114 Wis. 654 | Wis. | 1902
The claims of the appellant which are necessary to be considered are: (1) That the contract which appears in the letters and telegrams was not an absolute contract to ship two car loads of coal per week, but only a contract to do their best in the usual course of business to fill orders, and that, if Hesser & Milton were prevented from shipping coal as ordered by reason of scarcity of cars or other cause beyond their control, there was no breach of the contract; (2) that the words “subject to strikes” in the telegram of September 29th were so far of an ambiguous or uncertain nature that parol evidence should have been received showing their generally accepted meaning in the coal trade.
1. As to tire proper construction to be placed upon the contract, we think that the trial court was entirely right in construing it as an absolute contract to deliver as much as two car loads per week during the year “subject to strikes,” and that the fact of a scarcity of cars constituted no excuse for the breach of the contract, no such exception to the absolute character of the undertaking having been embodied in the letters or telegrams. The material part of tire letters and telegrams will be found set forth in the statement of facts, and it does not seem necessary to repeat them here, nor to do anything more than state our conclusions on the subject.
2. It is elementary law that the construction of written contracts whose words are plain is tire proper function of the court, but, if words or phrases are used therein which are technical, or have gained a definite and peculiar meaning in a certain trade by general usage, extrinsic evidence may be received, showing that such meaning has been acquired, and what it is. 2 Jones, Ev. §§ 461, 462. The words “subject to strikes” cannot be said to be entirely definite in their
It is said, however, by respondent, that this ruling was not prejudicial, even if it was erroneous, because it is said that it appears in the case that the defendant was compelled to expend, in order to fill the pump-house contract* more than $500 in excess of the contract price before the happening of the strike in Hesser & Milton’s mines. If this fact did appeal’, it would doubtless be a complete answer to the claim of prejudicial error; but a very critical review of the bill of exceptions shows that it does not appear. The only evidence on the question is the bare statement that defendant purchased -from outside parties, to fill the pump-house contract,
In this state of the case it cannot be held that the ruling out of the proposed evidence as to the meaning of the strike clause was-not prejudicial.
By llie Court. — Judgment reversed, 'and action remanded for a new .trial.