Hollenback v. HandHollenback v. Hand
The Washington' & Berkeley Bridge Company, a West Virginia corporation, as owner, undertook the construction of a bridge across the Potomac river near AVilliamsport, Md. The piers were to be of concrete from 20 to 40 or more feet in height and were designed to carry a steel superstructure of great weight and during construction heavy machineiy for placing it and cars after construction. It was, of course, necessary that these piers should be strong and well constructed of suitable material well and thoroughly mixed and placed properly and left to harden or set at least a.suitable time before placing a load thereon. The defendant company owed a duty to all who should go upon the piers while placing the superstructure to do its work properly and efficiently in all respects, and, if it knew the materials furnished for the construction of such piers were unsuitable and made a weak and dangerous struc
On the morning of December 16, 1908, while Hollenback, with other employés of the Pennsylvania Steel Company, was engaged in placing the iron beams extending from pier 9 to pier 10, on pier 10, and after same had been partially placed, the top portion of pier 10 gave way, that is, the girder or beam placed thereon on the upstream side cut or sheared right down through the upper part of the concrete pier and the girder, crane, traveler, and other ironwork with the men thereon, including Hollenback, the deceased, were precipitated to the bed of the stream some 40 feet below, and Hollenback received injuries from which he died.
The contention of the plaintiff was and is that the concrete was of improper material, improperly mixed, and weak and rotten owing to the negligence of the defendant company in using same and in constructing such pier, and that its negligence was such as to charge it with notice of such weakness, and that it turned this pier over or allowed same to pass to the hands of the Pennsylvania Steel Company for the uses and purposes intended knowing of such weakness, improper construction, etc., or legally charged with notice thereof, without notice to that company, and hence was and is responsible for the consequences that followed. The contention of the defendant was and is that the concrete was all right, composed of suitable material, properly mixed and placed, but that the weather conditions were
It is undoubtedly true that this concrete was not first class, or such as would have been produced by using sand such as was called for by the strict terms of the contract; but there was evidence that it was tested, accepted, and used,- all the contracting parties concurring in its use. Whether or not the concrete used in completing pier 10 before the accident was properly and sufficiently mixed was a disputed question. The evidence was not clear that the concrete used to repair and restore the top of pier 10 after the accident was mixed in the same manner as was that used in its completion prior to the accident. However, the fact that this stone, sand, gravel, and cement
Pier 10 was completed December 9th and gave way December 16th, or seven days later, while the load was being placed. The pressure of the load carried was about 78 pounds per square inch. The temperature during this time ranged from 24 to 57 degrees above zero. Subsequent to the injury a test of concrete made of these same materials, under less favorable atmospheric conditions, showed a compression strength at the end of seven days of 758 pounds per square inch. This concrete was subjected to a pressure of 5,000 pounds, and while under pressure was struck a blow with a sledge hammer and again tested, when it showed a compression strength of only 609 pounds per square inch, which indicated that the blow weakened the concrete. Undoubtedly it would not have withstood this pressure if improperly mixed. The plaintiff contends that this evidence shows conclusively that the concrete which gave way was improperly and negligently mixed, and that this negligence was the cause of the giving way of the pier; that it gave way under a pressure of 78 pounds per square inch, when if properly mixed it would have sustained a pressure of at least 600 pounds per square inch, leaving out all questions of the improper character or quality of the materials. But we have
“The true rule and. the reasons for it were well expressed in Morse v. Minneapolis & St. Louiá Railway, above cited, in which Mr. Justice Mitchell, delivering the unanimous opinion of the Supreme Court of Minnesota, after referring to earlier opinions of the same court the other way, said: ‘But on mature reflection we have concluded that evidence of this kind ought not to he admitted under any circumstances, and that the rule heretofore adopted by this court is on principle wrong; not for the reason given by some courts, that the acts of the employés in making such repairs are not admissible against their principals, but upon the broader ground that such acts afford no legitimate basis for construing such an act as an admission of previous neglect of duty. A person may have exercised all the care which the law required, and yet, in the light of his new experience, after an unexpected accident has occurred, and as a measure _of extreme caution, he may adopt additional safeguards. The more careful a person is, the more regard he has for the lives of others, the more likely he would be to do so, and it would seem unjust that he could not do so without being liable to have such acts construed as an admission of prior negligence. We think such a rule puts an unfair interpretation upon human conduct, and, virtually holds out an inducement for continued negligence.’30 Minn. 465 , 46S [16 N. W. 358 , 359].
“The same rule appears to be well settled in England. In a case in which it was affirmed by the Court of Exchequer, Baron Bramwell said: ‘People do not furnish evidence against themselves simply by adopting a new plan in order to prevent the recurrence of an accident. I think that a proposition to the contrary would be barbarous. It would be, as I have often had occasion to tell juries, to hold that, because the world gets wiser as it gets older, therefore it was foolish before.’ Hart v. Lancashire & Yorkshire Railway, 21 Law Times (N. S.) 261, 263.”
See, also, Corcoran v. Village of Peekskill,
But here the defendant offered evidence of the subsequent repairs and their character and of the material used, not to prove negligence in the original construction, but to show that the owner used the same material in the same way for the same purpose,' and that it made good and sufficient concrete when allowed to stand a sufficient length of time before being subjected to a load. The evidence did tend to show that the plaintiff’s intestate may have been negligent in going
Could not a defendant, sued for negligence in xnaking and selling weak and ixisufficient wagon wheels whereby the purchaser and user was injured, the insufficiency and weakness of the timber used being charged, show in defense that he' had used the same timber for years in making such wheels both before and after the accident, and that they had been actually used and had proved strong and sufficient? And could not the plaintiff show in proving his case that other wheels of the same size made of the same timber by the defendant had broken, gone to pieces, and been shown by actual use both before and after the accident in question to be dangerous because of the weakness of the timber? Or would mere opinions be substituted for these actual facts?
Going on pier 10 prematurely was not necessarily contributory negligence ; but it may have been the sole cause of the giving way of the pier. Here, until we come to the fact that the Pennsylvania Company placed the superstructure after the accident, the reason of the rule above referred to is absent. The defendant gave the evidence as> to the reconstruction of this pier and the materials used and the lengthi of time the concrete was allowed to stand before being subjected to a load for the purpose of showing the good character and sufficiency of the material. The reconstruction of the pier alone was done, not by the defendant company, but by the owner, the Berkeley Company, and could not operate as an admission of the defendant company that it was negligent in the original construction, or as an admission by the Pennsylvania Steel Company, or its employe, that it was negligent in going on the pier at the end of seven days after its completion. Mere reconstruction was not a fact tending to show that this material was proper and sufficient when properly mixed, but proof that if it was allowed to stand three to six weeks, and that it was then hard and solid, tended to show that it required more than seven days in. which to harden or set sufficiently to carry a load. Proof of this fact of waiting three to six weeks after the accident also tended to show that the Pennsylvania Steel Company with its men commenced operations on pier 10 too soon prior to the accident, and, as the proof also
If A. is sued by B. to recover damages for negligence in supplying improper and defective sand and cement or lime for the mortar used in' laying a high wall in which B. was at work placing timbers, whereby the wall was made weak, and hence crumbled and fell, causing the injury, could not A. show that the sand and cement were strong and suitable for the purpose, and that the wall fell because of plaintiff’s negligence in going thereon with timbers too soon and while it was •green, by proving that after the accident the same materials were used by defendant to reconstruct the wall, ánd that after standing a suitable time the wall was strong and bore the load without showing weakness ? • But. would it be competent for the defendant to show that the plaintiff himself waited a longer time than at first before going on the reconstructed wall ?
In the case at bar there was no change in material or mode of construction of-the pier by any one when the pier was reconstructed. The only change in operations was that, after the pier was reconstructed by the owner with the same material in the same way as before, it was by the Pennsylvania Steel Company allowed to stand some four to six weeks before being subjected to a load. Assume that the Pennsylvania Steel Company is shown by this evidence to have waited from four to six weeks before going on the reconstructed pier, and that thereby the jury may have been led to conclude it admitted that it went on the pier too soon in the first instance, was the evidence any the less admissible P It may be argued the Pennsylvania Company was not negligent in the first instance; but, in view of what happened on the 16th of December, it- had the right to use the precaution of waiting from four to six weeks, instead of seven days, before placing the load on the reconstructed pier, and that admitting the evidence in question was allowing a subsequent act of precaution taken by the Pennsylvania Steel Company in the light of experience and added knowledge to be used against the employé as an admission by said company that it went on pier 10 too soon or negligently in the first instance. The admissions of the Pennsylvania Steel Company made after the accident and injury, either by words or by acts, were not admissible against the administrator of Hollenback. If this may have been the effect of the admission of this evidence that the Pennsylvania Company waited three to six weeks as stated, and its use was not properly limited by the court, and its reception was objected to properly, then the ruling admitting the evidence was prejudicial error, and the plaintiff is entitled to a new trial. The question of the negligence of the Pennsylvania Steel Company was in the case and was brought in by the defendant company, which contended that the Pennsylvania Steel Company was negligent in going upon the pier with this heavy load at the end of seven days, and that its negligence or the premature
“The defendant has given evidence tending to show that the concrete was composed of proper and suitable materials, sand, cement, and broken stone, which were suitably, properly, and sufficiently mixed and properly placed in the forms, and that such forms were left in position the necessary length of time: but that, on account of weather conditions, cold or freezing weather conditions, the concrete had not sufficiently hardened or set when subjected to the weight and pressure placed thereon, and that the weight was placed thereon prematurely and negligently by the Pennsylvania Steel Company, and that, for this reason, it was not safe lo put the weight and pressure, to which it was subjected, upon it; and that, because of this premature subjecting of pier 10 to this great weight and pressure, the negligence of the steel company, it gave way and caused the accident and injury to the plaintiff’s intestate and his consequent death.
“If, gentlemen, you find this to be the truth of the case, then the plaintiff cannot recover in this action, for, in such ease, the injury to the plaintiff’s intestate, and his consequent death, would not he the result of the negligence of the defendant company, but the result of negligence or want of care or of poor judgment on the part of the Pennsylvania Steel Company.”
When the offer of proof by the witness Angle came as to what, was clone after the accident by way of reconstructing pier 10, the materials used, etc., including the time that was allowed to pass before going on the reconstructed pier with the superstructure, strenuous objection was made and repeated. The court in ruling on the objections, after stating the facts the defendant sought or was seeking to prove, said:
“Now the defendants are seeking to show, as I understand, they took off the top, and they not only found it hard, but he (witness) says they had to chisel it, and, when they did they conldn’t break the stone up, they had to cut through the stone. Now they seek to show, as I understand, what they are at, they have got some evidence to that effect, that they took the same sand from the same place, the same quality and character, the same foreign substance in that there was in that first used,' the same stones from same quarry, broken with the same crusher, and the same cement, same quality, mixed it in the same proportions, and in the same manner, and put it up there and let it stand longer than seven days, then I suppose they intend to show that it was firm, hard, and all that sort of thing; show that it is proper material, and that if it was put up there and let alone that it will harden and be of sufficient strength. They seek to show from that that this injury occurred because of the negligence of the Pennsylvania Steel Company in not properly inspecting that pier and in going on it prematurely when it was green and endangered the men in their hurry. Now that is about the sum and substance of what they are driving at, as I understand it.”
The court then made other remarks on the subject and concluded:
“So in that view I overrule the objections and give them (plaintiff) an exception.”
There was a plain statement by the court of the evidence offered or sought to be introduced and of its purposes, and one of such purposes was to show that the accident and injury were the result of the negligence of the Pennsylvania Steel Company, and one of the facts to be proved ruled upon was that the reconstructed pier was allowed to stand more than seven days before placing the superstructure thereon. The court evidently did not intend to rule, and there was no ruling, that such delay in placing the superstructure subsequent to the accident could be used or admitted as evidence of an admission
“Upon whatever pretense such evidence is put into the case, it is generally used to mislead the jury. It is sometimes accepted by them as an admission of negligence, and its natural tendency is undoubtedly to influence them in that direction.”
It was held prejudicial error to admit the evidence, as it was not essential for one of the purposes for which admitted, to show control over the highway, and had no tendency to show the possession by the commissioner of funds at the time of or prior to the accident complained of.
I think the Circuit Court of Appeals, in view of its decision in Barber Asphalt Paving Company v. Odasz,
“Q. How long after the pier was reconstructed before the Pennsylvania Company — oh, you say the Berkeley Company suspended work in December? A. Yes, sir.
“Q. After the completion of this pier? A. No, sir.
“Q. How long after the completion of this pier was it, if you can tell the jury, before the company went upon it? A. Dour or five weeks.
“Q. Just a minute, let me finish my question, to work?
“Mr. Matterson: What pier have you reference to?
“Mr. Borst: Pier 10.
“The Court: After it was repaired?
“(Objected to as illegal, improper, not binding upon this plaintiff, anything done subsequent 'to the injury. Objection overruled. Exception.)
“The Court: He may show how long they waited before they went on.
“A. Eour or five weeks.”
I think this presented the question in such shape that the ruling was clear error. The court said:
“He (defendant’s counsel) may show how long they (Pennsylvania Company) waited before they went on.”
True this preceded the examination of Angle before referred to, but it was not necessary to repeat the objection which I think sufficiently raised the question presented here.
In the case last referred to the witnesses were asked whether they could tell a way by which the accident could have been prevented. One witness in answer said:
“There is a platform made there now, but it was not there then, to prevent the car from falling.”
And another witness in answer said:
“The tramway is made different from its construction when Odasz was killed.”
When questions were directly asked as to whether or not changes or improvements had been made after the accident, objection was made
“The judge excluded the questions when directly and formally asked for the purpose of showing negligence before the accident; but the quoted answers slipped in, ostensibly in reply to the question whether the track was capable of a construction which would prevent accidents. The testimony was wanted by the'plaintiff’s counsel for the purpose of proving negligence. The answers showed the jury that changes had been made after the accident for the purpose of preventing sirhilar calamities in the future. A plausible but untrue inference from this class of testimony is apt to be that the subsequent act, for the purpose of securing perfect safety in the light of past experience, is an admission of a previous omission to take proper precautions, and has an effect to call the minds of the jury away from the real issue, which is that of reasonable, but not extraordinary, care at the time of the accident, in view, among other considerations, of previous and universal experience.”
However, during the examination of the witness Cullen, as we have seen, the question was raised, and the court said in overruling the objection:
“He may show how long they (the Pennsylvania Steel Company) waited before they went on.”
This referred to the going on the pier after its reconstruction with the superstructure. In view of all that took place, I am of the opinion the objections made were sufficient, not waived, and that prejudicial error was committed which demands a new trial. See, also, Dale v. D. D. & W. R. Co.,
It is true that the evidence was not offered to show negligence on the part of the Pennsylvania Steel Company, or of Hollenback, and there was no suggestion in the objection that it might be so used and was for that reason inadmissible; but the fact remains, as we have seen, that it was immaterial who or what company waited three to six weeks before going on the reconstructed pier after the accident, and it was dangerous to permit proof that the Pennsylvania Company, who went on the pier at the end of seven days before the accident, waited from three to six weeks after the accident before going thereon. The jury could have and may have used this fact as an admission of negligence made by that company after the accident and against the administrator of Hollenback. The jury was hot told they must not so use or consider it.
The motion to set aside the verdict and for a new trial is granted, and the order will be entered as of the date of the close of the trial; the term, having been held open for the purpose of the motion.