¶ 1 Appellant, Louise Herczeg, appeals from the trial court’s Order granting Ap-pellee’s, Bankson Engineers, Inc. (Bank-son), motion to dismiss based upon an affidavit of non-involvement filed pursuant to 42 Pa.C.S.A. § 7502. Appellant challenges the Order as violative of the coordinate jurisdiction rule. Alternatively, she asserts the trial court misapplied 42 Pa. C.S.A. § 7502 and erred as a matter of law in refusing to find Bankson owed the decedent a duty under the facts of this case. We affirm.
¶ 2 The facts and procedural background may be summarized as follows. In February of 1995, Hampton Township Municipal Authority (Hampton), as owner, retained Bankson to draft the plans and specifications for a water line extension project at Francis Drive in Hampton Township. Allison Park Contractors, Inc. (Allison Park) was hired by Hampton as the general contractor for the project. On March 20, 1995, Stephen M. Wagner, Appellant’s decedent who was employed by Allison Park, was working in an unshored trench approximately seven feet deep laying pipe when a cave-in occurred that completely engulfed Mr. Wagner. Rescue workers were able to extricate Mr. Wagner whereupon he was life flighted to a nearby hospital. Mr. Wagner never regained consciousness and succumbed to his injuries two months later.
¶ 3 On March 14, 1997, Appellant filed a wrongful death and survival action on behalf of the decedent and his parents against Hampton and Bankson. The complaint alleged Bankson designated itself as Hampton’s representative during the project and a representative of Bankson’s, a professional with substantial knowledge, was present at the site on the morning of the accident. It is alleged Bankson’s representative had actual knowledge that Appellant’s decedent was working in a dangerously unsafe trench in that the trench contained no shoring or bracing in violation of Bankson’s own specifications, federal law and industry practices. It is further claimed the risk of serious injury or death was reasonably foreseeable and Bankson’s representative took no steps to warn the workers or to correct the situation. Therefore, under these circumstances Appellant asserts Bankson breached a duty owed to her decedent and is liable for the resultant death of Mr. Wagner.
¶ 4 On April 2, 1997, Bankson filed preliminary objections to the complaint, including a demurrer to the negligence count. On July 1, 1997 after consideration of the parties’ briefs and oral arguments thereon the Honorable Joseph Jaffe denied the demurrer and struck the punitive damages claim without opinion or explanation. On July 21, 1997, Appellant filed an amended complaint. In Bankson’s answer to the amended complaint, Bankson denied the allegations of negligence asserting that it had no knowledge of an unsafe condition, no duty regarding the allegations and that none of its services were involved in the cause of the accident. Moreover, Bankson alleged that it had no authority to control the contractor’s work and never assumed by contract or conduct any responsibility for job site safety.
¶ 5 On March 30, 1998, Bankson filed a Motion to Dismiss based on affidavits of non-involvement as permitted by 42 Pa. C.S.A. § 7502. In this motion, Bankson
If [Appellant] does not produce such evidence, I will consider [Appellant’s] second claim that tort law imposes liability where a professional possesses special knowledge that a construction activity that he or she personally observes poses a clear, present, and imminent risk of harm to a worker at the site. In considering [Appellant’s] second claim, I will assume to be true [her] allegations that the representative of Bankson Engineers was a professional with special knowledge who personally observed construction activity that posed a clear, present, and imminent risk of harm. Consequently, I will be considering only the legal issue of whether these allegations state a cause of action.
Id.
¶ 6 Appellant conceded she was not attempting to fasten liability based upon contractual duties or the assumption of a duty by conduct, and thus did not file any affidavits or depositions. Appellant instead merely relied on the court’s statement that it would consider her liability theory as if all her allegations of fact were true. On December 28, 1998, the court entered an order granting Bankson’s Motion to Dismiss. However, this order was interlocutory because Hampton remained in the case. Appellant sought and was granted reconsideration. However, before ruling on the reconsideration Hampton was voluntarily dismissed from the action by Appellant’s filing of a praecipe with the Prothonotary on July 29,1999. On August 29, 1999, the court entered an order stating that “[u]pon the Prothonotary’s prior entry of [Appellant’s] voluntary discontinuance and dismissal of [Hampton], and following reconsideration of my December 28,1998 Memorandum and Order of Court, for the reasons set forth in my December 28,1998 Memorandum, [Appellant’s] action against Bankson Engineers, Inc. is dismissed pursuant to 42 Pa.C.S. § 7502.” Certified Record at 66 (Exhibit “B” attached to Notice of Appeal). This timely appeal followed.
¶ 7 Appellant raises the following issues: 1. Does Pennsylvania law impose a duty to act reasonably on a construction site engineer where the engineer observes and has actual knowledge of a safety hazard related to the project that violates the engineer’s own design specifications and where the engineer recognizes that imminent injury or death is reasonably foreseeable?
2. Were the issues raised by Bank-son Engineers, Inc.’s Motion to Dismiss Based on Affidavit of Non-Involvement resolved in [Appellant’s] favor by a previous court order overruling [Appellee’s] preliminary objections, and therefore, binding upon the parties and the court under the Coordinate Jurisdiction Rule?
Appellant’s Brief at 5. We will address these issues in inverse order.
¶ 8 Initially, we note this Court has not previously reviewed the procedures invoked by the trial court in addressing a motion to dismiss pursuant to 42 Pa.C.S.A.
¶ 9 We begin our analysis by first addressing whether the coordinate jurisdiction rule was violated. Appellant contends the legal authorities cited and arguments advanced in support of Bankson’s motion to dismiss pursuant to 42 Pa.C.S.A. § 7502 were essentially identical to those cited and argued in support of its preliminary objections in the nature of a demurrer. Thus, the subsequent Order entered by Judge Wettick impermissibly overturned the prior order overruling Bank-son’s preliminary objections. We cannot agree.
¶ 10 Ordinarily, judges of coordinate jurisdiction sitting in same case should not overrule prior decision of another judge of that jurisdiction.
Alco Parking Corp. v. Public Parking Auth. of Pittsburgh,
Where the motions differ in kind, as preliminary objections differ from motions for judgment on the pleadings, which differ from motions for summary judgment, a judge ruling on a later motion is not precluded from granting relief although another judge has denied an earlier motion. However, a later motion should not be entertained or granted when a motion of the same kind has previously been denied, unless intervening changes in the facts or the law clearly warrant a new look at the question.
Abbott v. Anchor Glass Container Corp.,
¶ 11 In the present case the motions differed in kind. “When reviewing preliminary objections the trial court looks to the pleadings, but, in considering a motion for summary judgment the trial court weighs the pleadings, depositions, answers to interrogatories, admissions and affidavits.”
Rosenfield,
¶ 12 Having determined the procedure utilized by the trial court was in the nature of a motion for summary judgment, we now proceed to examine whether the instant Order was properly granted. Our standard of review following the grant of summary judgment is well settled. Summary judgment may only be granted in cases where it is clear and free from doubt the moving party is entitled to judgment as a matter of law.
Sebelin v. Yamaha Motor Corporation,
¶ 13 In order to establish a cause of action in negligence, a plaintiff bears the burden of demonstrating that there was a duty or obligation recognized by law, breach of that duty by the defendant, a causal connection between the defendant’s breach of that duty and the resulting injury, and actual loss or damage suffered by the complainant.
First v. Zem Zem Temple,
¶ 14 Whether a duty exists under a particular set of facts is a question of law.
Huddleston v. Infertility Center of America, Inc.,
When considering the question of duty, it is necessary to determine whether a defendant is under any obligation for the benefit of the particular plaintiff ... and, unless there is a duty upon the defendant in favor of the plaintiff which has been breached, there can be no cause of action based upon negligence. Whether a duty exists is ultimately a question of fairness. The inquiry involves a weighing of the relationship of the parties, the nature of the risk and the public interest in the proposed solution. Our duty analysis depends on many factors and is necessarily rooted in public policy considerations, i.e., our ideas of history, morals, justice, and society in general in determining where the loss should fall.... Furthermore, duty is only a word with which we state our conclusion that there is or is not to be liability; it necessarily begs the question. ... To give it any greater mystique would unduly hamper our system of jurisprudence in adjusting to the changing times.
Campo v. St. Luke’s Hosp.,
¶ 15 The courts of this Commonwealth have consistently refused to impose a duty on design professionals to protect workers from hazards on a construction site unless there was an undertaking, either by contract or course of conduct to supervise or control the construction and/or to maintain safe conditions on the site.
Young v. Eastern Engineering and Elevator Co., Inc.,
¶ 16 Appellant argues the traditional principles of negligence law should imposes a duty on an engineer to exercise reasonable care for the safety of the general contractor’s workers when the engineer has actual knowledge of dangerous working conditions that create a foreseeable risk of serious injury to those worker’s. She submits this is true even where the contract places the responsibility for safety on the general contractor and the engineer’s plans and specifications did not create the dangerous conditions. We cannot agree.
¶ 17 Appellant offers in support of her argument the cases of
Balagna v. Shawnee County,
¶ 18 Nonetheless, even the Balagna court recognized:
that the great weight of authority supports the rule that an [engineer] does not, by reason of his supervisory authority over construction, assume responsibility for the day-to-day methods utilized by the contractor to complete the construction. The [engineer’s] basic duty is to see that his employer gets a finished product which is structurally sound and which conforms to the specifications and standards. Any duty that the [engineer] may have involving safety procedures of the contractor must have been specifically assumed by the contract or must have arisen by actions outside the contract. In determining whether the [engineer’s] contractual duty to supervise the construction includes the safety practices on the jobsite, the [engineer] may intentionally, or impliedly by his actions, bring the responsibility for safety within his duty of supervision. The factors which would appear to be relevant in any case where an attempt is made to expand the [engineer’s] liability beyond the specific provisions of the employment contract are set forth [as follows:]
(1) actual supervision and control of the work;
(2) retention of the right to supervise and control;
(3) constant participation in ongoing activities at the construction site;
(4) supervision and coordination of subcontractors;
(5). assumption of responsibility for safety practices;
(6) authority to issue change orders; and
(7) the right to stop the work.
Balagna,
at 1074-1075,
¶ 19 In Carvalho, supra, another trench cave-in case, the New Jersey Supreme Court reached a similar conclusion. Specifically, the court stated:
We conclude that considerations of fairness and public policy require imposing a duty on [the engineer] to exercise reasonable care to avoid the risk of injury on the construction site. The risk of serious injury from the collapse of an unstable trench was clearly foreseeable. [The engineer] had explicit responsibilities to have a full-time representative at the construction site to monitor the progress of the work, which implicated work-site conditions relating to worker safety. Those responsibilities related to the condition of trenches, the handling of utility lines crossing trenches, and whether measures to shore up and stabilize trenches through the use of a trench box were necessary. The engineer had sufficient control to halt work until adequate safety measures were taken. There was a sufficient connection between the engineer’s contractual responsibilities and the condition and activities on the work site that created the unreasonable risk of serious injury. Further, the engineer, through its inspector, was on the job site every day, observed the work in the trench, and, inferably, had actual knowledge of the dangerous condition.
Carvalho,
¶ 20 We are not persuaded that the rationales expressed in these cases warrant the establishment of a new rule of law fastening liability based strictly upon an assertion of actual knowledge of unsafe work-site conditions. At least with respect to
Carvalho
the presence of actual knowledge of the risk of harm was but one of the elements considered in the court’s assessment of the fairness of imposing a duty of care under the circumstances. Other factors considered were the relationship between the parties and the element of control flowing from the relationship and the opportunity and capacity of the defendant to have avoided the risk. A closer examination of
Carvalho
reveals the court placed equal if not greater weight on the existence of conduct by the engineer, combined with its contractual responsibilities, which the court found implied that the engineer assumed responsibility for work-site safety. For instance, the court observed that the engineer was contractually required to be at the site everyday to monitor the progress of the work.
Carvalho,
¶ 21 The instant case presents a very different factual scenario. Other than to make two visits per month to observe the progress and quality of the work, Bankson had no contractual agreement with Hampton or Allison Park to supervise the work or provide safety oversight. Further, Bankson was not required to have a full-time representative on site. Neither did Bankson participate in, nor interfere with, the means or methods of
¶ 22 In general, Balagna and Carvalho do not represent a significant departure from the present state of Pennsylvania law on this subject. However, we reject any notion that a duty arises based solely upon an engineer’s actual knowledge of dangerous conditions. Stated another way, such knowledge, in and of itself, does not create a tort duty. The decisions of the appellate courts of this Commonwealth concerning a design professional’s duty are not dependent upon the presence or absence of actual knowledge of unsafe working conditions. We believe such a notion adds nothing new to the duty analysis. If someone is under no legal duty to act, it matters not whether that person is actually aware of a dangerous condition. See Restatement (Second) of Torts § 314 (1965) (defining what is known as the common law nonfeasance rule). Conversely, if someone by contract or course of conduct has undertaken the responsibility for worker safety that person may still be liable even in the absence of actual knowledge of the dangerous condition if they should have known of the condition. “Actual knowledge” in our view merely relates to the element of the foreseeability of the risk of harm. Thus, we would agree with the trial court’s assessment that “there is not a great deal of difference between an ‘actual knowledge’ standard and a ‘should have known’ standard”.... Trial Court Opinion and Order of Court, 12/28/98, at 14. Even assuming, as we must, that Bankson had actual knowledge of the unsafe nature of the trench, it does not follow that we must hold Bankson responsible for the safety of the construction workers where those responsibilities were expressly undertaken by the contractor. This is especially true where the facts do not indicate the engineer took any actions that can be construed as impliedly assuming responsibility for construction-site safety. Accordingly, we find no error in the trial court’s Order dismissing Bankson from the case.
¶ 23 Order affirmed.
