Opinion
In this appeal, we consider the appropriate level of deference that the courts, in performing their de novo review of whether an arbitration award violates public policy, should give to the arbitrator’s factual findings. The defendant, Handy and Harman, Inc., appeals
1
from the judgment of the trial court granting the application of the plaintiff, HH East Parcel, LLC, to confirm, and denying the defendant’s application to vacate, an arbitration award rendered in favor of the plaintiff. On appeal, the defendant claims that the trial court, in confirming the award, improperly deferred to the arbitrator’s factual findings when the court concluded that a per diem
The record reveals the following undisputed background facts and procedural history. On or about December 31, 2003, the defendant sold real property located in Fairfield to the plaintiff for $8 million. The purchase and sale agreement (purchase agreement) required the defendant to demolish all existing buildings and structures on the property, and to remediate all environmental contamination on the property by December 31, 2004. The purchase agreement also pro vided that time was of the essence with regard to the remediation. Sections 14 and 15 of the purchase agreement contained a per diem clause that required the defendant to pay to the plaintiff $5000 for each day after December 31, 2004, that the defendant had failed to complete the demolition and remediation as specified therein.
Although the plaintiff paid the defendant $8 million and received title to the property, the defendant failed to complete the remediation by December 31, 2004, as agreed to by the parties. The defendant also failed to pay the necessary contractors and subcontractors for remediation services rendered by December 31, 2004, and they placed various mechanic’s liens on the property. Thus, the parties then entered into an environmental indemnification agreement (indemnification agreement) that required the defendant to indemnify and hold harmless the plaintiff for the losses caused by the defendant’s failure to complete the remediation.
Thereafter, on April 5, 2005, the plaintiff filed a demand for arbitration with the American Arbitration Association (association) pursuant to § 6 of the indemnification agreement,
2
and served a copy of that demand
on the defendant.
3
Attorney Edward V. Lahey, Jr., was selected as the arbitrator, and he conducted a two day arbitration in Stamford. At the arbitration, the defendant did not dispute its liability for breach of the purchase agreement, but did dispute the validity of the $5000 per diem clause, which the defendant claimed was an unenforceable penalty. The plaintiff contended, however, that
Shortly thereafter, the plaintiff brought this application to confirm the arbitration award pursuant to General Statutes § 52-417,
5
and the defendant filed its
application and cross motion to vacate the award pursuant to General Statutes § 52-418 (a),
6
claiming, inter alia, that “the award violate[d] public policy by awarding a draconian, limitless penalty . . . .”
7
The trial court relied on our decision in
Schoonmaker
v.
Cummings & Lockwood of Connecticut, P.C.,
On appeal, the defendant claims that the trial court improperly deferred to the arbitrator’s factual findings,
because the issue of whether the per diem clause was a penalty is a mixed question of fact and law subject to de novo review. The defendant also claims that the trial court improperly confined its review to the issue of whether the arbitrator’s findings were supported by substantial evidence, and claims that, even under that more restrictive standard of review, the evidence in the record does not support the arbitrator’s conclusion that the per diem clause was not an illegal penalty. In response, the plaintiff relies on our recent decision in
C. R. Klewin Northeast, LLC
v.
Bridgeport,
At the outset, we note that whether the trial court engaged in the correct level of review of the arbitrator’s decision presents a question of law over which our review is plenary. See id., 93; see
Most of the general principles at issue herein are undisputed, namely, that “arbitration is a creature of contract, whereby the parties themselves, by agreement, define the powers of the arbitrators. . . . Moreover, we have stated that when the parties have established the authority of the arbitrator, the extent of our judicial review of the award is delineated by the scope of the parties’ agreement. . . . When the parties have not restricted the scope of the arbitrator’s authority, the resulting award is not subject to de novo review even for errors of law so long as the award conforms to the submission. . . .
“The long-standing principles governing consensual arbitration are, however, subject to certain exceptions. Although we have traditionally afforded considerable deference to the decisions of arbitrators, we have also conducted a more searching review of arbitral awards in certain circumstances. In Garrity v. McCaskey, [223 Conn. 1 , 6,612 A.2d 742 (1992)], this court listed three recognized grounds for vacating an award: (1) the award rules on the constitutionality of a statute . . . (2) the award violates clear public policy ... or (3) the award contravenes one or more of the statutory proscriptions of § 52-418 (a). . . . The judicial recognition of these grounds for vacatur evinces a willingness, in limited circumstances, to employ a heightened standard of judicial review of arbitral conclusions, despite the traditional high level of deference afforded to arbitrators’ decisions when made in accordance with their authority pursuant to an unrestricted submission.” (Citations omitted; internal quotation marks omitted.) Schoonmaker v. Cummings & Lockwood of Connecti cut, P.C., supra,252 Conn. 426 -28.
“A court’s refusal to enforce an arbitrator’s award . . . because it is contrary to public policy is a specific application of the more general doctrine, rooted in the common law, that a court may refuse to enforce contracts that violate law or public policy. . . . This rule is an exception to the general rule restricting judicial review of arbitral awards. . . . The exception, however, is narrowly construed and ... is limited to situations where the contract as interpreted would violate some explicit public policy that is well defined and dominant, and is to be ascertained by reference to the laws and legal precedents and not from general consid
erations of supposed public interests. ... To be vacated under the narrow public policy exception, the award must be clearly illegal or clearly violative of a strong public policy. . . . Furthermore, [t]he party challenging the award bears the burden of proving that illegality or conflict with public policy is clearly demonstrated.” (Citations omitted; internal quotation marks omitted.)
C. R. Klewin Northeast, LLC
v.
Bridgeport,
supra,
The seminal case with respect to the nature of the judicial review given to a claim that an arbitration award violates public policy is
Schoonmaker
v.
Cummings & Lockwood of Connecticut, P.C.,
supra,
Our case law following
Schoonmaker
has emphasized that a reviewing court is bound by the arbitrator’s factual findings in reviewing a claim that an award rendered in a consensual arbitration violates this state’s public policy. See
State
v.
AFSCME, AFL-CIO, Council 4, Local 2663, 257
Conn. 80, 95,
The arbitrator’s factual findings are equally binding when the public policy claim has been raised before the arbitrator in the form of a defense that the underlying contract is illegal. In
C. R. Klewin Northeast, LLC
v.
Bridgeport,
supra,
We acknowledge that several Appellate Court decisions cited by the parties
In the present case, it is undisputed that the defendant’s claims implicate the clearly established public policy against the enforcement of penalty clauses in contracts. See,
e.g., American Car Rental, Inc.
v.
Accordingly, we engage in a de novo review of the arbitrator’s application of these legal principles to his factual findings. The arbitrator credited the testimony of Paul Dixon, the defendant’s negotiator, who, during negotiations, had proposed an initial liquidated damages figure of $1500, then $2500, and then finally increased that number to $5000, but commencing 180 days later than the parties originally had intended. The arbitrator then relied on the testimony of Michael Bradley, the plaintiffs negotiator, who testified that the plaintiff expected to earn $5000 per day from the property, which “is a valid proxy for damage caused by inability to use the asset acquired . . . .” Finally, the arbitrator concluded that liquidation of damages was appropriate because the party in breach retained the power to stop the damages by remediating the property. The arbitrator emphasized that the $5000 per diem figure was agreed upon by “representatives of two sophisticated businesses . . . .”
Thus, we conclude, on the basis of the facts as found by the arbitrator, that the per diem clause was a valid liquidated damages provision. In particular, we note that it was actively negotiated by the parties in an attempt to reach an agreement on the sale of the property. See
Hendricks Property Management Corp.
v.
Birchwood Properties Ltd. Partnership,
The judgment is affirmed.
In this opinion the other justices concurred.
Notes
The defendant appealed from the judgment of the trial court to the Appellate Court, and we transferred the appeal to this court pursuant to General Statutes § 51-199 (c) and Practice Book § 65-1.
The arbitration clause, § 6, of the indemnification agreement, provides: “Any disputes which the parties may have with respect to the parties’ obligations under this Agreement shall be resolved by expedited, binding arbitration, conducted by a sole arbitrator, in Stamford, CT, in accordance with the rules of the American Arbitration Association, then prevailing, or any successor organization thereto having jurisdiction and having offices in Connecticut. The parties shall agree upon the arbitrator, to resolve such dispute, within ten (10) days of a notice of dispute hereunder. If the parties shall fail to agree upon the designation of such arbitrator within such ten (10) day period, then either party may apply to the American Arbitration Association in Connecticut, or any successor organization thereto having jurisdiction and having offices in Connecticut, for the designation of such arbitrator. The designated arbitrator shall conduct such hearings and investigations as (s)he may deem appropriate and the decision of the arbitrator, absent fraud, bad faith, coercion or other misdeed, shall be conclusively binding upon the parties. Each party shall pay its own counsel fees and expenses, if any, in connection with any such arbitration proceeding, but the non-prevailing party in such arbitration, shall pay all expenses and fees of the arbitrator.”
Prior to initiating arbitration proceedings, the plaintiff had served the defendant with a written “ ‘notice of loss’ ” and demanded indemnification.
The arbitrator also ordered the defendant to report to the plaintiff concerning all contractors and subcontractors who had worked on the demolition and remediation effort, to reconcile their accounts, and to cause the satisfaction, challenge and discharge of all liens on the property. The arbitrator also directed the defendant, in accordance with the indemnification agreement, to pay the arbitration fees and expenses, although each party was to be responsible for its own attorney’s fees.
General Statutes § 52-417 provides: “At any time within one year after an award has been rendered and the parties to the arbitration notified thereof, any party to the arbitration may make application to the superior court for the judicial district in which one of the parties resides or, in a controversy concerning land, for the judicial district in which the land is situated or, when the court is not in session, to any judge thereof, for an order confirming the award. The court or judge shall grant such an order confirming the award unless the award is vacated, modified or corrected as prescribed in sections 52-418 and 52-419.”
General Statutes § 52-418 (a) provides: “Upon the application of any party to an arbitration, the superior court for the judicial district in which one of the parties resides or, in a controversy concerning land, for the judicial district in which the land is situated or, when the court is not in session, any judge thereof, shall make an order vacating the award if it finds any of the following defects: (1) If the award has been procured by corruption, fraud or undue means; (2) if there has been evident partiality or corruption on the part of any arbitrator; (3) if the arbitrators have been guilty of misconduct in refusing to postpone the hearing upon sufficient cause shown or in refusing to hear evidence pertinent and material to the controversy or of any other action by which the rights of any party have been prejudiced; or (4) if the arbitrators have exceeded their powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.”
The defendant also claimed that: (1) the award was made by an arbitrator not appointed in accordance with the parties’ indemnification agreement because of a false disclosure by the arbitrator at the time of his appointment; (2) the arbitrator had a “clear personal interest” that was not disclosed in advance; (3) the arbitrator exceeded his authority by enforcing a penalty clause, and the scope of the submission by deciding and relying upon an issue expressly not submitted to him; (4) the award was rendered untimely in violation of General Statutes § 52-416 (a); and (5) the award was made notwithstanding the defendant’s timely request for a continuance to obtain relief from an order prohibiting the offering of evidence. The trial court rejected these claims, and the defendant has not pursued them further in this appeal.
In reviewing the record, we, sua sponte, questioned the subject matter jurisdiction of the trial court over the defendant’s claims in the present case in light of our recent decision in
Bloomfield
v.
United Electrical, Radio & Machine Workers of America, Connecticut Independent Police Union, Local 14,
In
Schoonmaker,
we reasoned that “the identification and application of the public policy of this state presents considerations regarding which courts have greater expertise and knowledge than arbitrators, who are often drawn from the ranks of various professions including, but not limited to, the law. Because in this respect arbitrators and a reviewing court do not stand on equal ground, it comports with logic for the court to review the arbitrator’s interpretation of an ethics rule de novo rather than to leave it to the arbitrators themselves to attempt to apply pertinent public policy. Moreover, given that it is the role of the reviewing court to articulate the actual policy objectives that emanate from a particular rule of conduct, so too is a reviewing court better suited to evaluate whether certain facts, as found by the arbitrator, comport with the specific public policy that is at issue.”
Schoonmaker
v.
Cummings & Lockwood of Connecticut, P.C.,
supra,
We rejected the defendants’ argument that, “by applying de novo review to an arbitrator’s application of the ethics rules, we unwittingly open the floodgates of litigation to any party seeking to vacate an arbitration award that involves application of any one of the rules,” including disputes over attorney’s fees.
Sckoonmaker
v.
Cummings & Lockwood of Connecticut, P.C.,
supra,
To the extent that the defendant claims that factual determinations by the arbitrators must be reviewed anew by a trial court reviewing a public policy claim, we disagree, because we already have rejected that proposition as an “invitation to turn public policy challenges into the arbitration equivalent of a ‘mulligan’ by inviting de novo factual review of illegal contract issues.”
C.R. Klewin Northeast, LLC
v.
Bridgeport,
supra,
The “substantial evidence standard is highly deferential and permits less judicial scrutiny than a clearly erroneous or weight of the evidence standard of review.” (Internal quotation marks omitted.)
Jim’s Auto Body
v.
Commissioner of Motor Vehicles,
General Statutes (Sup. 2008) § 42-181 (c) (4) provides in relevant part: “Notwithstanding any provision of the general statutes or any regulation to the contrary, the Department of Consumer Protection shall not amend, reverse, rescind or revoke any decision or action of an arbitrator. ... In addition, either party to the arbitration may make application to the superior court for the judicial district in which one of the parties resides or, when the court is not in session, any judge thereof for an order confirming, vacating, modifying or correcting any award, in accordance with the provisions of this section and sections 52-417, 52-418, 52-419 and 52-420. Upon filing such application the moving party shall mail a copy of the application to the Attorney General and, upon entry of any judgment or decree, shall mail a copy of such judgment or decree to the Attorney General. A review of such application shall be confined to the record of the proceedings before the arbitrator. The court shall conduct a de novo review of the questions of law raised in the application. In addition to the grounds set forth in sections 52-418 and 52-419, the court shall consider questions of fact raised in the application. In reviewing questions of fact, the court shall uphold the award unless it determines that the factual findings of the arbitrator are no t supported by substantial evidence in the record and that the substantial rights of the moving party have been prejudiced. If the arbitrator fails to state findings or reasons for the award, or the stated findings or reasons are inadequate, the court shall search the record to determine whether a basis exists to uphold the award. . . .” (Emphasis added.)
This statute was enacted in 1990 in response to this court’s decision in
Motor Vehicle Manufacturers Assn. of the United States, Inc.
v.
O’Neill,
We disagree with the defendant’s reliance on
Groton
v.
United Steelworkers of America,
supra,
The trial court, therefore, did not need to conduct, in effect, appellate review of the arbitrator’s factual conclusions in the present case to determine whether they were supported by substantial evidence. This review, while commendably thorough, was unnecessary in the context of this consensual arbitration.
Parties to agreements remain, however, free to contract for expanded judicial review of an arbitrator’s findings. See
Stutz
v.
Shepard,
In support of its argument that the per diem clause is an illegal penalty clause, the defendant argues that the “self-help” provision of the purchase agreement permits the plaintiff to assume remediation responsibilities, at which point the per diem charges would stop accruing. The defendant does not, however, argue that the total liquidated damages amount itself violates public policy because the plaintiff had a duty, at some point, to mitigate those damages, rather than rely upon the per diem clause as a limitless annuity. Indeed, this decision, although concluding that the per diem clause at issue herein does not by itself violate public policy, should not be read to countenance such a practice, which would constitute an illegal penalty. See
Newington
v.
General Sanitation Service Co.,
The defendant, relying on the testimony of its counsel for the negotiation of the purchase agreement, claims that the per diem clause is an illegal penalty because the parties had characterized it throughout as a “ ‘hammer’ ” or “penalty.” See, e.g.,
American Car Rental, Inc.
v.
Commissioner of Consumer Protection,
supra,
