This action was begun in justice’s court. Plaintiff declared orally on the common counts, especially for goods, wares, labor, and merchandise, filing a bill of particulars charging defendant with items aggre
At the commencement of trial in the circuit, the court, against plaintiff’s objection “because of the competency of the items,” permitted defendant to amend his bill of particulars by increasing the item for altering the heating system from $150 to $371.48, previous notice having been given of the proposed motion for leave to amend, with a further itemized statement of the charges comprising the total of $371.48. On allowing the amendment the court said:
“The plaintiff having announced himself, through his counsel, as ready for trial on calling the docket on the first day of term, with full knowledge that the motion has been made, would be pressed, I think he cannot be heard now to object to the amendment.”
Error is assigned on this ruling of the court. Notice had been given of this motion to amend, and no surprise was claimed or objection made to the case proceeding to trial after the motion was granted. The amendment neither surprised plaintiff nor deprived him of any sub
Error is assigned on the rulings of the court in admitting in the first instance, refusing to strike out, refusing to give plaintiff’s requests in relation thereto, and leaving to the jury testimony offered by defendant in support, of his claim of recoupment relative to the excessive amount of coal alleged to have been consumed by the heating plant plaintiff installed. The total of plaintiff’s claim was for a balance of $336.07 and interest amounting to $16.80. The only matter disputed and put in issue by defendant was the heating and plumbing contract
There were two distinct items of recoupment urged against plaintiff’s balance by reason of failure to properly perform the contract. One was the cost of altering the heating system to conform with the specifications and make it operate as guaranteed, amounting to $371.48. This the jury allowed and deducted from plaintiff’s full claim, rendering a verdict for the balance in his favor. The other item was for excessive coal used, amounting to $563.50, which they manifestly rejected and disallowed. In view of this result, the ruling of the court was harmless error. It was said in Commercial Bank v. Chatfield, 12
“ Complaint is made of the refusal of the court to strike out an item of $1,000. It clearly appears that the jury disallowed this item, and, if it was error to deny the defendant’s motion to withdraw this item from the jury, it was error without prejudice.”
The only question in the case decided adversely to the plaintiff was defendant’s counterclaim of recoupment for
It is urged that defendant cannot enlarge his claim after action is begun, as he has done by his amended bill of particulars, based on repairs made subsequent to that time, and it is asked if—
“After payment is refused, and suit begun for recovery of the same, whether the defendant can then proceed to demolish the outfit, reinstall it, make his bill as large as he pleases, all of which is contracted after suit is begun for the original claim, and then come in and offset it against plaintiff’s bill ? ”
The performance or breach of the contract must have occurred, and the right to recover for performance, or by recoupment for nonperformance, must have arisen before the action was begun; but the right to recoup does not depend on whether or not the repairs were made either before or after commencement of action. If work was
Defendant claimed, and introduced testimony tending to show, that the heating system was improperly installed and the work not according to the contract; that plaintiff promised repeatedly to remedy the defects, and afterwards did some work to that end, but unsuccessfully; that, under plaintiff’s repeated promises, defendant refrained from having others make the necessary alterations until this suit was brought, after which he employed competent men to do it; that, while the material in the system was sufficient and good, it was necessary to do much of the work of installation over again, and, after it had been done according to the specifications of plaintiff’s contract, the plant worked successfully and economically. There was much testimony as to what the trouble was, it being claimed by defendant that the pipes had an improper slant and contained numerous pockets which prevented proper circulation; that the furnace was not put together right, the back grates being in front and front grates at the back, and a general inharmonious installation prevented successful operation. On the other hand, and in direct contradiction of this, it was the contention and testimony of the plaintiff that the system was, in the first instance, perfectly and properly installed by him according to specifications of his contract, that he tested it thoroughly and it operated successfully, and if it subsequently failed to do so it was owing to bad management and improper firing. These questions were square issues of fact properly left to the jury.
Error is alleged on the refusal of the court to grant a
Taking the record as a whole, we find no prejudicial error in the rulings of the court which require a new trial.
Judgment is affirmed.
