| Ky. Ct. App. | Oct 22, 1908

Opinion of the Court by

Judge Barker —

Affirming.

This is an action for the breach of an alleged contract between appellee and appellant for the sale and delivery by the former to the latter of 4,000 cubic yards of broken rock to be used in constructing lock and dam No. 6 in Green river. Appellee alleged in his petition that appellant, a corporation, had secured the contract from the United! States government to construct the lock and dam in question, and that in the construction of this work is needed about 4,000 cubic yards of broken stone of dimensions not less than one-half cubic foot ñor larger than what a man • could handle; that he entered into a contract with appellant by which he undertook to furnish it with the stone, and it agreed to pay him therefor 60 cents per cubic yard delivered on barges in Green river; that, after making this contract with him, the appellant wilfully and arbitrarily broke it, ahd refused to permit him to go on with it. The damages were laid in the petition at $1,250, and were said therein to consist of $250 expended in opening up the quarry in order to get out the stone, and $1,000 which the appellee could have made in profit had he been allowed to execute his contract as made with appellant. The appellant in its answer denied the existence of the contract, and this was the real issue between the parties, although there are several questions dis*55cussed in the briefs. A trial of the case resulted in a verdict in favor of appellee for $500 and from the judgment based upon that verdict this appeal is prosecuted. The evidence shows without question that the appellant agreed with the appellee for the purchase by it of the 4,000 cubic yards of broken stone at the agreed price of 60 cents per cubic yard. This contract was not only agreed to in all its terms, but was dictated to the stenographer of appellant, with instructions to him to write it out in duplicate and send by mail to appellee, who was to sign both and return one copy to appellant. Several days after this was done, A. Hollerbach, who seems to have been the active manager of appellant company, went up to appellee’s quarries from which' the rock was to be taken, and inspected them with appellee. While there, appellee asked Hollerbach why the written contracts had not been sent down as agreed upon, whereupon Hollerbach expressed surprise that he had not received them, and said: “You will get them by Tuesday” (it being then Sunday). Hollerbach left the quarries, and went on to his place of business, and appellee heard nothing further for several days, whereupon he wrote to appellant, inquiring why the contracts had not been sent down, and received a letter in reply that appellant had made other arrangements to get the stone it needed. Appellee then instituted this action.

The mere fact that the oral contract was tó be afterwards reduced to writing does not render it unenforceable. Bell v. Offutt, 10 Bush, 632" court="Ky. Ct. App." date_filed="1874-02-23" href="https://app.midpage.ai/document/bell-v-offutt-7379300?utm_source=webapp" opinion_id="7379300">10 Bush, 632; Mattingly v. Springfield F. & M. Ins. Co., 120 Ky. 768" court="Ky. Ct. App." date_filed="1904-12-08" href="https://app.midpage.ai/document/mattingly-v-springfield-fire--marine-ins-7135935?utm_source=webapp" opinion_id="7135935">120 Ky. 768, 26 Ky. Law Rep. 1247, 83 S.W. 577" court="Ky. Ct. App." date_filed="1904-12-08" href="https://app.midpage.ai/document/mattingly-v-springfield-fire--marine-ins-7135935?utm_source=webapp" opinion_id="7135935">83 S. W. 577. If the minds of the parties had met, and nothing else was to be agreed upon, the mere fact that the parties were to reduce *56their understanding to writing does not militate against the right of either to sue for a breach of the oral agreement. The testimony introduced by plaintiff (appellee) fully sustains his contention, and this is in no substantial respect disputed or contradicted by the appellant, or its witnesses, except that it alleged and undertook to prove that, after the contract was agreed on between appellee and Hollerbach, appellee said to the stenographer that he wished a different clause inserted as to the dimensions of the stone, and that, if this was not done, he would not sign it. This was denied by appellee, and that question was submitted to the jury in the instructions of the court, and found adversely to appellant.

Nor do we think the court erred in not submitting to the jury the question as to whether or not appellee had prepared and tendered a bond with surety conditioned for the faithful performance of the contract. Appellant’s evidence tended to show that a bond was to be given, and, while appellee denied that there was such an agreement, he admitted that he sometimes gave bond for the prompt performance of his contracts, and would have had no objection to giving bond for the performance of the contract under consideration. Appellant did not deny that it agreed upon the terms of the contract as alleged by appellee, or that these terms were dictated to the stenographer and taken down by him in shorthand; but it insists that there never was a contract, or, if there was one, it was rescinded by the demand of the appellee for the modification thereof. It does not deny that it made arrangements for the obtention of the desired amount of broken stone from another party, and that after it was impossible for it to carry out its contract with appellee. In other word's, it does not dispute *57that, if there was a contract between it and appellee, it broke it. Assuming this to be true, it was entirely immaterial whether there was a bond executed. Appellant did not allow the time for the execution of the bond to arrive, because, before that time, it ’".ade a contract with another party for the stone, and so notified the appellee.

We think the court correctly held that the question between the parties was whether or not there was a contract as claimed by appellee; and, if so, the amount of damages appellee sustained by reason of the breach. Hoilerbach’s own testimony established appellee’s contention of the existence of the contract, and his only excuse for the breach was that his stenographer had told him when he came hack from the quarries that appellee had said to him (the stenographer) that, unless there was a modifying clause inserted in the contract, he would not sign it. Being told this, he says he immediately, without notifying the appellee, made a contract with a different party for supplying the stone that appellant needed. Hoilerbach’s position in this matter is not a very enviable one. He knew that what his stenographer told him was not correct, because he had been at the quarries with appellee since the supposed conversation between the stenographer and appellee had taken place, and he knew that appellee was preparing to go on with the contract, and had there asked him why the written contract had not been sent to him, and he knew that he had promised appellee that the writing should go to him at least by the following Tuesday, and yet, knowing that appellee considered that he had a contract with appellant, and was going on at some outlay to prepare to execute it,, he, without any notice to appellee, made a contract, as said before, *58with another party; and, as he states, at a higher price.

We do not think the first instruction of the court assumes that there was a contract between appellant and appellee. If this were true, it would be erroneous, because the existence of the contract was the real issue between the parties. Instead of assuming the existence of the disputed contract, the court expressly told the jury that if they believed from the evidence that the appellee and appellant made a contract as set out in the petition, and appellant broke it, and that the appellee was ready and willing at all times to execute it, then h.e was entitled to damages from the appellant.

The court did not err in not instructing the jury that it was the duty of the appellee, even if there was a breach of the contract, to use reasonable diligence to sell the stone contracted for to other parties. The principle for which counsel for appellant contend has no application to a contract like the one under discussion. It is true, where there is a contract for personal services, and there is a breach, the-party whose services are to be engaged may not sit down and supinely permit the amount of his damages to grow. It is his duty to seek employment elsewhere, and the other party is only liable to the extent of the injury after the exercise of ordinary diligence by the complainant to obtain other employment still leaves him a sufferer by reason of the breach. In the case in hand the appellee had a rock quarry, and, although it might be true that he could have sold 4,000 cubic yards of rock to another party, that would not have diminished his damages in not being allowed to carry out his contract with appellant, because he' was entitled, if he could, to sell all the rock in *59his quarry; and it in no wise minimized the damage's he may have sustained by the breach of appellant’s contract that he might, perchance, have sold 4,000 yards of broken rock to some one' else. This i» quit*» different from a contract for personal services. There the contract cannot be performed for two different parties, and, when the employer refuses to carry out his contract for the personal services of the servant, the latter must look for another employer, and thus reduce the damages, arising from the breach, as much as possible. We do not mean to be understood as limiting the application of the principle of avoidance of damages to breaches of contracts for personal-service ; on the contrary, the rule is of much broader application, and it would, perhaps, not be going too far to say that the duty of those complaining of violations of contracts to minimize their damages as much as the exercise of reasonable diligence will accomplish is the general rule appertaining to the right to recover damages therefor. The complainant should reduce his damages whenever the principle can be applied without sacrificing any substantial right. A fair illustration of the general application of the rule may be found in the supposition that the breach of the contract under discussion had been by appellee’s refusing to deliver to appellant the stone contracted for. It would in the supposed case have been the duty of appellant to go out into the market and buy the stone, and it could only hold appellee liable for the difference between the contract price and what it had to pay for the stone on the market. This, from the very nature of the case, would cover all the damage it sustained by the breach of the contract. But the same principle is not applicable to the breach of contract complained of in this record. Appellee was *60entitled to enjoy the benefit of the profits of his contract with appellant, and, if he could have made as beneficial a contract with another, he was entitled to the benefits of that' also. In other words, he was entitled to carry forward as many such contracts as he could make, and, if he succeeded in making more than one, he was entitled to both profits. Receiving the profits of one such contract would not tend to recoup his loss by reason of the breach of another. Sedgwick on Damages (8th Ed.) section 608. It was not necessary for the appellee to expressly offer to go on with the contract after the breach. He was informed by the appellant that it had contracted for the stone from another party, and it was therefore useless for him to. make a formal tender of the stone to it. The law does not require the doing of a useless act.

Upon the whole case no substantial error was committed against appellant, and the judgment is therefore affirmed.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.