184 Ky. 484 | Ky. Ct. App. | 1919
Opinion of the Court by
Affirming.
Claiming that he entered into a contract with the defendant to fill defendant’s lot and to dig a cistern thereon for the sum of $1,307.00, and that he had performed services under the contract of the value of $1,200.00 when defendant stopped him from work, and that no part thereof had been paid except the sum of $200.00, plaintiff, Walter Wilkerson, brought this suit against the defendant, W. C. Hoefflin, to recover the sum of $1,007.00, the balance due for work performed under the contract. Defendant denied the allegations of the petition, and pleaded that the only contract he had with plaintiff was that plaintiff was to haul the dirt for 65c. per yard, that the amount of dirt hauled by plaintiff was only $300.00, and that he paid to plaintiff and his laborers, and to others, because of the negligent manner in which plaintiff did the work, the sum of $470.55, or $170.55 more than the value of the work performed by plaintiff. He asked that plaintiff’s petition be dismissed, and that he recover on his counterclaim the sum of $170.55. The trial before a jury resulted in a verdict and judgment for plaintiff in the sum of $585.90. Defendant appeals.
Plaintiff testified that he was to do the work under the contract for the sum of $1,307.00, while defendant testified that plaintiff was to receive only 65c per yard for the dirt hauled and spread, but the whole amount was not to exceed $1,307.00. Each of these theories was submitted to the jury, who were told, in substance, that if they found the contract to be as claimed by plaintiff, they
It is first insisted that the court did not give the correct measure of damages for the breach of the contract as claimed by plaintiff. In a case like this, where plaintiff has performed the contract in part, and its further performance has been prevented by the act of the defendant, he may either sue for the breach and recover damages, in Avhich event the measure of damages is the difference between the contract price and what it would have cost plaintiff to complete the contract, or he may sue and recover compensation for the work actually performed, in Avhich event the measure of his recovery is the reasonable value of such work. 6 R. C. L., sec. 348, p. 978; 9 Cyc. 688; Langstaff-Orm Mfg. Co. v. Wilford, 160 Ky. 737, 170 S. W. 1; Stearns Lumber Co. v. Inman, 154 Ky. 253, 157 S. W. 23; Foster v. Watson, 16 B. Mon. 387; Runyan, &c. v. Punxsutawney Drilling & Contracting Co., 31 R. 588, 102 S. W. 854. Here, plaintiff elected to sue for the work done under the contract. Hence, the measure of recovery given by the trial court was not erroneous.
It is further insisted that the evidence of the amount of work clone by plaintiff Avas too indefinite to support the verdict. It’ appears that numerous teams were employed for several days in hauling dirt.. Plaintiff says that all the dirt had been hauled; that there remained nothing to do except to level it off; that more than three-fourths of the Avork had been done, and that the Avork could have been completed in about a day and a half. Another witness testified that more than two-thirds of the work had been done. While this evidence may be somewhat lacking in certainty, it is sufficient, we think, to sustain the verdict.
Judgment affirmed.