278 F. 924 | 3rd Cir. | 1922
The Isaac Joseph Iron Company, plaintiff below, hereafter referred to as the plaintiff, and Henry Hirsch, doing business as Contractors’ Machinery & Supply Company, defendant below, hereafter referred to as the defendant, on March 7, 1918, entered into a contract, through letters and telegrams, by the terms of which the defendant agreed to make immediate delivery to the plaintiff of 1,000 tons of 56-pound relaying rails with angle bars, subject to the Pittsburg Testing Laboratory inspection, for the price of $55 per ton f. o. b. Durbin, W. Va. The plaintiff sued to recover damages for the defendant’s alleged breach of the contract in failing to deliver in accordance with its terms. At the trial the plaintiff’s evidence tend
The plaintiff’s representative, Hoeffer, went to Durbin on March 9, and, finding no cars, had three cars placed for loading. Monk, an inspector of the Pittsburg Testing Laboratory, was there to inspect the rails, and the representative of the Conservancy District, Kramer, was upon the ground looking after the interests of the Conservancy District. The inspection and loading of the rails had begun on March 12th, when Hoeffer left Durbin, anti he, having learned that a sufficient quantity of rails was not available in the Dumber Company’s tracks, and that there was no possibility of those available being ready for shipment within five or six weeks, on the 13th and 14th by letter demanded information from the defendant of the whereabouts of the rails to make up the balance of 1.000 tons. On March 18th three cars, containing 110 tons of rails that had passed Monk’s inspection, were shipped.
Meanwhile the plaintiff, having received no information from the defendant concerning other rails to fill the contract, and having been infonned that but 140 tons altogether were available for immediate delivery, owing to the fact that the Thorny Creek Dumber Company refused to allow any more rails to be taken up until it had finished hauling- out its logs, which was likely to take several months, on March 20ih notified the defendant that it had defaulted in its contract for immediate delivery of 1,000 tons, that it refused to accept the three carloads shipped, and that it would hold the defendant liable for damages for breach of its contract. The defendant offered no evidence, moved for a nonsuit, which was refused, and thereupon presented a point for a directed verdict for the defendant, which was also refused. Upon a verdict for the plaintiff, and a refusal of a new trial, the defendant prosecuted his writ of error, assigning as error the refusal of the defendant’s request for binding' instructions and the entry of judgment upon the verdict.
There was no evidence in the case of any tender of other rails to make up the 1,000 tons, or of any offer to perform, except from the Thorny Creek Lumber Company’s, tracks. It is perfectly palpable that the defendant could not, and did not intend to, perform its agreement, except by the immediate shipment of 110 tons, and of the rest at an indefinite time in the future. Under these circumstances, the plaintiff was not bound to accept a partial shipment, and its refusal to do so was not a breach of the contract upon its part. Cleveland Rolling Mill v. Rhodes, 121 U. S. 255, 7 Sup. Ct. 882, 30 L. Ed. 920; McFarland v. Savannah River Co., 247 Fed. 652, 159 C. C. A. 554.
The judgment is therefore affirmed.