91 Cal. 136 | Cal. | 1891
In the court below a demurrer to the complaint was sustained, and judgment thereupon entered in favor of the defendants. The plaintiffs appeal.
The question to be considered here is, whether the ruling of the court in sustaining the demurrer was correct. The demurrer was upon the general ground that the complaint did not state facts sufficient to constitute a cause of action, and also for ambiguity.
The allegations of the complaint, so far as necessary to be stated, are: That on February 28,1887, the defendant Field was the owner of record of the land upon which stands the building against which it is sought to enforce the lien, but that he held the same, in trust, for the Field’s Biscuit and Cracker Company, a defendant herein; that upon that day said Field entered into a contract with said company, whereby, in consideration of the issuance to him of eight hundred shares of its capital stock, he agreed to complete and deliver to the company, equipped and furnished with the latest improvements, a factory, to be constructed under his direction on said land, and as soon as completed, the same, with its appurtenances, to be conveyed to it; that immediately after the execution of this contract, the company issued and delivered to Field eight hundred shares of its capital stock, in full payment for said land, and for the building and machinery to be constructed thereon by him, and on November 5, 1887, the said Field conveyed to the company the land and improvements thereon. The complaint further avers that upon April 11, 1887, the said Field, “ as such contractor of and for the said defendant Field’s Biscuit and Cracker Company, employed plaintiffs herein to build, manufacture, and construct, at their own works, and deliver and put in place, upon foundations prepared by said Arthur Field, in said structure, building, and factory,” a steam plant, consisting of boilers, engine, heater, feed-pipes, etc., for the agreed price of five thousand six hundred dollars, and that said contract was duly performed by plaintiffs. It is not alleged that this contract was recorded, but it is averred
Plaintiff’s claim of-lien was filed for record within the time given by law.
The respondents insist that Field was the owner of the property upon which a lien is claimed at the time he contracted with plaintiffs to furnish for said factory the steam plant referred to in the complaint; and as the price agreed upon to be paid therefor exceeded one thousand dollars, and the contract was not recorded, that the contract was wholly void, under section 1188 of the Code of Civil Procedure, and no recovery can be had by plaintiffs thereunder.
1. Section 1183 of the Code of Civil Procedure provides that “ mechanics, material-men, contractors, subcontractors, artisans, architects, machinists,” etc., shall have a lien upon the property upon which they have bestowed labor or furnished materials, and “ in case of a contract for the work, between the owner and his contractor, the lien shall extend to the entire contract price, and such contract shall operate as a lien in favor of all persons, except the contractor, to the extent of the whole contract price; and after all such liens are satisfied, then as a lien for any balance of the contract price in favor of the contractor.” The section then provides that all such contracts (that is, those between the owner and his contractor) shall be in writing, when the amount agreed to be paid thereunder exceeds one thousand dollars, and, before work is commenced there-under, must be filed in the office of the recorder of the proper county; “ otherwise they shall be wholly void, and no recovery shall be had thereon by either party thereto.”
The ruling of the court below, sustaining the demurrer to the complaint, rests upon these two propositions: 1. That Field was the owner of the building he was constructing; and 2. That plaintiffs were contractors, within the meaning of section 1183 of the Code of Civil Procedure; and the failure of respondents to maintain either one of them is fatal to the judgment appealed from.
2. But assuming this to be so, the question still remains, Were the plaintiffs contractors as that word is used in section 1183 of the Code of Civil Procedure, where it speaks of a “ contract for the work between the owner and his contractor”? If so, their contract, not having been recorded, was wholly void, and the demurrer was properly sustained. We are of the opinion that, upon the facts alleged, plaintiffs were not such contractors, but were material-men. Although one may furnish materials to be used in the construction of a building, under an express contract, he does not become a contractor as that term is used in the law relating to mechanics’ liens. That law recognizes a clear distinction between contractors, subcontractors, material-men, and mechanics, and these different words designate distinct classes of persons. All are referred to as being entitled to liens, and the priority of their several liens is declared, and it is quite clear to us that the word “ contractor,” in sections 1183 and 1184 of the Code of Civil Procedure, does not refer to a material-man. The section, in requiring the contract “ between the owner arfd
This view of the law is sustained by the reasoning of Mr. Justice Sharpstein in the case of Sparks v. Butte County Gravel Mining Co., 55 Cal. 392, in defining the words “original contractor,” as found in section 1187 of the Code of Civil Procedure.
There can be no doubt that the plaintiffs here were simply material-men. Under their contract they were to manufacture at their own shop the boiler, engine, heater, feed-pipes, and necessary attachments, and deliver them finished and complete, and properly set them in the building; but the work done by them on the premises of defendants, in placing them in position, was only the completion of their contract to deliver such finished machinery, and did not convert them into contractors for the erection of the factory, or any part of it, within the true intent of the statute. The contract was essentially one to furnish materials for the factory, and not a building contract.
3. What has been said disposes of the second ground of demurrer, to the effect that the contract was void because not complying with section 1184 of the Code of Civil Procedure, as that section only refers to. the contract of the contractor.
We are satisfied that the complaint states a cause of action, and if the defendants have any defense to the action, it is not disclosed by the complaint. In reaching
4. We do not think the complaint is ambiguous in the respect pointed out by the demurrer.
Judgment reversed, with directions to overrule the demurrers interposed by defendants.
McFarland, J., and Sharpstein, J., concurred.
Hearing in Bank denied.