232 Mass. 528 | Mass. | 1919

Crosby, J.

This is an action of contract to recover the cost of making an excavation for an elevator plunger installed in an addition to the High School building in Winthrop. The defendant was. the general contractor, and sent a postal card dated May 14,1915, to the plaintiffs inviting them to submit an estimate upon the work of furnishing and installing two plunger elevators in the building. The plaintiffs replied by letter dated May 21,1915, proposing to do the work for the sum of $596. This letter contained the following: “It is understood that in sinking the plunger we should strike any serious obstruction such as beams, solid rocks, foundations any other such materials, the removing of the same will be billed to you at regular rates.” There was no further communication between the parties until September 21,

1915, when the defendant wrote the plaintiffs as follows: “Will you kindly call and see us regarding the two hydraulic lifts in the Winthrop High School. We should like to arrange for this work with you if possible, and conditions at the building are now such that you can give an accurate figure.”

The record recites that one Howard, vice president of the de*530fendant company, testified as follows: ‘“I saw Mr. Slack after I sent the letter of September 21st, and told him that we had dug cellar fourteen feet and he could go and see the place and perhaps could give a definite figure.’ The witness further testified that he told Slack that he wanted a definite figure; that he had to figure everything he dug; that he had in the foundation, fourteen feet of the wall, and that he could see the formation. Mr. Slack testified as follows: ‘I went to Winthrop and looked over the place where the work was to be done, and found I could perform the work with a considerable number of feet less piping than I first contempleted, equalling in money value $28.”’ On September 27, 1915, the plaintiffs wrote the defendant as follows: “In reply to installation of two hydraulic Elevators at Winthrop High School, would say that after going over the grounds we will be able to shade our previous figures twenty eight dollars, making the price of installation Five Hundred Sixty Eight Dollars ($568.00). All work guaranteed to comply with the new State Law. Trusting to receive your valued order.” On receipt of this letter the defendant wrote the plaintiffs as follows: “Your proposal to install two hydraulic elevators at the Winthrop High School, according to plans and specifications by the architect, Willard M. Bacon, with all work guaranteed to comply with the new State law, for the sum of Five hundred and sixty-eight ($568.00) dollars, is hereby accepted.”

Thereafter the plaintiffs installed the two elevators. In doing the work it was necessary to dig two holes fourteen feet below the level of the cellar. In digging one of them rocks and boulders were encountered, and the plaintiffs stopped work and sent for Howard, who went to the building and told the plaintiffs’ representative to “ Go to it and get the rocks out.” The plaintiffs removed the rocks and completed the work. They have been paid $568 by the defendant in accordance with the offer contained in the letter of September 27, and bring this action to recover for the extra work occasioned, by the removal of the rocks and boulders, which the trial judge found were a "serious obstruction.” The report contains all the material evidence, and the only question is whether the plaintiffs are entitled to recover for the extra work under the clause above referred to in the plaintiffs’ letter of May 21.

*531The intention of the parties as shown by the evidence makes it plain as matter of law that the original proposal of the plaintiffs was not accepted; and that afterwards the defendant’s work at the building had so far progressed that the plaintiffs were willing to submit a new proposal to do the entire work for $568. The defendant’s letter of September 21 shows that it desired to receive an “accurate figure” for which the work could be done; and after a further examination of the premises the plaintiffs made the proposal which was finally accepted by the defendant. The undisputed facts show that the provision for extra compensation for the removal of any “serious obstruction,” which was contained in the plaintiffs’ letter of May 21, written more than four months before any contract was finally concluded, was not within the contemplation of the parties when the last offer was made and accepted. The work for which the plaintiffs now seek to recover manifestly was included in the final agreement, and must be held to have been so understood by both parties. The order of Howard to the plaintiffs’ agent to remove the rocks does not affect the rights of the parties, as it merely directed the plaintiffs to do what was required of them under the contract.

The cases of Cunningham v. Parks, 97 Mass. 172, and Thayer v. Burchard, 99 Mass. 508, relied on by the plaintiffs, are not applicable to the case at bar, as the evidence shows that as matter of law the provision for extra compensation, referred to in the plaintiffs’ first letter, was not included in the contract as finally made.

Under the contract the plaintiffs, for the price named, took the risk of encountering obstructions and agreed to do all the work necessary to install the elevators. Stuart v. Cambridge, 125 Mass. 102. Braney v. Millbury, 167 Mass. 16. See Howard v. Harvard Congregational Society, 223 Mass. 562, 565. The defendant’s first, fourth, fifth and seventh requests should have been given. The order dismissing the report must be reversed and judgment entered for the defendant.

So ordered.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.