• The action is based on a subscription, of which the following is a copy:
“ Omaha, Nebraska, March 17th, 1880.
“ We, the undersigned, agree to pay to Messrs. Steele, -Johnson & Co., of Omaha, Neb., the sum set opposite our respective names, upon the comрletion and occupancy by*653 them, as wholesale grocers, of a three-story brick building, 66 feet by 120 in size, on lot 4, block 150, in Omaha, Douglas county, Nebraska; said building to be completed and occupied by them on or before the first dаy of November, 1880; said building to have an outside appearance-equal to the Burlington & Missouri R. R. building on the corner of Farnam and 10th streets, Omaha, Neb.
J. Strickler....................................,.........$100.00
G. W. Homan........................................... 200.00
J. S. McCormick......................................... 250.00
Elnathan Mills.......................................... 75.00
Geo. B. Lalte............................................ 75.00
Geo. W. Doane.......................................... 75.00
First National Bank, by H. W. Yates.............. 50.00
W. W. Lowe............................................ 50.00
O. C. Housel............................................. 50.00”'
The plaintiffs below (defendants in error) allege in their petition, in substance, that on the 17th of March, 1880, they were wholesale grocers in Omaha, and that the defendant below was the owner of certain real estate situate near lot 4, block 150, in said city; that said plaintiffs were about to erect a large and expensive building, but had not then decided on a location; that the defendant, on that day, in order to induce the plaintiffs to locate said building on lot 4, block 150, and in consideration of like agreements of and subscriptions of other parties, also lot owners or interested in real estate in said city, subscribed and promised to pay the plaintiffs the sum of $200 for 'that purpose, and that, relying upon said subscriptions, the plaintiffs located and erected said building on said lot, and have duly performed all the conditions of said contract on their part to be performed; and that after said building was completed and occupied by the plaintiffs they demanded payment of said sum, which was refused.
The answer of the defendant below admits the partner
1st. That the verdict is not sustained by sufficient evidence.
2d. That the verdict is contrary to law.
3d. That the court erred in refusing to give the instructions asked by the defendant.
4th. That the court erred in instructing the jury to find for the plaintiffs.
In the briefs of the plaintiff in error no mention is made of error, either in giving or refusing instructions. That ground, therefore, may be considered as abandoned. The only question, therefore, to be considered is, whether or not the evidence sustains the verdict. There is no conflict in the tеstimony, and it shows the following facts: That in the spring of 1880 the plaintiffs below were looking for a location; that they had three in view, viz., lot 4, block 150, ■a lot on the corner of 10th and Harney streets, and one on the corner of 9th and Farnam strеets; that the price asked for lot 4, block 150, was $8,000. The lot, it seems, was owned by parties in New York, and as Mr. Johnson was going thereon business, he seems to have been authorized by his firm to purchase it, at not to exceed $6,500. The testimony of a member of the firm upon that point is as follows: <c I think we made an offer first of six thousand dollars. Mr. Johnson went to New York on business, and expected to see the administrator of the estate while there. It was understood between him and his рartners that we were to go as high as $6,500. We thought that was the full value of the property; and if we failed to get that, we had those
It is claimed on behalf of the plaintiff in error that there is no mutuality in the сontract, and certain cases are cited to sustain the position, which will be noticed in their order. First, Turnpike Co. v. Collins,
In Academy v. Davis,
In Academy v. Gilbert,
In Commissioners v. Perry, 5 Ohio, 57, the contract was as follows:
“We, the undersigned subscribers, do hereby promise to pay the commissioners of the canal fund of the state of Ohio, for the use of said fund, the sums severally annexed to our names, in three several equal installments, the first on January 1, a.d. 1827; the second on January 1, A.D. 1828, and the third and last on January 1, a.d. 1829, upon condition that the canal be located on the east side of the Cuyahoga river from the lower rapids to the village of' Cleveland.
“Cleveland, December 6, 1825P
The contract was held to be valid. In that case the legislature had authorized the commissioners to recеive
In Fremont Bridge Co. v. Fuhrman,
But it is said that the building was not completed and occupied November 1st, 1880, and therefore the defendant below is not liable. An examination of the contract shows that the sums were to be paid on “the completion and occupation of the building.” In the next sentence it is stated that the building is to be completed and occupied on or before November 1st, 1880. The rule in regard to time aрpears to be this: That where there is nothing special in the nature of the property or of the purposes for which it was intended, although a particular day may be fixed for the completion of the contract, yet the general object being the accomplishment of the purpose for which the promise was made, viz., the completion of the contract, the particular day named is merely formal.
A different rule obtains where the nаture of the property or the purpose for which it was intended is of such a character as to make time material. In this case the ob
3d. It is claimed that the actiorx should have been to recover on a quantum meruit and not uрon the contract, that when the suit is upon the contract alleging compliance therewith everything is essential in the contract to authorize a recovery. Pax’sons states the rule in such cases as follows: “ If the time be set in which certain work is to be done it is not in general so far of the substance of the contract that if the work be done, but not until some days later, no compensation will be recovered; but an action for the price will be sustаined leaving the defendant to show any ixxjuxy he has sustained by the delay, and use it in reduction of damages by way of set-off,” etc. 2 Parsons on Contracts (5 Ed.), 660. This, we think, states the law correctly. The few days which elapsed after the time fixed for thе completion and occupation of the building and the time in which it was actually completed and occupied do not in our view affect the right to recover. The defendants’ attorneys in their brief virtually admit this, but say the actiоn should not have been upon the contract. This
It is apparent that substantial justice has been done, and the judgment is affirmed.
Judgment affirmed.
