114 N.Y.S. 1107 | N.Y. App. Div. | 1909
In this action to foreclose a mechanic’s lien there are several appellants. Their claims relate to the distribution of a fund in the hands of the comptroller of the city of Hew York. On February 5, 1903, the firm of Williams & Gerstle entered into a contract with the board of education of the city of Hew York and the city of Hew York for installing heating and ventilating ¡apparatus in a public school for the sum ,of $23,995. Williams & Gerstle proceeded with the execution of the contract until February or,March, 1905, when they abandoned it. The city thereupon proceeded to complete the work at the expense of the contractors. When the work was finally completed there remained unexpended a fund of $6,049.25, applicable to the payment of lienors and others who might be able to establish claims thereto.
Prior to the abandonment of the work by the contractors and on April 9, 1904, the plaintiff had filed a lien for $2,200. The regularity, validity and priority of this lien are not questioned. On
The judgment appealed from awards the plaintiff, the Johnson Service Company, and the American Radiator Company,, the full amounts for which they filed liens, thus exhausting the fund applicable to the payment of liens. As to the claim of the attaching creditor, the Heine Safety Boiler Company, it is found that on June 1, 1904, the date of the levy of the attachment, there was no claim in existence in behalf of Williams & Gerstle against the citj upon which a valid levy could be made. The facts, so far as they bear upon the finding; are as follows: On January 26,1904, before any lien or attachment had been filed or served, work had been done by the contractor of the estimated value of $2,549.25, which was retained by the city under the clause in the contract which permitted it to retain until the full completion of the contract, fifteen per cent of the amounts earned by the contractor. On May 4, 1904, after the filing of plaintiff’s lien, but before the service of the Heine Safety Boiler Company’s attachment, there had been certified as having been earned by the contractor $2,350, of which eighty-five per cent, or $1,997.50, Was presently payable, the balance being retained to await the completion of the contract. A mechanic's lien attaches primarily to whatever may be due to the contractor when the lien is filed. If nothing is then due, or if the amount due is insufficient to meet the lien, it attaches to any amount which may subsequently Recome due under the contract. (Van Clief v. Van Vechten, 130 N. Y. 571.) An attachment, on the other hand, applies only to an amount which has become an indebt
“ -In order to enable the Contractor to prosecute the work advantageously, the said sum or amount shall be paid in installments as the work progresses, as follows, viz.: In installments of -eighty-five per centum (85 per cent) of the value of the work performed upon application made in writing to the Superintendent by the Contractor, together with -an accurate schedule in detail of the materials furnished and work done since the last preceding payment. ■
“ The final payment of the balance due and unpaid under the contract, including the fifteen per cent-(15 per cent) of the total amount of the-contract price, shall be payable thirty days after the contract is fully performed, completed and the entire work accepted, and when the work is all complete, as herein provided, ánd the'keys delivered to the Superintendent of School Buildings.”
Beading this whole clause together, it will be seen that we have the case of a contract for a lump,sum, no part of which is to become due or payable until the completion of the contract, except that a percentage of the amount.earned from time to time is to be advanced “in.order to enable the Contractor to prosecute the work advantageously.” If nothing had been said about the advancements as the work progressed, it would be quite clear that nothing would be due to the contractor until the completion of the contract. The fact that eighty-five per cent of the apparent estimated value of the
A different question is raised by the appeal of the American Radiator Company whose lien was filed after that of the Johnson Service Company. The contract of the latter company was to install its system of temperature regulation in the school building, a 'contract which involved the performance of labor as well as the furnishing of .materials. The Americair Radiator Company sold steam radiators to the contractors, but performed no work on the building. ■ The claim of the American Radiator Company is that it is entitled as a materialman to a preference over all sub-contractors irrespective of any question as to priority in filing liens, Section 2 of the Lien Law (Laws of 1897, chap. 418) defines the several terms used in that act. .. Under it the term “ sub-contractór ” is defined to mean “a person who enters into a contract for the improvement of such real property with a contractor or with a person who has contracted with or through such contractor -for the performance of his contract or any part thereof.” A “ material man ” is defined as “ any person, other than a contractor, who furnishes material for such improvement.” Under these definitions it is clear that the Johnson Temperature Regulating Company was a sub-contractor and the American Radiator Company was a material-man. By chapter 419 of the Laws of 1897 certain sections relating to liens and the enforcement thereof were added to the Code of Civil Procedure, and it was provided that they were to be construed with
The plain meáning of this section appears to be that material-men are now included in the favored class, which formerly comprised laborers alone, and are awarded a preference over .other lienors irrespective of the date of the filing of the liens. (See Hedden Const. Co. v. Proctor & Gamble Co., 62 Misc. Rep. 129.) It would be idle to speculate upon the reasons for or the justice of this distinction. It is sufficient that the Legislature has so decreed in plain terms. All of the lienors in this case dealt directly with the principal contractors, and in that regard stand
Ingraham, Laughlin and Clarke, JJ., concurred; Patterson, P. J., not voting.
Judgment modified as directed in opinion, and as so modified affirmed, with costs as stated in opinion. Settle order on notice.