providing a proper supply of lumber. But that was waived by the subsequent agreement that the defendants would return and complete the work on being notified by plaintiff that the lumber was ready. This notification was given, but defendants pleaded that the delay in giving it was so unreasonable, as to operate an abandonment of the contract, and that, in fact, the lumber was not ready at the time of the notice given. The ground on which plaintiff places his right to recovery by his allegations, is substantially that he was in no default ; that he had performed the precedent condition by giving notice, and that the failure being wholly on the part of defen
But it appears from the facts in the cause, that the liability of the defendants does not rest solely on the ground of the fact that lumber was prepared and notice given by plaintiff. It appears that the whole amount of the price of the work, with the exception of three dollars, had been paid by the plaintiff, while the evidence shows that a large portion of the work had not been completed by the defendants, and that by the usual rate of charges, the work not completed would amount to two
The defendants, as we have seen, would not, if no money had been paid, be entitled to recover the whole contract price, but only the damages they had sustained. The plaintiff could not, in such case, sue at all to enforce the performance of the contract, or to recover damages for its non-performance, on account of his failure to perform the condition of supplying the lumber.
The failure of the plaintiff to have lumber in readiness at the time of his notice, would not, it is conceived, be a forfeiture of all right to any portion of the money which he had advanced to the defendants, but would make him liable for such damages as had accrued to them, in consequence of his default. This may perhaps absorb the greater portion of the money paid, but he is entitled to the excess, if any should remain ; and this may, on a proper state of pleading, be recovered by him.
There are other questions in the cause, but it is believed that they do not require any distinct consideration, and that no error of controlling importance, except the one discussed, was committed in the cause. It would have been proper to have allowed defendants’ allegation of unreasonable delay on the part of the plaintiff, in giving notice to the defendants, to have stood as pleaded. If it had turned out on proof, that the plaintiff had made but a small payment on the contract, it would have been
It is possible—and, from the facts, it seems probable—that justice was done between the parties by the verdict of the jury, yet, the defendants have complaimed of the judgment, and for the error of sustaining the exception to the plea that the plaintiff had not lumber in readiness at the time of his notice, the judgment is reversed and the cause remanded.
Reversed and remanded.