232 Mass. 528 | Mass. | 1919
This is an action of contract to recover the cost of making an excavation for an elevator plunger installed in an addition to the High School building in Winthrop. The defendant was. the general contractor, and sent a postal card dated May 14,1915, to the plaintiffs inviting them to submit an estimate upon the work of furnishing and installing two plunger elevators in the building. The plaintiffs replied by letter dated May 21,1915, proposing to do the work for the sum of $596. This letter contained the following: “It is understood that in sinking the plunger we should strike any serious obstruction such as beams, solid rocks, foundations any other such materials, the removing of the same will be billed to you at regular rates.” There was no further communication between the parties until September 21,
1915, when the defendant wrote the plaintiffs as follows: “Will you kindly call and see us regarding the two hydraulic lifts in the Winthrop High School. We should like to arrange for this work with you if possible, and conditions at the building are now such that you can give an accurate figure.”
The record recites that one Howard, vice president of the de
Thereafter the plaintiffs installed the two elevators. In doing the work it was necessary to dig two holes fourteen feet below the level of the cellar. In digging one of them rocks and boulders were encountered, and the plaintiffs stopped work and sent for Howard, who went to the building and told the plaintiffs’ representative to “ Go to it and get the rocks out.” The plaintiffs removed the rocks and completed the work. They have been paid $568 by the defendant in accordance with the offer contained in the letter of September 27, and bring this action to recover for the extra work occasioned, by the removal of the rocks and boulders, which the trial judge found were a "serious obstruction.” The report contains all the material evidence, and the only question is whether the plaintiffs are entitled to recover for the extra work under the clause above referred to in the plaintiffs’ letter of May 21.
The cases of Cunningham v. Parks, 97 Mass. 172, and Thayer v. Burchard, 99 Mass. 508, relied on by the plaintiffs, are not applicable to the case at bar, as the evidence shows that as matter of law the provision for extra compensation, referred to in the plaintiffs’ first letter, was not included in the contract as finally made.
Under the contract the plaintiffs, for the price named, took the risk of encountering obstructions and agreed to do all the work necessary to install the elevators. Stuart v. Cambridge, 125 Mass. 102. Braney v. Millbury, 167 Mass. 16. See Howard v. Harvard Congregational Society, 223 Mass. 562, 565. The defendant’s first, fourth, fifth and seventh requests should have been given. The order dismissing the report must be reversed and judgment entered for the defendant.
So ordered.