126 N.Y.S. 298 | N.Y. App. Div. | 1910
On the 8th of October, 1907, one John E. O’Connor purchased of the defendant its elevator plant and steam pumps iir a building known as the World Building. The agreement provided :
“ It is understood that we are to remove the freight elevators and machinery immediately on acceptance of this letter and the rest of the’ elevators and pumps immediately upon notice from you that théy are out of commission. You to run over all of the material to us on or before the first-day of March, 1908. It is further understood that all of this material is to be removed without inconvenience to the Press Publishing Company or their tenants under the superintendence of your representative within fifteen (15) days, after notice-from you that the said material is ready to be removed, and after said fifteen (15) days all our right and title to said machinery shall cease. JOHN E. O’CONNOR.”
The contract was assigned to D. Lowey & Go. on the fifteenth of October. The assignee started in to remove the material some time- in November, but discontinued the work pursuant to an arrangement with one Williamson, the defendant’s superintendent, that the latter would notify them when to resume. On the twenty-ninth of February Williamson notified-' said assignee to resume work, and work was resumed on March second. On the thirtieth of March a dispute arose which resulted in said assignee discontinuing the work of .removal. . There is a dispute whether that was done pursuant to the order of said Williamson. The plaintiff brings this action as assignee of said D. Lowey & Co. to recover for the material not removed.
It is to be observed that all material was to be removed within fifteen days after notice. If does not appear to what the delay beyond the fifteen days was due. That question does not seem to have been raised on the trial, and was not submitted to the jury. We must assume on-this appeal that the plaintiff’s assignor had the, right, on the thirtieth of March, to continue the work of removal, and that it ivas prevented by the wrongful act of the defendant. The important question, then, is the question of damages.
Obviously, the plaintiff was entitled to the value of the material not removed, less the reasonable cost of removal. The plaintiff’s
These rulings require a reversal of the judgment.
It is unnecessary to cite authority upon the proposition that the damages recoverable for breach of contract are such as may fairly be said to have been within the contemplation of the parties. While, of course, the certainty of proof required may vary according to the circumstances and necessities of the case, it has never been held, so far. as we are aware, that a party claiming damages may have the benefit of favorable contracts, made by him with third parties after the making of the contract for breach of which damages are claimed. As well might the plaintiff have been permitted to show that some one had agreed to remove the material for nothing or that he had contracted tó sell it for several times its-market value as a basis for recovering, not the value of the property, but what he would in
The judgment and order should be reversed- and a new trial granted, with costs to appellant to abide the event.
Ingbaham, P. J., Clabke, Scott and Dowling, JJ., concurred.
Judgment and order reversed, new trial ordered, costs to appellant to abide event.