Hoerstman General Contracting, Inc v. HahnHoerstman General Contracting, Inc v. Hahn
This case calls on us to decide whether an accord and satisfaction existed between the parties. The Court of Appeals found that it did not. We disagree and rule that the parties reached an accord and satisfaction. Therefore, we reverse the decision of the Court of Appeals and remand the case to the trial court for entry of judgment in favor of defendants.
SUBSTANTIVE FACTS AND PROCEDURAL HISTORY
This case centers on a сontract to remodel and reconstruct a lakeside residence in Edwardsburg, Michigan, 1 made between plaintiff, Hoerstman General Contracting, Inc., and defendants Juanita and Ronald Hahn, the owners. Unfortunately, several unforeseen events during construction caused significant delay and cost overruns. When plaintiff did not meet the expected deadline to complete the work, Ronald Hahn informed plaintiffs owner that he wаnted the job finished no matter the expense. Plaintiff agreed to work under these conditions if Ronald agreed to pay the extra costs. Ronald made it clear that he was not concerned with the price.
Plaintiff followed Ronald’s oral instructions on changes to the project. These were not minor modifications. They included moving walls and tearing up concrete floors. According to plaintiff, a later-compiled written list of the oral changes to the contract covered over ten pages. Despite these significant alterations, Ronald refused to agree in writing to any changes to the existing contract.
Defendants acknowledged that they owed more than the original bid price and paid plaintiff $125,000. But plaintiff claimed defendants owed an additional $32,750. In an apparent attempt to settle the dispute, plaintiff sent a lettеr to defendants asking for $16,910.79. Plaintiff indicated that it would provide the lien waiver and close the account in exchange for payment of the amount requested.
Defendants did not pay the $16,910.79. Instead, they replied with a letter in which they calculated the balance due at $5,144.79. They included with the letter their check for that amount. They wrote “final payment” on the check. In the letter, they indicated that they believed that their payment of $5,144.79 closed the account. The letter provided:
If we send you a check for $5144.79 we will consider this account closed and will not expect discussion of the other * items.[ 2 ] We will then expect the lein [sic] waiver to he sent. If this is not acceptable, we will have to resort to arbitration per attorney [sic].
Plaintiff sought legal advice. Its attorney crossed out the words “final payment” on the check and advised plaintiff tо deposit it. Plaintiff followed this advice, credited defendants’ account in the amount of $5,144.79, and did not close the account.
When defendants made no additional payments, plaintiff brought suit seeking damages and foreclosure of its construction lien. Defendants counterclaimed for amounts they believed they had overpaid. In their answer to plaintiff’s complaint, defendants asserted the affirmative defense of accord and satisfaction. After a bench trial, the court awarded plaintiff approximately $26,000 after setting off $5,800 on defendants’ counterclaim. The court did not explicitly rule on the issue of accord and satisfaction.
STANDARD OF REVIEW
The existence of an accord and satisfaction may be decided as a question of law if the facts of the case are undisputed and not open to opрosing inferences.
Urben v Pub Bank,
ACCORD AND SATISFACTIONS
An accord and satisfaction is an affirmative defense
3
grounded in contract principles. An accord is a contract and requires a meeting of the minds of those who enter into it.
Fritz v Marantette,
Cases in which an accord and satisfaction defense is relevant involve a good-faith dispute about an unliquidated amount owing under a contract. One party makes a tender in satisfaction of the claim (an accord). The other accepts or rejects the accord. If the second party accepts the tender, there is both an accord and a satisfaction. See
Nationwide Mut Ins Co v Quality Builders, Inc,
In this Court’s handling of common-law accord and satisfaction, two lines of cases developed. The first holds that whether there was a sufficient meeting of the minds for an accord and satisfaction is a question for the jury.
5
The second holds that the required meeting of the minds is implied
As in this case, the affirmative defense of accord and satisfaction often involves the use of a check. A check is a negotiable instrument entered into between the maker and the payee.
Huler v Nasser,
UCC PREEMPTION IN CASES INVOLVING NEGOTIABLE INSTRUMENTS
In 1964, the Michigan Legislature enacted the Uniform Commercial Code. In 1993, the Legislature added to Article 3 of the UCC a provision governing accord and satisfaction. Article 3 is known as the “Uniform Commercial Code-Negotiable Instruments.”
(1) If a person against whom a claim is asserted proves that (i) that person in good faith tendered an instrument to the claimant as full satisfaction of the claim, (ii) the amount of the claim was unliquidated or subject to a bona fide dispute, and (Hi) the claimant obtained payment of the instrument, the following subsections apply.
(2) Unless subsection (3) applies, the claim is discharged if the person against whom the claim is asserted рroves that the instrument or an accompanying written communication contained a conspicuous statement to the effect that the instrument was tendered as full satisfaction of the claim.
(3) Subject to subsection (4), a claim is not discharged under subsection (2) if either of the following applies:
(a) The claimant, if an organization, proves that (i) within a reasonable time before the tender, the claimant sent a consрicuous statement to the person against whom the claim is asserted that communications concerning disputed debts, including an instrument tendered as full satisfaction of a debt, are to be sent to a designated person, office, or place, and (ii) the instrument or accompanying communication was not received by that designated person, office, or place.
(b) The claimant, whether or not an organizatiоn, proves that within 90 days after payment of the instrument, the claimant tendered repayment of the amount of the instrument to the person against whom the claim is asserted. This subdivision does not apply if the claimant is an organization that sent a statement complying with subdivision (a)(i).
(4) A claim is discharged if the person against whom the claim is asserted proves that within a reasonable time before collection of the instrument was initiated, thе claimant, or an agent of the claimant having direct responsibility with respect to the disputed obligation, knew that the instrument was tendered in full satisfaction of the claim.
Whether a statutory scheme such as
In general, where comprehensive legislation prescribes in detail a course of conduct to pursue and the parties and things affected, and designates specific limitations and exceptions, the Legislature will be found to have intended that the statute supersede and replace the common law dealing with the subject matter. [Id., citing 2A Sands, Sutherland Statutory Construction (4th ed), § 50.05, pp 440-441.]
The Legislature has the authority to abrogate the common law.
Rusinek v Schultz, Snyder & Steele Lumber Co,
As already noted, Article 3 of the UCC is comprehensive. It is intended to apply to nearly every situation involving negotiablе instruments. See
Therefore, the language of the statute shows that the Legislature covered the entire area of accord and satisfactions involving negotiable instruments. It clearly intended that the statute would abrogate the common law on this subject. 9
Our conclusion is buoyed by the UCC comment to
As part of the revision of Article 3, Section 1-207 has been amended to add subsection (2) stating that Section 1-207 “does not apply to an accord and satisfaction.” Because of that amendment and revised Article 3, Section 3-311 governs full satisfaction checks. Section 3-311 follows the common law rule with some minor variations to reflect modern business conditions. [MCLA 440.3311 , comment 3.]
Thеse comments support a finding of preemption. They demonstrate the Legislature’s intent to modify and update the common law. Therefore, we hold that
APPLYING
The first requirement of an accord and satisfaction is a good-faith tender to the claimant аs full satisfaction of the claim.
Defendants demonstrated “honesty” in their settlement offer to plaintiff. They offered plaintiff what defendants thought was a fair deal. In their letter to plaintiff, as part of the accord, defendants went through the various additions to the construction contract. They estimated what each cost and listed each disputed item. Juanita Rems Hahn gave a full explanation of why defendants thought they should not have to pay for the disputed items. Defendants’ accounting also included a detailed list of all payments made. In total, the accounting covers several pages.
After adding their estimation of all costs and subtracting all the payments, defendants аrrived at $5,144.79 as the amount of the accord and tendered it to plaintiff. Given that this tender was made in such detail and with clear explanations of its reasoning, we conclude that defendants’ tender was made in “good faith” as required by
The second requirement of an accord and satisfaction involving a negotiable instrument is that the claim be unliquidated or subject to a bona fide dispute.
Plaintiff performed extra work without an agreement regarding the amount to be paid. Because the cost of the changes and overruns were left unspecified and are in dispute, the claim for them is unliquidated.
Plaintiff argues the contrary. It asserts that, to the extent that defendants conceded that they owed part of the disputed debt, that portion of the debt was liquidated.
“The fact that part of the claim was conceded did not divide the liability into two liquidated claims. Whatever the rule in other jurisdictions, this court holds that such a claim is unliquidated and payment of the conceded amount furnishes consideration for settlement of the whole.” [Lehaney v New York Life Ins Co,307 Mich 125 , 131;11 NW2d 830 (1943), quoting Long v Aetna Life Ins Co,259 Mich 206 , 209;242 NW 889 (1932).]
See also
Tanner v Merrill,
The third requirement contained in
onee the first three requirements are satisfied, the question becomes whether the claim was discharged. Under the statute, there are two ways to discharge a claim. According to
Even if we did not find a discharge of the debt under
Unless subsection (3) applies, the claim is discharged if the person against whom the claim is asserted proves that the instrument or an accompanying written communication contained a conspicuous statement to the effect that the instrument was tendered as full satisfaction of the claim. [MCL 440.3311(2) .]
“Conspicuous”: A term or clause is conspicuous when it is so written that a reаsonable person against whom it is to operate ought to have noticed it. A printed heading in capitals (as: non-negotiable bill of lading) is conspicuous. Language in the body of a form is “conspicuous” if it is in larger or other contrasting type or color. But in a telegram any stated term is “conspicuous”. Whether a term or clause is “conspicuous” or not is for decision by the court.
In this case, defendants wrote the words “final payment” on the comment line of the check. They were in capital letters and not obfuscated in any way. They meet the definitiоn of “conspicuous” because they were written so that someone would notice them.
The letter sent with the check also contains a conspicuous statement that the check discharges the claim. Specifically, the letter provided:
If we send you a check for $5144.79 we will consider this account closed and will not expect discussion of the other * items. We will then expect the lein [sic] waiver to be sent. If this is not acceptable, we will have to resort to arbitration per attorney [sic].
This statement was the concluding paragraph, directly above the signature line. It was not placed in a footnote or other location that plaintiff might skip over while reading. Therefore, it too was a “conspicuous” statement that the check was tendered as full satisfaction of the claim, and that the claim was discharged. 12
Two exceptions to
CONCLUSION
We find that by enacting
Therefore, the trial court erred in not applying the UCC to this case. The Legislature used clear language to describe in detail a course of conduct to pursue in order to accomplish an accord and satisfaction. It designated specific limitations and exceptions to the rule.
Applying
Reversed and remanded to the circuit court.
Notes
Originally, the residence belonged solely to Juanita Rems. Juanita married during the course of construction and added her husband, C. Ronald Hahn, to the title.
iphe “* items” refers to а list of disputed charges for changes made in the project.
MCR 2.111(F)(3) provides:
Affirmative Defenses. Affirmative defenses must be stated in a party’s responsive pleading, either as originally filed or as amended in accordance with MCR 2.118. Under a separate and distinct heading, a party must state the facts constituting:
(a) an affirmative defense, such as contributory negligence; the existence of an agreement to arbitrate; assumption of risk; payment; release; satisfaction; discharge; license; fraud; duress; estoppel; statute of frauds; statute of limitations; immunity granted by law; want or failure of consideration; or that an instrument or transaction is void, voidable, or cannot be recovered on by reason of statute or nondelivery;
(b) a defense that by reason of other affirmative matter seeks to avoid the legal effect of or defeat the claim of the opposing party, in whole or in part;
(c) a ground of defense that, if not raised in the pleading, would be likely to take the adverse party by surprise.
Black’s Law Dictionary (7th ed) provides a useful definition of “accord and satisfaction”:
An agreement to substitute for an existing debt some alternative form of discharging that debt, coupled with the actual discharge of the debt by the substituted performance. The new agreement is called the accord, and the discharge is called the satisfaction. [Emphasis in original.]
See
Fritz,
See
Lehaney v New York Life Ins Co,
(1) This articlе applies to negotiable instruments. It does not apply to money, to payment orders governed by article 4a, or to securities governed by article 8.
(2) If there is conflict between this article and article 4 or 9, articles 4 and 9 govern.
(3) Regulations of the board of governors of the federal reserve system and operating circulars of the federal reserve banks supersede any inconsistent provision of this artiсle to the extent of the inconsistency.
“The expression of one thing is the exclusion of another.” Black’s Law Dictionary (7th ed), p 1635.
We note that this conclusion does not eliminate common-law accord and satisfactions entirely. An accord and satisfaction can exist without the use of a negotiable instrument. For instance, the parties could use cash or goods to satisfy a debt rather than a check.
The clаim must be in dispute at the time of the accord. Contract principles apply to it.
Fritz,
Plaintiff failed to note the existence of
We first note that, despite what the common law may state,