This suit arises from two spare parts requirements contracts between the United States Army Communications & Electronics Command (“CECOM”) and Hi-Shear Technology Corporation (“Hi-Shear”). Following a trial, the Court of Federal Claims held that CECOM had breached the contracts by negligently overestimating in its invitations for bids (“IFBs”) the number of spare parts that would be required during the contract period. Hi-Shear Tech. Corp. v. United States, 53 Fed.Cl. 420, 422 (2002). The court awarded Hi-Shear damages in the amount of $17,793.56, plus interest. Id. at 445; Hi-Shear Tech. Corp. v. United States, 55 Fed. Cl. 418 (2003) (denying Hi-Shear’s motion for reconsideration).
On appeal, Hi-Shear argues that our decision in
Rumsfeld v. Applied Cos., Inc.,
BACKGROUND
I.
The two requirements contracts called for Hi-Shear to provide spare parts for the AN/TTC/TYC-39 circuit switch (“T-39 Circuit Switch”).
1
The T-39 Circuit Switch has over 3,000 individual spare parts, approximately 1,100 of which were managed by CECOM in the procurement at issue in this case.
Hi-Shear,
The acquisition packages eventually matured into IFBs. Each IFB described a one-year requirements contract, with a government option to extend the contract for up to four years. For each line item, each IFB set forth three estimated quantity ranges (Ranges A, B and C), as well as a specific estimated contract quantity.
Hi-Shear, 53
Fed. Cl. at 425. In the case of each line item, the estimated contract quantity corresponded to the “lower end of the middle” quantity range for the item.
Id.
The IFBs also stated that, in the case of each line item, bidders were to provide unit prices for each of the quantity ranges for each of the five possible ordering years.
Id.
at 424. Hi-Shear submitted bids in response to two IFBs. In doing so, in the case of each line item, it bid the
As it turned out, the requirements estimates in the IFBs failed to take into account two important factors of which CE-COM was aware, or should have been aware. Id. at 432. First, CECOM failed to consider that the level of need for parts would be affected by an increase in the number of parts on hand based on new incentives for field units to return defective or damaged parts. Id. Second, the requirements estimates did not take into account the number of parts on hand at the time the estimates were made. Id. As a result of neglecting this information, CE-COM used the base average monthly demand, rather than the net base average monthly demand for the parts involved in the procurement. Id. at 424. As a result, the spare parts requirements set forth in the IFBs, and thereafter stated in the contracts, were overestimated.
Subsequently, although CECOM extended both contracts twice, it only issued one order under contract F301 and two orders under contract F305. Id. at 425. The order under contract F301 was for $153,300.00 worth of spare parts, which represented less than twelve percent of the total estimated quantity of parts for that contract. The total value of orders under contract F305 was $92,805.97, representing less than twenty percent of the total estimated quantity of parts for that contract.
When CECOM chose not to exercise any options after the second option year under either contract, Hi-Shear filed certified claims with the contracting officer. Id. at 425, 427. Hi-Shear claimed breach of contract damages in the amount of $310,319 under contract F301 and $53,330 under contract F305. Id. In its claims, Hi-Shear sought to recover the fixed overhead and general and administrative (“G & A”) costs that it alleged it would have incurred, as well as the gross profit it stated it would have made, under each contract had the government purchased all of the estimated requirements for the base year and each of the four option years stated in the IFBs. Id. at 426.
II.
After the contracting officer denied its claims, Hi-Shear timely filed suit in the Court of Federal Claims under the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-613 (2000). Following a trial, the court held that CECOM had breached the two requirements contracts by negligently overstating, in the IFBs, its estimated requirements for spare parts. However, the court disagreed with Hi-Shear’s damages assessment and awarded only $17,793.56 in total damages for both contracts.
Before the Court of Federal Claims, Hi-Shear sought damages spread over the base year and the four option years of each contract, even though CECOM only extended each contract twice.
Hi-Shear,
As far as the base year and the exercised option years were concerned, Hi-Shear asserted that it was entitled to “the profit and burden that it anticipated in its bid and would have earned if the Government’s representations of its requirements had been true.” Id. at 438. Specifically, as it had before the contracting officer, Hi-Shear sought to recover the profit it would have made under the contracts if the government had ordered the quantity of spare parts estimated in the IFBs, plus fixed overhead and G & A costs. Id.
The Court of Federal Claims ruled first that Hi-Shear was not entitled to anticipated profits on unordered parts. The court stated: “A plaintiff that has proven that the government was negligent in estimating contract requirements, however, still bears the risk of variances in the government’s requirements due to factors other than the government’s negligence .... ”
Id.
To determine Hi-Shear’s damages, the court instead resorted to what has been referred to as the “jury verdict” method for approximating damages. The “jury verdict method” is “most often employed when damages cannot be ascertained by any reasonable computation from actual figures.”
Dawco Construction, Inc. v. United States,
The Court of Federal Claims started from the premise that Hi-Shear’s damages recovery should be based upon “what [CE-COM] would have estimated its contract requirements to be if it had not been negligent.”
Hi-Shear,
As noted, Hi-Shear’s claims included (1) fixed overhead relating to the unordered quantities and (2) gross profit related to the unordered quantities, including G & A costs.
Id.
at 442. In assessing these claims, the Court of Federal Claims relied, in part, on a government audit by the
With respect to the gross profit related to unordered quantities, the Court of Federal Claims again turned to the DCAA audit. The DCAA concluded that “based on our analyses, the contractor would have experienced a loss on both of these contracts even if all contract requirements had been ordered.” Id. at 444. The court noted that “[p]laintiff has presented no evidence that, if capitalized and amortized, the engineering costs would have been sufficiently covered by the orders the court has found it entitled to, namely, the orders the government would have estimated had it accounted for unserviceable returns over the base year and the two executed contract years.” Id. Thus, concluded the court, “plaintiff has failed to prove that it is entitled to lost profits.” Id. Consequently, Hi-Shear was not awarded any lost profits.
Finally, the Court of Federal Claims addressed Hi-Shear’s claim for G & A costs. The DCAA audit agreed with Hi-Shear’s estimate that its G & A rate was twenty-six percent. The court noted that “Hi-Shear did not incur ... any labor or material costs on the contracts for items that were not ordered. Nor has it claimed non-fixed overhead costs.” Id. Therefore, reasoned the court, “Hi-Shear may only recover G & A costs related to fixed overhead,” which amounted to twenty-six percent of the fixed overhead to which Hi-Shear was entitled, or $3,671.69. Id. The total damages award was thus $17,793.56, plus interest pursuant to 41 U.S.C. § 611 from May 12, 1997. Thus, the court awarded Hi-Shear the fixed overhead and G & A costs that it would have incurred during the base year and the first two option years if the government had ordered the quantity of spare parts that CECOM would have estimated in the IFBs if it had properly prepared its estimates. Following the denial of its request for reconsideration, Hi-Shear timely appealed to this court. We have jurisdiction pursuant to 28 U.S.C. § 1295(a)(3).
ANALYSIS
I.
The sole issue before us is whether the Court of Federal Claims erred in arriving at High Shear’s damages award: We review a damages award by the Court of Federal Claims for an abuse of discretion.
Hughes Communications Galaxy, Inc. v. United States,
On appeal, Hi-Shear argues that the decision of the Court of Federal Claims in this case is contrary to
Applied Cos.,
where we stated that an adjustment in contract price is the proper way for a contractor to recover damages for breach of a requirements contract resulting from negligently prepared government estimates.
II.
We do not agree with Hi-Shear that the decision of the Court of Federal Claims in this case is contrary to
Applied Cos.
In
Applied Cos.,
the Defense Logistics Agency (“DLA”) entered into a requirements contract to purchase refrigerant storage cylinders from Applied Companies (“Applied”). There were two types of refrigerant cylinders — one for R-12 refrigerant and one for R-114 refrigerant. In its initial request for proposals (“RFP”), DLA estimated that it would require 62,945 R-12 cylinders and 56,550 R-114 cylinders. Prior to the contract award, DLA personnel realized that they had greatly overestimated the number of cylinders required. This information, however, was not communicated to Applied or any of the other offerors. Applied was awarded the contract. Eventually, DLA ordered only about ten percent of its estimated requirements before terminating the contract for convenience, apparently prior to delivery of any cylinders.
Applied Cos.,
Applied Cos.
came to us as an appeal by the government from a decision of the Armed Services Board of Contract Appeals (“ASBCA” or “Board”). In its decision, the ASBCA held that the DLA had breached its contract with Applied by negligently failing to inform Applied that the estimates in the. RFP were inaccurate.
Id.
at 1330. The Board also stated that, during quantum proceedings, Applied could seek to recover the profits it anticipated making on the total number of cylinders that DLA estimated in the RFP.
Id.
We affirmed the Board’s ruling on liability. In so doing, we held that “to the extent that a government estimate is inadequately or negligently prepared, its inclusion without correction in a solicitation or contract constitutes a misrepresentation that, whether deliberate or unintentional, amounts to a breach of contract.”
Id.
at 1335 (citing
Womack v. United States,
We first noted the general rule that “when there has been a breach of contract, the non-breaching party is entitled to an award of damages that will place it ‘in as good a position as [it] would have been had the breaching party fully performed.’ ”
Id.
at 1336 (quoting
Wells Fargo Bank, N.A.
However, where the breach is solely in the form of inadequately or negligently prepared estimates, anticipatory lost profits are not available for the overestimated, unordered quantities.
Id.
This is because in order to recover anticipatory profits, it must be “definitely established” that without the government’s breach there would have been a profit.
Cal. Fed. Bank,
After determining that Applied was not entitled to recover anticipatory lost profits, we suggested as an alternate approach the method used in
Everett Plywood v. United States,
Thus, the Court of Claims determined that an equitable adjustment in the price of the timber Everett harvested was an appropriate remedy for the government’s breach because it placed Everett in the position it would have been in had the government not breached the contract by providing an inaccurate estimate in the prospectus. The court also allowed Everett to recover for unrecouped costs for road construction at the timber site. Id. at 434.
Having affirmed the ASBCA’s ruling that the government was hable to Applied for breach of contract, we remanded the case to that Board for proceedings on damages. We stated that if it was determined any cylinders were delivered to DLA, Applied should have the opportunity to establish that it was entitled to an equitable adjustment in the price of the cylinders. However, we continued, if it was determined that no cylinders were delivered to DLA, then Applied was limited to the remedy available to it under the contract’s termination for convenience clause.
Applied Cos.,
An equitable price adjustment recognizes that, because of economies of scale, the non-breaching party may have estimated a lower price per unit for the goods or services it contracted to deliver. As a result, the non-breaching party suffers damages for the lesser quantity of goods or services it provides at the lower price before termination. Thus, the “equitable adjustment compensates for changes by paying a contractor its increased costs resulting from the change, plus an allowance for profit on that cost.”
Id.
at 1341 (citing
United States v. Callahan Walker Constr. Co.,
We do not agree with Hi-Shear that the decision of the Court of Federal Claims in this case is inconsistent with
Applied Cos.
First, the court properly rejected Hi-Shear’s contention that it should be awarded damages computed on the base year and all four option years.
See Gov’t Sys. Advisors, Inc. v. United States,
Second, the Court of Federal Claims’ rejection of Hi-Shear’s claim for lost profits on unordered spare parts during the base year and the two exercised option years was fully consistent with
Applied Cos.
There, as just discussed, we stated that where the government’s breach of contract is in the form of inadequately or negligently prepared estimates, anticipatory lost profits are not available for the overestimated, unordered quantities. However, in rejecting Hi-Shear’s claim, the court stated: “[T]he court finds that plaintiff has failed to prove that it is entitled to lost profits.”
Hi-Shear,
It is true that we stated in
Applied Cos.
that
Everett Plyioood
“suggests the proper methodology” for determining the recovery to which a contractor is entitled when the government breaches a requirements contract by providing faulty pre-bid estimates.
Applied Cos.,
III.
We have addressed at some length Hi-Shear’s principal argument on appeal-— that the decision of the Court of Federal Claims was contrary to our decision in Applied Cos. and that Hi-Shear was entitled to an equitable adjustment in the contract price of the spare parts delivered under contracts F301 and F305. We have explained that the court’s decision was consistent with Applied Cos. Hi-Shear also makes an alternative argument, however. It contends that if it is not entitled to an equitable price adjustment, it still should recover either anticipatory lost profits in the amount of $363,649 or reliance damages in the form of its unrecouped expenditures. Hi-Shear calculates those expenditures at $298,787.
Hi-Shear asserts first that
Applied Cos.
is not controlling precedent because neither party in that case addressed the matter of an equitable adjustment and because the panel
sua sponte
raised the point.
See Boeing N. Am., Inc. v. Roche,
Turning to the merits of Hi-Shear’s alternative argument, we have already explained above in our discussion of Applied Cos. why Hi-Shear is not entitled to recover the profits it anticipated based on the quantities of spare parts estimated by CE-COM for the two contracts. That leaves Hi-Shear’s claim for reliance damages.
The DCAA audit determined that the cost to Hi-Shear to produce the number of spare parts that were ordered was $536,725, while the sum Hi-Shear received for those parts based upon its bid price was $237,938, resulting in a loss of $298,787.
Hi-Shear,
We do not think that Hi-Shear is entitled to recover its so-called reliance damages. “The underlying principle in reliance damages is that a party who relies on another party’s promise made binding through contract is entitled to damages for any losses actually sustained as a result of the breach of that promise.”
Glendale Fed. Bank, F.S.B. v. United States,
What Hi-Shear is seeking to recover — -the difference between its costs in producing the spare parts it delivered and what it was paid for those spare parts based upon its bid price — -are not reliance damages. What Hi-Shear actually is
Hi-Shear’s chief executive officer, Mr. Mooney, testified that the reason the cost of producing ordered spare parts was above the bid price was because Hi-Shear had to perform engineering for the contract that would have been capitalized and amortized over the unordered parts. As the Court of Federal Claims pointed out, however, Mr. Mooney incorrectly assumed that Hi-Shear was entitled to all of the estimated contract requirements for the base year and the four option years. Id. In short, the premise for Hi-Shear’s bid was not reasonable.
True reliance damages — in the form of expenditures made in reliance on the contract — may be recoverable when a requirements contract is terminated for the convenience of the government. According to Federal Acquisition Regulation (“FAR”) § 52.249-2, “Termination for Convenience of the Government (Fixed Price),” the government may pay to the contractor, inter alia, “[t]he costs incurred in the performance of the work terminated, including initial costs and preparatory expenses allocable thereto” and profit on that amount. 48 C.F.R. § 52.249-2(g)(2)(i), (iii) (1993). In this case, however, Hi-Shear’s contracts were not terminated for convenience; rather, they continued through the base year and the first two option years.
CONCLUSION
For the foregoing reasons, the decision of the Court of Federal Claims is affirmed.
AFFIRMED.
Notes
. The T-39 Circuit Switch is a tactical communications switch that provides automatic switching for the Tri-service Tactical Communications System.
. We stated in
California Federal Bank
that "Dlost profits are a recognized measure of damages where their loss is the proximate result of the breach and the fact that there would have been a profit is definitely established, and there is some basis on which a reasonable estimate of the amount of the profit can be made.”
. The Court of Federal Claims did not explain why it used Hi-Shear's original bid prices when recalculating the value of the contracts. We assume that it did so because Hi-Shear itself did not alter its bid prices in the face of different quantity ranges in the IFBs. In any event, Hi-Shear does not allege that it would have bid higher prices had it had the revised estimates. It merely states that it "defies common sense” that it would have made the same bid decisions, without saying what it actually would have done.
