Himler Coal Co. v. Ella and Albert Kirk

275 S.W. 371 | Ky. Ct. App. | 1925

Reversing.

Appellees own a tract of land in Martin county. The Himler Coal Company proposed to build a line of railway up the bottom from the Norfolk Western Railway to its coal mine. This line crossed a corner of appellees' tract. They forbade the building of the railway on the ground that under its title papers the coal company had no right-of-way there. Thereupon the coal company filed a petition in equity to enjoin the appellees from interfering with it in building the line of railway across the corner of their land. The coal company obtained a preliminary injunction, which on motion was dissolved by the circuit court. It then brought the case before a judge of this court, who reinstated the injunction. While this action was still pending appellees brought this suit against the coal company charging that it had entered upon their land without right and destroyed buildings, etc., to their damage in the sum of $20,000.00. The coal company filed an answer denying the allegations of the petition, pleading its title and pleading the pendency of the equity action in abatement of the action for damages, alleging that that action was in the same court and undecided. A demurrer to this paragraph of the answer was sustained by the court. At a subsequent term the court dismissed the equity action. The coal company appealed with supersedeas. It then filed an amended answer setting up these facts and praying the court to postpone the trial of the action for damages until the appeal was heard in this court. The court overruled the motion, and the action for damages coming on for hearing before a jury, instructed the jury in substance that the coal company was a trespasser and liable for the damages sued for and that the jury might in their discretion allow punitive damages. The jury found for the plaintiff and fixed the damages at $5,500.00. The coal company appeals.

The appeal in the equity action for an injunction was determined by this court since the judgment appealed from was rendered. This court reversed the judgment of the circuit court. Himler Coal Co. v. Kirk, etc., 205 Ky. 666.

In the equity action the thing in controversy was the right of the coal company under the deeds to a right-of-way *30 over the land. In the action for damages precisely the same question was presented, and in addition to this the question of the amount of damages if the coal company was not entitled to a right-of-way. By section 92 of the Code it is made a ground of demurrer that there is another action pending in this state between the same parties for the same cause, and by section 118 it is provided that a party may by an answer make this objection when it is not shown by the pleading of his adversary. Two actions cannot be at the same time prosecuted for the same cause. L. N. R. R. v. Ohio Valley Tie Co.,161 Ky. 212. The coal company could not be required to litigate in two actions pending at the same time in the same court the question whether it had a right under its deeds to build the railway. If it had the right to build the railway it was not liable for damages for exercising its rights. The second action, therefore, necessarily turned on the same question as the first. The demurrer to the plea in abatement should have been overruled. The hearing of the case should have been postponed until the question of the rights of the parties had been determined in the other case.

"In other words, if a final judgment in the former suit would support a plea of res judicata in the subsequent suit, the suits are identical for this purpose." 3 Am. Eng. Ency. of Law and Practice, p. 1222.

The instructions of the court to the jury were not the proper instructions under the law of the case as settled by this court in the opinion above referred to. No instruction on punitive damages should have been given. All other questions are reserved.

Judgment reversed and cause remanded for further proceedings consistent herewith.

midpage