Lead Opinion
Respondents, students of the California School for the Blind, brought this lawsuit in Federal District Court against petitioner state officials, claiming among other things that the school’s physical plant did not meet applicable seismic safety standards. Their complaint alleged rights of action undеr the Education for All Handicapped Children Act of 1975, 89 Stat. 773, 20 U. S. C. §§ 1232, 1401, 1405, 1406, 1411-1420, 1453, and § 504 of the Rehabilitation Act of 1973, 87 Stat. 394, as amended, 29 U. S. C. § 794. After a lengthy
Petitioners have petitioned this Court for a writ of cer-tiorari to review the judgment of the Ninth Circuit, but in the meantime the tests ordered by the District Court’s preliminary injunction have been completed. We therefore are confronted with a situation nearly idеntical to that addressed in University of Texas v. Camenisch,
Dissenting Opinion
dissenting.
Although I agrеe with the majority that a case such as this could be moot if the full burden imposed by the preliminary injunction has passed, it is not at all clear that that is the situation here. If this case is moot, the facts making it moot occurred subsequent to the Court of Appeals decision, and so do not appear on the record. That makes this case quite distinct from University of Texas v. Camenisch,
Mootness is mentioned twice in the papers before the Court. First, petitioners argue in their petition for certio-rari that the cаse is not moot in spite of the fact that “by the time this Court considers the instant petition, the state officials may well have already comрlied with the injunction. . . .”
This theme is repeated in the respondents’ opposition. Resрondents assert that the tests ordered by the District Court have been completed “and the final report in all likelihood will be completed before this Court determines whether to grant the present petition.” Brief in Opposition 14 (emphasis added). The opposition goes on to assure the Cоurt that “should the final report of the trial court’s experts indicate, and the trial court find, that the Fremont site is seismically safe, there will remain no live issue whatsoever between the parties as to any aspect of the case.” Id., at 15 (emphasis in original). Although respondents have vigorously argued that once certain events occur this case will become moot, they have stopped conspicuously short of assuring the Court that those events have occurred. Indeed, they do not argue that the case is moot, but instead argue that the case “will become moot before [the] Court can hear or determine the issues presented.” Id., at 10.
In suрport of the opposition, respondents have attached to their filing a letter written by a consulting geologist who presumably is doing work thаt the preliminary injunction requires petitioners to have done. The letter, like the pleadings, stops short of informing this Court of the completiоn of all work done pursuant to the District Court’s preliminary injunction. Dated November 27, 1984, the letter states that additional review of aerial photographs will be completed in “the next 45 days,” that a draft report by investigators “should be completed in December” to be followed by а final report “by mid-January,” and that the consulting geologists’ report “should be submitted about 60 days later.” App. to Brief in Opposition 1-2.
The last filing in this case was the opposition, filed on December 7, 1984, and that, as I discussed above, went no
Although the Court may believe that the end is so near that it can safely be assumed, the future may well hold surprises for the parties as well as for the Court. A clear understanding of the facts of a case and of their legal implications should be a prerequisite to disposing of a case as moot. This case is a complex one and prior to disposition on mootness the parties should be informed of the Court’s suspicion as to mootness and be asked to provide the Court with facts and arguments. Because this was not done, I dissent.
