The parties to this action entered into a written contract whereby the plaintiff was to furnish all labor necessary, and to complete, in a good and workman-like manner, the entire steam-heating plant of defendant’s new building in Deadwood, on or before July 15, 1899; defendant was to provide Wilks heater, hot-water tank, steam boiler, smokestack, and setting of boiler; all other material was to be furnished by the plaintiff, and boiler set ready for connections by July 1st. It was expressly stipulated that if the plaintiff failed to comply with the conditions of the contract the defendant should have the right to employ men, procure material, and complete the job at the plaintiff’s expense; that the plaintiff should forfeit $5 for each day that the contract remained incomplete after the date above specified; and that any delay in the completion of the contract, caused by the act or negligence of the defendant in not having the boiler, Wilks heater, and tank ready when wanted, should be compensated for at the s^me rate per day, after the date set for the completion of the job. Plaintiff alleges that the defendant failed to have the boiler set and ready for connections until October 5th, and thereby delayed the plaintiff in completing his contract until October 18th; that, if defendant had complied with the contract
Upon the trial the plaintiff, sustaining the allegation of damages in his complaint, confined himself solely to the number of days lost by him between July 1st and October 18th, and testified that the value of his services during that time was $5 per day. No evidence was introduced tending to show any difference in the cost of completing the contract in October over what it would have been in July. At the close of the case the defendant moved the court to instruct the jury to return a
The judgment and order appealed from are reversed.