Hochen Ex Rel. Estate of Hochen v. Bobst Group, Inc.Hochen Ex Rel. Estate of Hochen v. Bobst Group, Inc.
Plaintiffs-appellants Ismael Hochen (“Hochen”) and Richard Dufault (“Du-fault”) were injured on August 2, 1994, as a result of an explosion in a printing press at their place of employment, Avery Den-nison Corporation (“Avery”). 1 Hochen and Dufault subsequently brought suit against defendant-appellee, the Bobst Group, Inc. (“Bobst”), 2 claiming liability for negligence, failure to warn, and breach of warranty, in connection with Bobst’s activities related to the printing press in 1971 and 1972 and in 1994. In separate rulings, the district court granted Bobst’s motions for (1) partial summary judgment on all claims arising out of its activities in 1971 and 1972; (2) partial summary judgment on the breach of warranty and failure to warn claims arising out of Bobst’s activities in 1994; and (3) judgment as a matter of law on the remaining negligence claims. Appellants now ask us to review the first and third rulings as well as the district court’s decision to exclude testimony by their expert witness. We affirm.
I. BACKGROUND
In 1971 and 1972, Bobst designed and constructed the press in question, Press 8 (the “press”), following Avery’s custom specifications and requirements, and in
In 1994 Avery undertook a project to upgrade the press. Although Avery decided to conduct the upgrade with in-house employees, it requested that Bobst send field technicians to the plant for several days to work on the installation of two used pieces of equipment, an S-1480 Re-gistrón control system (the “S-1480”) and an R-820 infeed electronic system (the “R-820 infeed”). The S-1480 was an electronic registration device that helped identify the relative position to each other of successive colors being printed on a label and adjusted the print cylinders to ensure their proper alignment. The R-820 infeed electronic system was a part of the infeed that, along with a companion R-820 outfeed system, controlled the tension of the paper web as it passed through the press. For the press to operate correctly, the same tension of the web had to be maintained throughout the entire printing process. Tachometers on the press measured web speed and sent voltage signals that allowed different parts of the press to operate in a synchronized fashion. Bobst technicians installed one tachometer as part of a component of the S-1480 called an auto-sequencer. The parties disagree as to whether Bobst had a duty to synchronize the voltage signal of this tachometer with the voltage signals of other devices on the press — and specifically with the voltage signal from a tachometer in the outfeed unit — and as to whether the auto-sequencer was intended to be operational at all at the time of the installation.
The Bobst technicians worked at Avery from approximately June 26, 1994 to July 3, 1994. The parties strongly contest how Bobst’s services during this period should be characterized. Appellants argue that Bobst was hired to install, start up, and debug the S-1480 and R-820 infeed because they were the “experts” on these devices. Bobst counters that its field technicians were hired only to fill in a labor shortage arising out of vacations taken by Avery’s own employees and that Avery intended to complete the work with its own electricians and tradesmen. In any case, the record indicates that Avery discharged Bobst’s technicians shortly before the 4th of July weekend, at a time when the press was not operational, telling them that they would be called back if needed.
On August 2, 1994, an explosion in the press injured Hochen and Dufault. Appellants brought suit against Bobst, alleging that Bobst was liable for negligence, failure to warn, and breach of warranty in connection with its activities involving the design and installation of the press in 1971 and 1972 and involving the upgrade in 1994. With regard to the 1994 upgrade, appellants’ theory was essentially that Bobst failed to correct voltage problems with the press’s tachometers, leading to problems with web tension. Avery employees testified that, on the day of the explosion, the web had so much slack that it was dipping into one of the ink pans before shooting into the dryers and appellants argued that the flammable solvents in the ink caused the explosion in the
On December 5, 1997, the district court granted Bobst’s motion for partial summary judgment on all claims arising out of any deficiency or neglect by Bobst in the design, construction, or installation of the press in 1971 and 1972, holding that these claims were barred by Massachusetts’s six-year statute of repose, Mass. Gen. L. ch. 260 § 2B, concerning improvements to real estate. Hochen v. Bobst Group, Inc., No. 96-11214-DPW, R. Doc. 56 (D.Mass. Dec. 5, 1997). The parties thereafter consented to proceed before a magistrate judge for trial and entry of judgment pursuant to 28 U.S.C. § 636(c). On May 10, 2000, the magistrate judge further entered summary judgment in favor of Bobst on the breach of warranty and failure to warn claims related to Bobst’s activities in 1994. Hochen v. Bobst Group, Inc., No. 96-11214-RBC, R. Doc. 234 (D.Mass. May 10, 2000).
The negligence claims relating to the 1994 upgrade — the only claims to survive the two summary judgment motions — went to trial before a jury in May 2000. On May 19, 2000, in a bench ruling, the magistrate judge excluded the testimony of appellants’ expert witness, Daniel Harwood, on these claims and granted Bobst’s motion for judgment as a matter of law on the issue of negligence, thereby disposing of the case. Hochen v. Bobst Group, Inc., No. 96-11214-RBC, R. Doc. 264 (D.Mass. May 19, 2000).
Here, appellants ask us to review three of the district court’s rulings: (1) the order granting summary judgment to Bobst on claims held to be barred by the statute of repose; (2) the ruling excluding testimony by appellants’ expert witness; and (3) the ruling granting Bobst’s motion for judgment as a matter of law on the negligence claims. Appellants do not appeal the summary judgment ruling in favor of Bobst on the breach of warranty and failure to warn claims related to Bobst’s activities in 1994. We affirm the exclusion of the expert witness testimony and the grant of judgment as a matter of law on the 1994 negligence claims. We also affirm the district court’s 1997 grant of summary judgment in favor of Bobst on the claims arising out of Bobst’s activities in 1971 and 1972, but on grounds other than the statute of repose.
II. CLAIMS ARISING OUT OF 1971-1972 ACTIVITIES
On appeal, Bobst contends that the statute of repose question is moot. 3 Bobst argues that, even if we were to find that the statute of repose does not bar appellants’ claims arising out of the design, manufacture, and installation of the press in 1971 and 1972, the claims must fail because appellants never designated any relevant expert opinion testimony. Such designation is required under Rule 26(a)(2) of the Federal Rules of Civil Procedure. Without the qualified expert opinion testimony, Bobst argues, appellants could not submit their claims to the jury, even if we were to remand the case for retrial as to their 1971 and 1972 claims.
After a review of the record, we agree with Bobst that appellants failed to designate any expert testimony on any purport
Although, under Massachusetts law, expert testimony may not be required in cases where the jury can find a design or manufacturing defect based on the testimony of the injured or of co-workers, here the nature of the defect or breach of warranty and its causal relation to the accident were complex and thus appropriately the subject of expert testimony.
See Goffredo v. Mercedes-Benz Truck Co.,
III. NEGLIGENCE CLAIMS ■ ARISING OUT OF 1994 ACTIVITIES
In order to succeed on a claim of negligence at trial, appellants were required to establish that (1) Bobst owed them a duty of care, (2) Bobst breached that duty, and (3) Bobst’s breach of the duty caused the injury to appellants.
See Davis v. Westwood Group,
A. Exclusion of Expert Testimony
At trial, appellants offered testimony by Harwood to support their claims of negligence by Bobst in its activities relating to the 1994 upgrade of the- press. Harwood’s testimony would have -addressed, first, the scope of the work assigned to Bobst by Avery, and, second, the cause of the explosion in the gas dryer. On the first issue, the magistrate judge held , that Harwood’s testimony as to what the Bobst technicians’ work orders meant was irrelevant because the terms should be interpreted from the perspective of a field technician and not from the perspective of an engineer. As to the second issue, the magistrate judge held that Har-wood’s testimony with respect to the press was not reliable because “the testimony is not based on a sufficient knowledge of the machine.”
Rule 702 of the Federal Rules of Evidence assigns to the trial judge the responsibility for ensuring that an expert’s testimony as to scientific, technical, or other specialized knowledge “both rests on a reliable foundation and is relevant to the task at hand.”
Daubert v. Merrell Dow Pharm., Inc.,
B. Grant of Judgment as a Matter of Law
The third ruling appellants contest is the grant in favor of Bobst of judgment as a matter of law, pursuant to Rule 50(a) of the Federal Rules of Civil Procedure, on the negligence claims arising out of Bobst’s work on the press in 1994. Appellants argue that, even without the expert testimony, they made out a prima facie case of negligence that should have been submitted to the jury. 7 The magistrate judge found that the appellants had failed to introduce sufficient evidence as to the duty and causation elements of their negligence claim. The magistrate judge ruled that the jury could find that a proximate cause of the explosion was the web slack, leading to the ink-drenched web entering the dryer. However, the magistrate judge found (1) that appellants had failed to prove that Bobst had an obligation to correct any voltage problems the press may have had and (2) that, even if Bobst had an obligation to correct any problems, appellants offered no evidence that the un-syn-chronized voltage was a proximate cause of the web slack.
We review the grant of a motion for judgment as a matter of law de novo.
See Brennan v. GTE Gov’t Sys. Corp.,
On the question of duty, appellants urge us to find that the magistrate judge took too narrow a view of Bobst’s role in the upgrade of the press. The magistrate judge found insufficient evidence that Bobst had any obligation to work on the tachometer in the outfeed, which, in the state in which it had been left, allegedly would have sent a voltage signal to devices in the S-1480 and/or R-820 infeed that was inconsistent with the signals generated by those devices. Appellants’ argument is essentially that, whether or not
We find that appellants have not produced “more than a mere scintilla of evidence” in support of their theory of duty and that they therefore cannot withstand a motion for judgment as a matter of law. 8 First, the record does not support the argument that Bobst had an obligation to synchronize the electronic controls of the press. Appellants have directed us to several segments in the depositions and trial testimony that allegedly support the position that Bobst had an obligation to ensure that the electronic systems, as a whole, were compatible. Much of the cited testimony, however, simply stands for the proposition that, in order for the press to run properly, the electronics on the various devices had to be synchronized, and not for the proposition that Bobst was the party with the obligation to ensure that these electronics were synchronized. Even where the testimony suggests that Bobst may have had an obligation to check out the electronics on the S-1480 9 and the R-820 infeed, we find nothing that could be considered “more than a mere scintilla of evidence” to the effect that Bobst was required to synchronize the voltage signals on these systems with voltage signals coming from other devices on the press. 10
Second, even acknowledging that the record of depositions and testimony is voluminous and the issue at hand complex, so that “more than a mere scintilla of evidence” suggesting appellants’ theory of duty could conceivably be uncovered,
11
we
Because we agree with the magistrate judge that appellants have not presented “more than a mere scintilla of evidence” in support of a duty on the part of Bobst to synchronize the voltage signals coming from the various devices on the press, we need not reach the question of whether they presented sufficient evidence on the question of causation. 13 We affirm the grant of judgment as a matter of law on the negligence claims against Bobst arising out of its role in the 1994 upgrade.
IV. CONCLUSION
For the reasons stated above, we affirm (1) the grant of summary judgment in favor of Bobst on all claims arising out of its activities in 1971 and 1972; (2) the ruling excluding testimony by appellants’ expert witness; and (3) the grant of judgment as a matter of law in favor of Bobst on the remaining negligence claims.
Costs to appellee.
Notes
. Ismael Hochen has died since the commencement of this lawsuit and Ismar Hochen, the administrator of his estate, has been substituted as plaintiff-appellant. The remaining three plaintiffs are the wife and children of Dufault.
. The suit was originally filed by Ismael Ho-chen in Middlesex Superior Court in March 1996. In April 1996, the complaint was amended to add the Dufault family. In June 1996, Bobst removed the case to federal court pursuant to 28 U.S.C. §§ 1332 and 1446.
. Appellants had previously filed a motion to certify the statute of repose question to the Supreme Judicial Court of Massachusetts. We note that, because we do not reach the statute of repose question, appellants' motion is moot.
. As we have mentioned supra and delineate further in section Til, the magistrate judge correctly excluded Harwood's expert testimony on the upgrade-related claims, so that ultimately appellants have presented no admissible expert testimony on any of their claims.
. We note that we may rule on the sufficiency of appellants' expert testimony at the appeals stage and need not give appellants the opportunity to cure the deficiency in the expert reports by remanding to the district court. In
Weisgram v. Marley Co.,
.
Appellants have argued that the magistrate judge’s findings on this point were inconsistent and contradictory, in that the magistrate judge stated that he was not finding that Harwood "was unqualified to have obtained the necessary knowledge and to give opinion testimony about the machine,” but rather that Harwood had not demonstrated that "he had gained the requisite degree of knowledge and familiarity with the machine so as to be able to render reliable testimony.” We see no inconsistency in this statement. The magistrate judge reasonably determined that, although Harwood could have acquired the familiarity with the press necessary to make his
. We note that the magistrate judge does not appear to have relied on the exclusion of the expert testimony in determining that Bobst was entitled to judgment as a matter of law. The magistrate judge's discussion of the expert testimony follows his discussion of the motion for judgment as a matter of law.
. We reject up-front appellants' argument that, because the same magistrate judge stated in a ruling in a related proceeding that appellants had "at best a
50-50"
chance of succeeding in their case against Bobst,
Hochen v. Bobst Group, Inc.,
. We note again here that the parties additionally disagree as to whether the auto-sequencer on the S-1480 was intended to be operational at all.
. For example, appellants urge us to read testimony by John William Guertson, Avery's research and development manager at the time of the accident, to say that "Bobst was hired to install the S-1480 electronic system and the electronic system for the R-820 in-feed and that, when they left, presumably, they had checked out those electronic sys-terns.” While Guertson does testify to the effect that Bobst had checked out the electronic systems for the R-820 and the S-1480, the testimony continues as follows:
Q. Is it your testimony that you don't know whether or not Bobst checked out the electronic system on the outfeed R-820 rewind?
A. Right.
s}; ^5 sjs sfc
Q. But if Bobst came in to do the infeed, is it your belief that Bobst also, while they were there, would have also done the out-feed?
A. No, I don't think so.
Hochen v. Bobst Group, Inc., No. 96-11214-RBC, Transcript, vol. II at 56 (D.Mass. May 16, 2000).
.Appellants argue that the magistrate judge failed to read certain deposition testimony and that therefore they were not "fully heard” as required before
the
court may grant a motion for judgment as a matter of law
. Gary W. Guidi, the Avery maintenance supervisor to the press at the time of the explosion, testified as follows:
Q. At some point did you release the Bobst workers?
A. Yeah. I mean, July 4th is — we kind of called it a day and figured we'd come back and start reducing things to practice and finish up whatever needed to be done.
Q. So, on July 3rd, when Mr. Verhoeven [a Bobst technician] left, that was with your blessing; right?
A. That's correct.
* * »
Q. And I just want to determine what the status was of the electronic work at the end of July 3rd, when Mr. Verhoeven left. Was it completed?
A. I would say, you know, the terminations were done. The equipment was at a point where it could be reduced to practice. Find out any — you could reduce to practice, find any other issues that may crop up, and you know, see what happened from that point. It wasn't to the point where you could say this press is finished and let’s run this press.
Hochen v. Bobst Group, Inc., No. 96-11214-RBC, Transcript, vol. IV at 51-52 (D.Mass. May 18, 2000).
. We note that, as with the design defect claims arising out of Bobst's activities in 1971 and 1972, the alleged causal relationship between Bobst's activities in 1994 and the accident is complex and thus appropriately the subject of expert testimony.
Goffredo,