107 Mo. App. 385 | Mo. Ct. App. | 1904
It seems to be conceded that the contract for making the improvement was not valid and effective unless confirmed by an ordinance passed by the common council. And the first question raised by the appeal is whether or not the ordinance confirming
It is contended that from the date of the passage of the repealing and amendatory act, that is to say from the thirteenth of March until the third Monday in the April following, there was no legal officer or body in existence authorized to exercise the legislative function of the city. If this be so, then during the existence of this hiatus — this .vacuum — if a pestilence had broken out in the city, or if its water or light supply had been destroyed, or if it had been visited by a disastrous fire or flood, or other calamity, and action on the part of the legislative department had been required to relieve
It can not reasonably be supposed that the Legislature by the passage of this act intended to tie up and paralyze the public business — to cripple, disable and render cities of the class to which it relates helpless for more than a month. The language of the act clearly negatives any such legislative intention, but if such intention were doubtful or uncertain, considerations of public policy would forbid a construction productive of such consequences. I can not doubt from the language employed in it that the lawmakers intended by its enact
But if the members of the common council after the passage of said act were not de jure officers, they were de facto. They were, it seems to me, in office under such apparent circumstances of color as would lead men to suppose them to be legal officers entitled to exercise the legislative function of the city. There is nothing to show that they did not act in good faith in continuing to exercise the legislative function. There was no other officer or body then in existence authorized by law to exercise such functions. Even though their office had been abolished and there was no longer any such office to fill, yet as there was color of right for their action as such officers; and though their offices had been abolished the new legislative officers or body had not been elected, nor organized, so that their acts so far as they affected the rights of third persons and the public were valid as the acts of a de facto legislative body. The members of the commrin council were not mere intruders or usurpers. The offices which they pretended to fill were originally legal offices, so that they were valid in their birth.
My conclusion is that the common council, notwithstanding the passage of the repealing and amendatory act of March 13,1901, was still in existence on March 18, next following, and that it was in the lawful exercise of its legislative functions when it passed the said confirmatory ordinance; but if this was not so, that then under the facts of the case disclosed by the record the rule of validation applies to said confirmatory ordinance. It results, therefore, that in either view which I have expressed, the taxbills can not be held void on the ground that the contract for doing the work was not confirmed by an ordinance of the common council.
II.
But it is suggested that- even if the confirmatory ordinance was valid, that the taxbills are still invalid for the reason that the improvement was not completed within the time required by the ordinance ordering it to be made. Adverting to the ordinance ordering the improvement, and I find that it required - Ashland avenue between certain designated points thereon, “to
Time, then, was not bv the terms of this ordinance made of the essence of this transaction. And the con
The defendant did not complete the improvement within the ninety days stated in the contract. The law is, that where a definite time for the completion of an improvement is specified in the ordinance ordering it, or, if no time be specified therein but is made of the essence of the contract by the stipulation of the parties, then, in either case, if the work be not completed within the time so specified, the taxbills will be void. Neill v. Gates, 152 Mo. 585; Childers v. Hohnes, 68 S. W. (Mo.) 1046; Barber Asphalt Co. v. Ridge, 169 Mo. 376; Rose v. Trestrail, 62 Mo. App. 352; McQuiddy v. Brannock, 70 Mo. App. 535; Wittemore v. Sells, 76 Mo. App. 248; Safe Deposit Co. v. James, 77, Mo. App. 616; City v. Davis, 80 Mo. App. 574; Ayres v. Schmohl, 86 Mo. App. 349; Winfrey v. Linger, 89 Mo. App. 159. As the ordinance ordering the improvement did not specify any time for the completion of the work, and as it was not made of the essence of the contract by the express stipulation of the parties thereto, it remains to be determined in what time the defendant was required to complete the improvement.
Carlin v. Cavender, 56 Mo. 286, was a suit on a special taxbill issued by the city engineer of the city of St. Louis to defray1 the cost of improving a street in front of the property of defendant. The ordinance authorizing the work fixed no time for its completion.
“There is obviously no merit in the point that the-work was not completed within the time limited by the contract. There is nothing to show that time was of the essence of the contract. For prudential reasons the engineer suspended the work for a time and the contractors assented to the suspension, but when it was deemed advisable to proceed, the work was then completed and received. It does not appear that the defendant suffered any'injury by the delay.” Strassheim v. Jerman, 56 Mo. 104, approved the ruling made in Carlin v. Cavender.
In Ayres v. Schmohl, 86 Mo. App. 349, it was said that the vital difference between that case and Carlin v. Cavender, ante, was that in the-latter the contract did not make the time prescribed of the essence of the contract, while in the former it did. It was also further said in the same case:
“Those cases (Carlin v. Cavender and Strassheim v. Jerman, 56 Mo. 104). held that where the ordinance did not fix the time and the contract did, that a failure to complete the work within the time stated in the contract did not necessarily avoid the bills,- there being nothing to show that it was of the essence of the contract or the delay was unreasonable.” The rulings of this court, as was said in Ayres v. Schmohl, have been that the time, in which public work should be done is a legislative function and that it can not be delegated to the city engineer; and which rulings are inharmony with that made by the Supreme Court in Neill v. Gates, supra. It inevitably follows from these considerations that the
The city was under an implied duty to furnish the defendant a graded street on which to lay the asphaltum pavement ordered by the special ordinance (Ash v. Independence, 79 Mo. App. l. c. 74), and this duty it recognized and undertook to discharge by passing the ordinance of January 26, 1901, and letting a contract thereunder on March 18, 1901, providing for the grading of the street. The defendant immediately after the confirmation of the paving contract procured and had on hand and was ready and prepared with the necessary materials, tools and equipment to proceed with the execution of the contract, but was ordered by the city engineer not to proceed until the grading contractor had executed his contract, which like that ordering the paving of the street required the work to be completed within a reasonable time. The grading was carried on under
Where the ordinance ordering improvements prescribes a definite time for completion of the work, failure of the city to furnish a graded street within that time will not prolong the life of the contract or excuse performance. Rose v. Trestrail, 62 Mo. App. l. c. 358, and the other cases cited in plaintiff’s brief. But where the improvement is required by the ordinance not to be completed in a definite time but in a reasonable time, then.the action of the city in faliing to grade or cause
The facts shown in this case are not such as are calculated to impress my mind with the conviction that the plaintiff is justly entitled to the equitable relief which she seeks. The improvement was oue that her agent, the, city, was duly authorized by its charter to have made and it was completed by defendant according to the special ordinances and the contract and was accepted by the city. And for aught that appears she stood by and saw the defendant expend its material, labor and money in making the same, without protest or objection; but when it was completed, when she had received all the benefits which could result to her lots from so substantial an improvement, she then for the first time objected and invoked the interposition of a court of equity to relieve her property from being burdened with its proportion of the cost of such improvement. It does not appear that the delay in the completion of the improvement was unreasonable or that the plaintiff suffered any injury in consequence of it, and I think she has not shown herself entitled to equitable relief.
The questions which I have considered and ruled adversely to the plaintiff’s contentions in the foregoing opinion are decisive of the case and therefore it becomes unnecessary to notice the subordinate questions raised by the appeal.
It is my conclusion that the decree of the circuit court should be reversed.