The Appellate Division affirmed the summary judgment which the Law Division had entered for the defendant. We certified on the plaintiff’s application. 33 N. J. 110 (1960).
The plaintiff’s complaint alleged in its first count that the Borough of Glen Rock advertised for bids on work to be done on Doremus Avenue, Glen Rock and submitted specifications to the prospective bidders; the plaintiff was the lowest bidder and entered into a contract with the borough on September 6, 1956; in the course of the work the borough requested that the plaintiff perform certain extra services and furnish certain extra materials; and it performed such services and furnished such extra materials for which it claims the sum of $5,877.35 from the borough. The second count repeated the allegations of the first count and sought recovery in quantum meruit. The borough’s answer denied most of the allegations in the complaint and set forth three affirmative defenses which alleged that (1) there had been an accord and satisfaction, (2) if the plaintiff furnished labor and materials for which it had not been paid it did so without lawful authority from the borough and (3) the plaintiff executed a written instrument which had the legal effect of extinguishing its claim. After the filing of its answer the borough moved for summary judgment upon the ground that the plaintiff had “been paid in full for the monies allegedly due.” An affidavit by Mr. Barney Smith, the borough’s Assistant Superintendent of Public Works, was attached to the motion papers and referred to various instruments on file in the Borough Clerk’s office. These instruments included Engineer’s Certificate Fo. 1201 which was dated September 10, 1957 and indicated that the balance due the plaintiff was $14,261.45, voucher dated September 23, 1957 for payment in accordance with Engineer’s Certificate Fo. 1201 and check dated September 23, 1957 in the sum of $14,261.45 to the order of and endorsed by the plaintiff.
In due course the defendant’s motion was argued orally before the Law Division. Counsel for the plaintiff at that time stressed that summary judgment would be improper since there was a material factual dispute. In response to the trial court’s inquiry as to whether the Engineer had authority to authorize the extra services and materials allegedly furnished by the plaintiff, counsel for the plaintiff stated that the borough’s answers to interrogatories acknowledged that “he was authorized” and that in any event he was not “thoroughly prepared” to meet the issue of authorization in view of the fact that the only issue raised by the motion was “whether or not there was an accord and satisfaction, whether the plaintiff was paid for this additional work.” At the conclusion of the argument the trial court expressed the view that it appeared “indisputably from the affidavit of the defendant that the items for which the plaintiff seeks recovery in the complaint has been paid for by the defendant to the plaintiff”; and the summary judgment which was entered thereafter set forth that the pleadings and affidavits
The plaintiff’s appeal from the summary judgment was duly heard by the Appellate Division which did not direct its attention to the issue of accord and satisfaction or payment but stated that in the exercise of its original jurisdiction it had examined the borough’s call for bids, its contract with the plaintiff dated September 5, 1956, the accompanying specifications and the “statements demonstrating the manner and method of financing the payment of the sums to grow due for the improvement of Doremus Avenue.” It noted that the contract price was expressly based on estimated quantities and that the quantities were to be increased or decreased as provided in the specifications which, in turn, provided for “extra or reduction orders” by the Engineer and for “supplementary agreements” in the event of certain plan changes. The Appellate Division found that the plaintiff’s “failure to obtain extra orders or supplementary agreements” barred recovery by it in contract; it also found that the plaintiff was barred from recovery in contract by the absence of any appropriation for the extra work and materials (see N. J. S. A. 40:2-29; 40:50-6) and the absence of any bidding with respect thereto (see N. J. 8. A. 40:50-1). Insofar as the plaintiff’s quantum meruit claim was concerned the Appellate Division expressed the opinion that it was barred by statute (N. J. S. A. 40:2-29) and did not come within any of the exceptions recognized by this court in Hudson City, etc., Co. v. Jersey City Incinerator Authority, 17 N. J. 297, 309 (1955). See Home Owners Construction Co. v. Borough of Glen Rock, 59 N. J. Super. 519 (App. Div. 1960).
The Appellate Division affirmed the trial court’s action but we are satisfied that the meagre record furnished no proper basis for the entry of summary judgment. See
Judson v. Peoples Bank & Trust Co. of Westfield,
17
N. J.
“Summary judgment is recognized as a wholesome device which may avoid needless delay and expense in awaiting and conducting trial; and the expeditious determination of a cause is admittedly an important goal of our present rules of practice and judicial administration. Nonetheless when its attainment involves the deprivation of a full and fair trial on disputed facts, its price comes too high. See Doehler Metal Furniture Co. v. United States,149 F. 2d 130 , 135 (2d Cir. 1945) ; Transcontinental G. P. L. Corp. v. Borough of Milltown, 93 F. Supp. 283, 286 (D. C. D. N. J. 1950). In the Doehler case the court noted the time lost in the federal courts where summary judgments have been improvidently entered and reversed on appeal; similar instances in our state courts are not at all rare. See, e. g., Mitchell v. Wrightstown Community Apartments, Inc., supra [4 N. J. Super. 321 (App. Div. 1949)]; Hodes v. Dunsky, 5 N. J. Super. 333 (App. Div. 1949) ; Lionshead Lake, Inc. v. Township of Wayne, 9 N. J. Super. 83 (App. Div. 1950). In appropriate circumstances premature summary determination might perhaps be avoided by more liberal use of the court's comprehensive power to continue the motion, with conditions if necessary, where pretrial depositions and discovery may serve to remove doubts as to whether there are disputed questions of material facts. Of. Rule 3:56-7; Goldboss v. Reimann, 44 F. Supp. 756 (D. C. D. N. Y. 1942).” 11 N. J. Super., at pp. 4-5.
See also Monmouth Lumber Co. v. Indemnity Ins. Co. of North America, 21 N. J. 439, 449 (1956); McDermott v. Botwick, 38 N. J. Super. 528, 532 (App. Div. 1956).
Although the Appellate Division supplemented the record with various materials relating to the Doremus Avenue project, they furnished no sufficient basis for the entry of summary judgment. The original contract disclosed that the contract price was based on estimated quantities which could be increased or decreased in accordance with extra or reduction orders by the Engineer. If the matter were permitted to proceed to trial the plaintiff’s evidence might well establish, as it has urged before us, that the extra work and materials were within the contemplation of the original contract, that the Borough Engineer had authority to authorize the extra work and materials, and that, under the particular circumstances, further approval in writing from the Engineer was either not required or was waived.
In
Ippolito v. Borough of Ridgefield, supra,
the Borough of Ridgefield advertised for bids for the construction of a sewage disposal plant. Ippolito bid $10,300 for the completed plant, unit prices for contingent extras, and cost plus 15% for work on which no unit prices were bid. He was awarded the contract and duly entered upon his work. In the midst of the work the borough decided that the nearly completed foundation would be unsafe and ordered extra work for which no unit prices were provided in the
In the course of his opinion for the Court in
Ippolito,
Chancellor Walker relied on cases elsewhere which allowed recovery for extra work despite the absence of any bidding with respect thereto where it appeared that there was no effort to evade the bidding statute and the extra work was merely incidental to the original contract or was necessitated by an unforeseen emergency; the Chancellor expressed the view that the municipality was adequately protected since, under the court’s holding, a jury would be called upon to decide "whether the new work was occasioned by an unforeseen emergency or was but an incident of that provided for in the original contract, or was a mere effort to evade the statute.” See 94
N. J. L.,
at
p.
104. In
Pyle v. Kernan, supra,
the court noted that "a reasonable degree of latitude is essential to an intelligent and efficient administration of public works” and that "if the rule were otherwise, public interests would be greatly jeopardized in the event of emergencies and unforeseen obstacles in construction work.” 36
P. 2d,
at
p.
584. In
Michigan City v. Witter, supra,
the court referred to the fact that conditions during the course of the work disclosed that the original specifications were defective and expressed the view "to hold that under such circumstances the municipality, or the agents placed in charge of the construction, were without power to correct the mistake would be the height of folly,” and it concluded that if “the power to make necessary changes does exist, and the power is exercised at added cost and expense to the contractor, it would be unjust to deny him compensation therefor.” 34
N. E. 2d,
at
p.
135. See
Thomsen-Abbott Construction Co. v. City of Wausau, supra,
It must be borne in mind that the original contract was duly preceded by bidding and appropriation in strict accordance with the applicable statutes (see
N. J. S. A.
40:2-29, 40:50-l, 40:50-6), in that respect the case at hand is distinguishable from the cases relied upon by the Appellate Division such as
Slurzberg v. City of Bayonne, 29 N. J.
106 (1959) and
Hillside Tp., Union County v. Sternin,
25
N. J.
317 (1957). See also
Bauer v. City of Newark,
7
N. J.
426 (1951). The bidding and appropriation statutes embody sound public policy in the furtherance of efficient governmental administration and in “the avoidance of waste, extravagance and ill-considered spending.” See
Slurzberg v. City of Bayonne, supra,
29
N. J.,
at
p.
115. The statutes must, of course, be faithfully observed and any attempt to evade them must be stricken down. But they must also be construed and applied fairly and sensibly so as to further rather than defeat the legislative goals. In the course of a construction contract,
bona fide
emergencies may well arise and incidental alterations may well be required. Where the resulting additional expenditures are reasonable and are conscientiously viewed as being in fulfillment of the original undertaking rather than as departing therefrom
(cf. Hanna v. Board of Education of Wicomico County,
200
Md.
49, 87
A. 2d
846, 848
(Ct. App.
1952)) it would clearly be contrary to the public interest to halt the undertaking and call for bidding with respect to the additional work entailed by the emergency or the incidental alteration. It may fairly be assumed that such course was not within the contemplation of the Legislature. See
Ippolito v. Borough of Ridgefield, supra,
94
N. J. L.,
at
p.
103;
cf. Antieau, The Contractual and Quasi-Contractual Responsibilities of Municipal Corporations, 2 St. Louis U. L. J.
230, 251 (1953). Similarly it may fairly be assumed that the Legislature did not contemplate the halting of the undertaking pending a further
Finally we come to the issue of whether the absence of written orders relating to the extra services and materials necessarily precluded recovery. The plaintiff does not suggest that it ever obtained written orders but it does urge that further approval in writing from the Engineer was either not required or was waived. It asserts that during the course of its work it was discovered that the road base was in a very unstable condition and the Borough Engineer and Borough Inspector advised that it would be necessary to remove the unstable element and replace it with a 2% inch stone rather than with the normal sub-base fill; that the Engineer and Inspector notified it to proceed and stated that the borough would pay for the extra work; that acting in good faith and in reliance upon the Engineer’s advice it performed this and other incidental extra work and followed the course of procedure suggested or directed by the Engineer for obtaining payment from the borough. Although in
Guizzette v. Katrek,
124
N. J. L.
461, 464
(Sup. Ct.
1940), Justice Case noted that mere performance of extra work does not give rise to the waiver of a construction contract provision requiring that the authority for the extra work be in writing, he did not in any wise question that the writing requirement may be expressly or impliedly waived by the clear conduct or agreement of the parties or their duly authorized representatives. See
Headley v. Cavileer,
82
N. J. L.
635, 637
(E. & A.
1912);
Fortunato v. Cicalese,
93
N. J. L.
461
(E. & A.
1919);
Guenther v. Moffett,
77
N. J. L.
206
(Sup. Ct.
1908);
cf. Johnson v. Hospital Service Plan of N. J.,
25
N. J.
134, 141 (1957);
Eeversed and remanded.
For reversal and remandment—Chief Justice Weinteaub, and Justices Jacobs, Feancis, Peoctoe, Hall and Schettino—6.
For affirmance—Hone.