History
  • No items yet
midpage
Highland Construction Co. v. Stevenson
636 P.2d 1034
Utah
1981
Check Treatment

*1 HIGHLAND CONSTRUCTION COMPA

NY, corporation, a Utah Appellant, STEVENSON,

LaMar D. D. dba LaMar Company,

Construction United States

Fidelity Guaranty Company,

Maryland corporation, and Shell Oil

Company, corporation, a Delaware De Respondents.

fendants and

LaMar D. dba D. LaMar Company,

Construction

Third-Party Plaintiff.

No. 17099.

Supreme Court of Utah.

Aug. 1981.

Opinion Rehearing Dec.

HOWE, Justice: by an of an action appeal arises out This sub-contractor, Highland Con- excavating Highland), (hereinafter Company struction contractor, D. LaMar against general (herein- Company Construction Stevenson Stevenson), bonding com- Stevenson’s after Guaranty Fidelity and pany, United States USF&G), and Shell (hereinafter Company Shell). Highland (hereinafter Oil as a result damages it suffered alleged that plans and unrea- construction of defective and Shell delays by Stevenson sonable The trial of their work. performance found no cause sitting jury, without a of Ste- of action on all claims declaratory for a venson’s counterclaim properly had been judgment that for certain back-charged by Stevenson also awarded granted. The court items was High- attorney’s fees and costs. appeals. land entered August On of Utah with the State into a contract with the work in connection all perform the Du- what is known as of construction Project. The River Road chesne Highway a section of State upgrade was to Duchesne, Utah. 35, of miles north located 5 August Ste- week During the first have it negotiated venson work. the earth perform some High- culminated negotiations These moving, the earth agreement to do land’s This excavation. roadway including the put into Stevenson-Highland contract August or about signed on writing and August 9. was dated president negotiations, During these inspected Bergener, Bryan Highland, times, required as site a number be- general terms of by the tween Stevenson the Steven- into by reference incorporated son-Highland sub-contract. project site moved onto Christensen, Martineau, Roger P. Ray G. for the area preparing clearing and began appellant. City, Lake

Salt 12, it August By August 6. excavation water saturated areas of Wilkinson, Hirschi, Le- had encountered David L. J. Rand condi- These road base. unstable Ford, for defend- City, Lake land D. Salt sub-exca- some perform it to required tions respondents. ants and trial, judgment vation in order to After in fa- remove the unstable soil was entered defendants, and replace dismissing plaintiff’s it with vor of the a more stable base. claims granting This work defendant Stevenson’s mainly performed August request declaring he had days previous signing to the formal back-charged in the properly sum Stevenson-Highland contract on or $3,497 work August about *3 required complete by plaintiff’s to reason of 9, On August and with consistent indus- jobsite comple- abandonment of before try practice, pre-construction conference obligations. tion of its contractual The by representatives attended of all court also awarded the defendant Steven- companies which work would on the son attorney’s fees. project. purpose The meeting of such Highland’s point appeal first on to coordinate their At the activities. con- finding that the that trial court erred in spokesman ference a from Shell stated that plans specifications and which pipes relocation its roadside would be preparation used in of its were not bid completed in about four days, rule applicable defective. The to this as not completed actually days until ten later. signment is any of error that if there Highland alleges that delay by this Shell competent support findings to evidence unreasonably progress interfered with of the and conclusions such find of Highland’s excavation. ings, rationally and conclusions based While Highland working on the exca- thereon, appeal. be will not disturbed vation, installing Stevenson was pipes some judgment of the court is The and constructing a concrete-lined ditch. At supported competent in this by evidence various times the work of the two compa- case. The record shows that nies interfered and caused to be president, Bergener, access to Bryan had And, delayed. on occasion Stevenson di- descriptions aspects detailed of all of the rected Highland’s equipment men and to project connected his earth perform work obligation which sole was the obligations, including the soil unstable con of Stevenson. ditions. A of the provision general contract 6, On October removed its incorporated by reference into equipment from the project and Stevenson Stevenson-Highland provid subcontract was forced complete to the excavation work part ed in that: at expense, his own he amount back- required The bidder is to care examine charged Highland. $83,- A total amount work, fully the of the proposed site 591.90 was by Highland received for the proposal, specifications, supplemen plans, performed, work it which amount included specifications, special provisions tal and $6,600 an additional for sub-excavation of submitting before a pro forms subgrade. unstable posal. Furthermore, re materials port, survey, plans soil profiles, and and July On Highland commenced test pertaining proposed data to the work against alleging defendants are inspection available for bidders at plans specifications provided Division, the Materials Test West 200 were defective and they failed to re- South, City, Utah, or Salt Lake the dis veal the existence of unstable road base. It trict office. The submission a bid shall further claimed that breach- be prima considered facie evidence that ed the sub-contract by causing it to be required bidder has made the exami work, delayed in its Shell had also nation and is satisfied as conditions to the unreasonably interfered with its work performing to be encountered work . . . progress. addition, In Highland sought re- imbursement from for the use of

Highland’s equipment, provision and for A in the Survey Soil Materials fees and costs. Report provided that: In of the contentions Project range Type Range:

Soil A-(9) very plastic (In-site from weath- that Stevenson and Shell caused shale) non-plastic silty, ered unreasonably delayed, plaintiff present- A-l-a be sandy gravel. testimony the form of from ed evidence in Drainage: pointed Mr. and also to the Ste- drainage Bergener Natural surface var- good is con- poor. venson-Highland ies from accu- contract wherein Some water mulates in marshy provision obligating saturated zones tained a occur irrigation seeps plain- where complete water certain work advance of irrigation operation delay ditches and canals. The not to plaintiff’s tiff’s so as main area in which saturation zones occur for the de- progress. work lies between 850 + 00 station and station pri- consisted fendants Stevenson Shell +910 Inspec- marily testimony from the required tor who was be on the There was map also a of the at- *4 the during working hours to observe survey report tached to the soil which con- He testified progress of the construction. tained a regard notation with to condi- plaintiff’s operations were not unrea- that tions: seeping “Some from canal to drain- Mr. sonably delayed by Stevenson or Shell. ditch, age saturated marsh and areas.” Stevenson, project was also the who on executed subcontract on or hours, testified during working similarly August about some two weeks unreasonably delayed plaintiff that was not after it had begun project work on the by the of its earth progress had encountered the unstable Fur- soil. activities of either Shell or Stevenson. thermore, there was adduced at evidence, conflicting Based the trial on this trial that Bergener Mr. examined the court for the defendants. This Court found during site sometime the first week there findings will not disturb those where of June and physical observed the condi- competent evidence to them. soil, including tions of the seepage from the canal to a nearby drainage Also ditch. argues the trial Highland next that on observable site marsh by failing apply court to the “total erred grass, alkali and surface water. cost” determine amount theory to the dollar evidence, on the foregoing Based argument This is of damage of suffered. could judge properly concluded that that no avail the trial court found because potential had notice of difficulties were not defendants liable might hinder its work progress reason, no fur any damage. For this plans that the specifications were not of error assignment ther discussion of this defective for give failure to such notice. necessary. assign second and third Plaintiff’s final is that Highland’s contention similarly ments of error are aimed toward awarding erred in the trial court Stevenson finding of fact. court’s any award failing fees and in attorney’s alleges the in finding trial court erred parties At the fees to neither Stevenson nor Shell Oil stipulated that neither would then subjected plaintiff delays to unreasonable fees, respect attorney’s evidence with by reason concurrent their activities mat by the of that that consideration court appears construction site. It from the the court’s ter until after would be deferred that Highland stipulated record that it was in chief. ruling on the merits the case entering aware at the time of into the issuance of a memorandum Following with contract that it neces which the trial court sary that decision in work on the utilities and other sched hearing a items be simultaneously carried on with request uled consideration his moving operations earth held hearing was not attorney’s that such could ex fees. reasonably activities be date, par- all pected operations prior to the scheduled interfere with because 1038 (1978); So.2d 754 Flagala Corp. Hamm, ties v. stipulated that the hearing could be Fla.App., (1974) (foreclosure 302 So.2d 195 waived and if a hearing were held lien), of mechanic’s the meaning within of a Stevenson and his attorney testify would giving pre- fees to actually Stevenson had and necessarily vailing thereon, 346, party event a lawsuit incurred attorney’s $18,597, fees totaling Cervantes, Stott v. 23 Wash.App. and that such amount was reasonable. (1979), 595 P.2d 563 and within the Based on that stipulation, the court accord- meaning awarding a statute costs to ingly awarded for that prevailing party, Shearer, v. Dawson 53 amount of attorney’s fees. That award was (1959). Wash.2d make no difference 337 P.2d 46 It proper should Paragraph 6(e) under of the sub-con- plaintiff whether the tract providing: money recovers during the defendant In the event defaults Sub-Contractor the course of the by voluntary pay- obligations of its here- performance ment or whether plaintiff recovers that under, shall be to re- Contractor entitled by judgment. amount In both instances in- cover from all costs Sub-Contractor the of has money recovered by virtue with the curred in connection ment of Contractor’s enforce- Magnin Co., its action. Joseph See Inc. hereunder, rights Schmidt, Cal.Rptr. 89 C.A.3d including costs and reasonable at- Supp. (1978). case, In the instant fees, torney’s whether with or incurred $10,300.78 long past paid due when by judgment. before or without suit or after paid, Stevenson and since it was albeit vol- The trial court found untarily, plaintiff’s after action was com- by breached sub-contract plaintiff Highland menced the was indeed failing the work complete “prevailing party” particular on that *5 required and perform under the sub-contract fact, cause of action. In view that High- by failing approval to obtain the final attorney’s land was entitled to an fee under inspectors be- of Stevenson and fore the court ney’s for a attorney’s § 14—1—8 reasonable fee in equipment men from removing its and bringing its recovery action for the of the project. finding, In view that $10,300.78 maintaining that action until attor- properly awarded Stevenson payment. High- Stevenson made his Since in “connection with the fees incurred further, land recovered nothing legal serv- rights...” enforcement of [his] pursuing ices incurred in its action after the question A difficult is more payment date of are not recoverable. presented Highland as to whether was enti Highland It is not fatal did not any attorney’s tled to be In awarded fees. present any evidence to court as to complaint Highland prayed attor what would be a par- reasonable fee. Both ney’s upon 14-1-8, fees in reliance U.C.A. § sought ties presumably argued there (1953) providing that: fees, attorney’s claiming each it or he any brought upon In action either should be the “prevailing party.” They provided prevailing- bonds herein . . . the however, stipulated, spect that evidence with re- action, separate party, upon each cause of attorney’s to amount of fees would attorney’s shall recover fee a reasonable presented not be until after the court had [Emphasis to be taxed as costs. added.] ruled on the merits of the When case. par- Highland prevailing claims be “the court favor of Stevenson and de- days ty” because 164 after it this filed any fees,

' Highland attorney’s nied pending action action and while this the pointless Highland ed then request- below, court Stevenson admitted opportunity present an evidence as to Highland voluntarily paid he owed and he $10,300.78 what its fees would have been. After the suing amount it was for. ruling trial court’s on the merits in favor of payment In view of that after the parties not did return to started, prevailing Highland was party” was “the they stipulate since were able to as to regard to that cause of action. what regard- Stevenson’s evidence would be It generally party has been held that a ing attorney’s his fees. judgment whose favor an affirmative is is rendered, judgment or not whether The affirmed, below is but the initially sought for less than plaint, in the com- case is remanded with directions for the “prevailing party” a is within trial court to fix and award reasonable attorney’s meaning awarding of a statute attorney’s fee in Highland in ac- prevailing party, fees to the Peter Marich & opinion. cordance with this No costs on Associates, Powell, Fla.App., appeal Inc. v. awarded. pre- was not consequence is that the issue SWAN, K. J., THORNLEY OAKS, now appeal cannot served for be heard to concur. Judge, District Retired complain.3 him- disqualified STEWART, J., having SWAN, Retired self, participate; not did REHEARING ON Judge, sat. District HOWE, Justice: denied, but Rehearing is The Petition for arguments MAUGHAN, J., heard modified to of the opinion Court filed. opinion before died court, upon remand to provide opportunity shall be afforded and dis- Justice, (concurring HALL, Chief is not evidence that present senting). fees either be- legally attorney’s entitled to $10,300.78 De- paid Highland on cause the judgment of the would affirm the I due, past or that cember was not modification. court without for not legal justification “pre- is a that it Highland’s contention the commencement of paying it before to an and thus entitled vailing party,” action. fees, presented was not award any evidence nor was to the trial OAKS, J., HALL, J., THORNLEY C. Consequently, thereof.1 offered SWAN, Judge, concur. District K. Retired raising issue precluded STEWART, J., disqualified him- having appeal.2 first time on for the herein; SWAN, self, participate does not majority that it of the assertion Judge, sat. Retired District any not did hot fatal MAUGHAN, J., arguments but heard the what would court as to to the trial was filed. opinion died before the All ipse dixit. fee is an be a reasonable the will- than fatal is renders it other that ingness majority of part on the of a remand for the defy precedent and court to op- Highland a second affording purpose assertion prove its case. The portunity to *6 appeal. presented by begs also the issue evi- present did fail only Not fee, did not it also of a reasonable dence for the first presented theory, advance prevailing that it was also appeal, time on party. MARTINEAU, Lynn Debra Similarly, I am unable to subscribe to the Appellant, further assertion of the majority that it v. pointless request- to have ed an opportunity further evi- Mary Elliot ANDERSON and Christine J. dence as to fees after the court found in Anderson, Defendants Stevenson. Had theo- Respondents. ry, as now appeal, advanced on been duly presented trial, at 16923. may No. very well just have been as enlightened as was Supreme Court Utah. this Court in discerning that there may be more than one prevailing party given in a Sept. However, lawsuit. it matters not what the ruling of the court might been, point crucial is that the issue was not presented and upon. The unavoidable City Corp. Ensign Company, v. 2. Park Utah may not be awarded fees 1.That (1978); Edgar Wagner, Utah, given stipulation 586 P.2d 446 as to or evidence without a Utah, (1977). thereof, Finance 572 P.2d 405 see Freed the value Utah, Company, P.2d 1039 Motor v. Stoker (1975). 3.Id.

Case Details

Case Name: Highland Construction Co. v. Stevenson
Court Name: Utah Supreme Court
Date Published: Dec 15, 1981
Citation: 636 P.2d 1034
Docket Number: 17099
Court Abbreviation: Utah
AI-generated responses must be verified and are not legal advice.