We adopt the trial court’s findings of fact, as follows: "The plaintiff [Hilton Construction Co., Inc.] is a Georgia
"In approximately May, 1978, the Rockdale County Board of Education issued invitations to bid on the Vocational Edúcation wing addition to Heritage High School in Rockdale County, Georgia (hereinafter referred to as 'the project’). The project was to be built with a combination of local Rockdale County funds and funds from the State of Georgia through the Georgia Department of Education. The amount of state funds committed on the project is limited to four hundred thousand ($400,000.00) dollars with local funds making up the balance. In order to be eligible for the state funds, the Rockdale Board of Education was required to follow bidding procedures of the Georgia Board of Education, which required that 'the award of the contract will be made to the responsible bidder submitting the lowest acceptable bid.’
"On June 14, 1979, at 3:00 p.m., the bids submitted on the project were opened by the Rockdale Board of Education. Five bids were submitted with the plaintifPs bid being the lowest dollar bid at seven hundred eighteen thousand ($718,000.00) dollars. The second lowest dollar bid was submitted by Cube Construction Co., at seven hundred twenty thousand six hundred ($720,600.00) dollars. After opening the bids, the Superintendent of the Rockdale School System, Don J. Joiner, discussed the various bids and bidders with Willard N. Lamberson, the architect employed by the school system for the project... 1
"Solely on the basis of the aforesaid conversation he had had with the project architect (Lamberson) earlier in the day [see footnote 1, above] . . . defendant Joiner recommended to the local board that it reject Hilton’s bid and award the contract to Cube, the second low bidder. The local board accepted defendant Joiner’s recommendation, rejected Hilton’s bid, and accepted Cube’s bid. The Board of Education and Cube Construction Co. entered into a contract for construction of the project on June 18, 1979.
"On June 22,1979, plaintiff sent a letter to the Board of Education protesting the awarding of the contract to Cube Construction Co. and requesting a hearing before
"It should be noted that at the June 14, 1979, meeting, none of the board members had been provided with any information indicating any problems Hilton had on any construction projects it was then currently performing. At no time did the local board make any independent investigation of its own about Hilton. The only additional information provided to the board relative to Hilton was at the subsequent board meeting, in executive session, on July 2,1979, at which time the board was told by defendant Joiner that Hilton was late on the Georgia Tech project. After obtaining this information on July 2, 1979, the board neither inquired about nor obtained any further information about whether Hilton was in fact late on the Georgia Tech job, nor did they learn or inquire about whether it was Hilton’s fault if it was indeed late on the project at Georgia Tech. The board accepted the superintendent’s statement at face value.
"At this later meeting on July 2, the board considered plaintiffs Motion for Reconsideration, and after discussing the matter among themselves and with Joiner decided to uphold their original decision.” 4
Plaintiff filed this action for mandamus and injunction in the Rockdale County Superior Court on July 6 and obtained a temporary restraining order against the
On August 24, following an evidentiary hearing, the trial court denied plaintiffs request for mandamus and injunction. Plaintiff appeals and the defendants cross appeal.
1. Plaintiff-appellant contends that the trial court erred in finding that the school board was authorized to reject its low bid. We agree.
The board rejected plaintiffs bid because plaintiff was "unknown” while Cube was "known.” The State School Board regulations, sec. 40-3820(3)(L), which have the force and effect of law, Code Ann. § 32-653a, provide that projects using state funds will be awarded "to the responsible bidder submitting the lowest acceptable bid.” (No argument is made that plaintiffs bid was not "acceptable” within the meaning of this regulation.) Whatever may be meant by the word "responsible,” we are certain that being "unknown” does not show that a bidder is not "responsible.” The board was not authorized to reject plaintiffs bid on the basis that plaintiff was "unknown.”
The board argues that it was entitled to rely on the investigation performed by its agents. As the board acknowledges, the decision whether to accept or reject the bids was a decision to be made by the board. Here the board merely accepted the superintendent’s recommendation to reject plaintiffs bid and to accept Cube’s. This decision was not based upon facts reported to the board because "... at the June 14,1979, meeting, none of the Board members had been provided with any information indicating any problems Hilton had on any construction projects it was then currently performing.” As the trial court also found, at the time plaintiffs bid was
Finally, the information conveyed to the board at its July 2 meeting that plaintiff was late on the Georgia Tech project did not establish that the plaintiff was not responsible. Being late on a project without any finding as to who caused the delay does not show that a bidder was not "responsible.” For the reasons stated above we therefore conclude that the school board was not authorized to reject the low bid. This disposes of the issues raised on appeal by the plaintiff-appellant.
2. On cross appeal, the defendants enumerate several additional errors. First, they argue that Hilton does not have standing to challenge the award of the contract to Cube. They do not contend, however, that the competitive bidding procedures promulgated by the State Board of Education and relied on by Hilton were not legally binding on the school board in this case. State Board of Education Regulation, § 40-3820 (3) (L); see Op. Atty. Gen. 77-32 (1977). Hilton claims standing as the low bidder to assert a violation of these regulations. We find it clear beyond peradventure that Hilton has a legally protected interest created by state law which gives it standing to assert this violation. See Association of Data Processing Service Organizations, Inc. v. Camp,
3. Defendant-appellees also contend in their cross appeal that plaintiff failed to exhaust administrative
Hilton sought to restrain performance of the contract and to obtain the right to perform itself. The state board could give only the prior relief and that only pending the appeal. It could not replace Cube with Hilton in the contract documents, nor could it grant Hilton damages. "Impossibility or improbability of obtaining adequate relief by pursuing administrative remedies is often a reason for dispensing with the exhaustion requirement.” Davis on Administrative Law 625, § 189 (1951). We decline to hold that Hilton is barred from relief by its failure to exhaust administrative remedies where those remedies were inadequate. United States Alkali Export Assn. v. United States,
4. The board argues that mandamus will not lie to void the contract with Cube. We agree. Mandamus is the remedy for inaction of a public official. "Mandamus is not the proper remedy to compel 'the undoing of acts already done or the correction of wrongs already perpetrated, and . . . this is so, even though the action taken was clearly illegal.’ 38 CJ 592, § 70.”
Wilson v. Sanders,
5. The board argues that equitable relief is not available because plaintiff had adequate remedies at law, namely, (1) appeal to the State Board of Education and (2) damages at law. The first of these was decided adversely to the board in Division 3, above. As we also determined in that division, injunctive relief may well be inappropriate at this time. Hence we leave the question of damages versus injunctive relief for determination by the trial court in light of this opinion.
Judgment reversed in case 35624; judgment affirmed
Notes
(Footnote added.) The content of Lamberson’s conversation was not conveyed by Superintendent Joiner to the Board of Education prior to the award of the contract to Cube. In that conversation "Lamberson
(Footnote added.) In order to be eligible for state funds, it was necessary that the contract be entered into before July 1, 1979. (The state’s fiscal year ends on June 30 of each year.)
(Footnote added.) Plaintiffs attorney was not permitted to question the Board members at this meeting as to why the Board had rejected plaintiffs bid and awarded the contract to Cube.
(Footnote added.) No written decision was entered by the board as a result of its July 2nd meeting.
Although the exhaustion rule has perhaps most often been applied in equity cases where it may be viewed as one aspect of the doctrine of "adequate remedy at law”, the rule itself has long applied to cases at law. See Myers v. Bethlehem Shipbuilding Corp.,
