65 A. 6 | Md. | 1906
On October 16th, 1902, the plaintiffs who were the successful bidders for the erection of the State House Annex at Annapolis, entered into a written agreement with one of the defendants, George Jewell, to haul all the material needed for the erection of said annex, and to lay all the bricks used therein for certain payments, and at certain prices set forth in said agreement, and by the terms of said agreement the said Jewell was to furnish, within ten days after its execution, to the plaintiffs, a corporate bond in the penalty of four thousand dollars, conditioned for the faithful performance of his agreement. On October 21st, 1902, the required bond was executed by Jewell, and by his co-defendant in this suit, The United States Fidelity and Guaranty Company, and was delivered to the plaintiffs, and thereupon in due course, the said Jewell began the performance of said contract, and continued therein until May 6th, 1903, when he ceased to supply any bricklayers for the prosecution of said work, and never afterwards did, or attempted to do any work under said contract. This action on his part grew out of the fact that on May 6th, 1903, the plaintiffs notified Jewell that as they had then paid him more money than the contract called for at that time, he should look elsewhere for his pay roll, but as he did not provide for it, the men stopped work that night. On the following Tuesday, however, the plaintiffs paid the men up to May 6th, but they still refused to resume work until paid for waiting time. Thereupon, on May 11th, the plaintiffs sent a written notice to Jewell that as he had refused to furnish the necessary labor to prosecute the work, and had notified plaintiffs of his intention to abandon the same, that they should proceed on Friday, *275 May 15th, at 8 A.M., to provide the necessary labor therefor, and that the cost of the same would be deducted from any money that should become due him. To this notice no reply was ever received. On May 12th, 1903, the plaintiffs sent to the United States Fidelity and Guaranty Company a copy of the above notice to Jewell, and informed said company that as Jewell had failed to comply with his said contract, they should proceed to complete said work at his expense, holding said company as surety on said bond; and on May 13th, 1903, a second written notice was sent said company by the plaintiffs, stating that Jewell had abandoned the work, and that plaintiffs should hold said company financially responsible for any losses, delays or other expenses connected with his failure to abide by the terms of said contract. Receiving no reply, and nothing being done towards resuming said work, the plaintiffs then made a new agreement for the performance of said work, with Wm. E. Feldmeyer, by whom the same was fully performed at the expense of the plaintiffs, and upon the completion of said work, so performed, at reasonable and proper prices, the cost thereof, after deducting the amount due for completing the same under the terms of the agreement with Jewell, exceeded, by the sum of $4,189.93, the sum which would have been due said Jewell for the same work under said contract, and this suit was brought on said bond to recover the penalty thereof, it being less than the cost of completing said work. The declaration was in the usual form, setting out the condition of the bond, and its breach by Jewell in not hauling the materials and laying the brick as required by the bond.
The defendants pleaded that the bond was given as a security for the faithful performance of the contract of October 16th, 1902; that by said contract it was a condition precedent to the continuance by Jewell in the performance of the work thereunder, that certain specified payments should be made said Jewell by the plaintiffs at certain designated times, which payments the plaintiffs failed and refused to make as required by said contract, and that Jewell had not refused or failed to *276 keep and perform said contract, and did not commit any breach of said bond. The plaintiffs replied that they did make all payments as they became due and payable under said contract, and that said Jewell did commit the breaches of his obligation as set forth in the declaration. Issue was joined on this replication, and a verdict was rendered in favor of plaintiffs for $5, and from the judgment entered on this verdict, the plaintiffs have appealed.
The whole case, and all the exceptions, turn upon the construction of the following clause in the agreement of October 16th, 1902:
"And it is further agreed that should the said George Jewell at any time refuse or neglect to supply a sufficiency of properly skilled workmen to prosecute said work with promptness and diligence, or fail in the performance of any of the agreements herein contained, such refusal, neglect or failure being certified to by the architects, the said Henry Smith and Sons shall be at liberty, after three days written notice to the said George Jewell, to provide any such labor, and deduct the cost thereof from any money then due, or that may thereafter become due to the said George Jewell under this contract. And if the architects shall certify that such refusal, neglect or failure, is sufficient ground for such action, the said Henry Smith Sons shall be at liberty to terminate the employment of the said George Jewell on said work, and to enter upon the premises, and to take possession for the purpose of completing said work under this contract, and to employ any other person or persons to finish the work. And in case of the discontinuance of the employment of the said George Jewell, he shall not be entitled to any further payments under this contract until the work shall be wholly finished, at which time, if the unpaid balance of the amount to be paid under this contract shall exceed the expenses incurred by the said Henry Smith Sons in finishing the work, such excess shall be paid to the said George Jewell; but if the expenses shall exceed such unpaid balance, the said George Jewell shall pay the difference to the said Henry Smith Sons. Suchexpenses shall be audited *277 and certified to by the architects or superintendent, whose certificate thereof shall be conclusive upon the parties."
The proof that Jewell abandoned the work deliberately, and without any valid excuse therefor, is positive and full, and due notice having been given by the plaintiffs of their purpose to complete the work at his risk, they are entitled to recover the difference between the reasonable cost of completion, and the balance of the contract price unpaid, unless there is something in the agreement in this case which forbids such recovery.Davis v. Ford,
This constitutes the first exception.
The plaintiffs then offered to prove by one of them that they had no control of, or authority over the architects of the annex, when the agreement of October 16th, 1902, was made, nor subsequently, and that said architects were not their agents or employees, to which the defendants objected, and the Court sustained the objection. This constitutes the second exception.
The plaintiffs then offered to prove by competent witnesses, the making of the contract with Feldmeyer to complete the work abandoned by Jewell, after due notice according to the agreement with Jewell, the completion of the work by Feldmeyer; the payment to him of the actual cost of labor and material, with a commission of 7 1/2 per cent for use of tools and supervision according to the terms of the agreement with him; that all these payments were reasonable and proper amounts for work and material furnished, and for supervision; *278 and that the amount of such payments after deducting the amount due and unpaid for completing the work under Jewell's contract, amounted to $4,182.93 in excess of what would have been due Jewell for the same work, and exclusive of $700 paid Jewell's men at the time he abandoned his contract, but the plaintiffs declined to furnish evidence that the amounts paid Feldmeyer were ever audited or certified by the architects named in their contract with the State, to which the defendants also objected, and the Court sustained the objection, and refused the offer of proof.
This constitutes the third exception.
At the close of the plaintiff's case, the defendants, without offering any evidence offered two prayers: 1st. That there was no evidence legally sufficient under the pleadings to entitle the plaintiffs to recover. 2nd. That there was no evidence legally sufficient under the pleadings, to show the plaintiffs had sustained any actual damage by reason of the alleged abandonment of the work by Jewell, and that the recovery could only be for nominal damages.
The Court refused these prayers, but granted the following instruction of its own in lieu of those offered:
"The jury are instructed that the plaintiffs have offered no evidence legally sufficient under the pleadings, to show the amount of the damages, if any, sustained by them by reason of the alleged abandonment by the defendant, Jewell, of the written contract between him and the plaintiffs, dated October 16th, 1902, offered in evidence, and that therefore the verdict of the jury must be for nominal damages only." The principal, and a controlling question, therefore, if decided in favor of the plaintiffs, is whether the clause in question has any application to a right of action for breach of the agreement arising from the abandonment of the work by Jewell.
No case in this Court has been cited in which that question has been decided, but it is well settled that wherever one construction will sustain, and another will oust the jurisdiction of the Courts, the former will be adopted if it can be done consistently with the language of the agreement. *279
In Lauman v. Young,
In Fontano v. Robbins, 18 Appeal Cases, Dist. of Columbia, 417, the Court said, "Special stipulations submitting the demands of a contractor to the adjudication of supervising architects and engineers, though enforceable, are in derogation of common right and the ordinary freedom of action, and must clearly appear to be within the intention of the contract. Construction, in case of doubt, is in favor of one resisting enforcement."
And in Gubbins v. Lautenschlager, 74 F. 167, the Court said: "Citation of authority is unnecessary for the legal proposition that contracts are not literally construed for the purpose of finding therein provisions debarring parties from access to the Courts for settlement of controversies."
With these principles in view, let us examine the paragraph of the agreement in this case which gives rise to the controversy.
An analysis of this paragraph will show that it is divisible into two clauses, providing for two distinct methods of procedurein case of the contractor's failure to prosecute the work in themanner prescribed by the contract, but making no provision for his abandonment of the contract.
The first clause provides that in event of his failure to supply a sufficiency of properly skilled workmen to prosecute said work with promptness and diligence, or in the performance of any of the agreements contained in said contract, such refusal, neglect, or failure, being certified to by the architects, the plaintiffs should be at liberty, after three days written notice *280 to the contractor to provide any such labor and to deduct the cost thereof from any money then due, or thereafter to become due to said contractor. In such case, nothing else appearing, the contractor would be at liberty to proceed with the work, in the manner he deemed a compliance with his contract, while the plaintiff could supply the deficiency in skilled workmen, or perform the labor totally neglected by the contractor, at the expense of the contractor. The second clause provides that if the architect shall certify that such refusal, neglect or failure, is sufficient ground for such action, the plaintiffs shall be at liberty to terminate the whole employment of the contractor, and complete all the work either themselves, or by the employment of any other person for that purpose. And that in case of the discontinuance of the contractor's employment by the plaintiffs, that he should be entitled to no further payments until the work was completed, when, if the unpaid balance under the contract should exceed the expenses incurred by plaintiffs in finishing the work, such excess should be paid him; but if such expenses should exceed such unpaid balance, the contractor should pay the difference to the plaintiffs. The paragraph then concludes. "Such expenses shall be audited and certified to by the architects or superintendent, whose certificate shall be conclusive between the parties." The expenses thus required to be audited and certified, are those, and those only, incurred under the two methods of procedure above stated. The plaintiffs took neither of these methods. The contractor however took a course, which however satisfactory to him was not provided for by the agreement of the parties. He abandoned his contract altogether, of his own volition, and in doing so, he remitted both the plaintiffs and himself to the ordinary methods of procedure, and to the ordinary rules of evidence in actions for the breach of contract. This we think is the plain and reasonable interpretation of the paragraph in question. The first clause provides for only a partial failure of performance by the contractor, not regarded by the architects as sufficient ground for discontinuing or terminating his employment. The second *281 clause provides for such discontinuance or termination of employment, and it is obvious that such discontinuance for the purpose of bringing the parties within the terms of this clause, could only be worked by the act of the plaintiff. The remedy provided by this second clause is a summary and arbitrary remedy, and when exercised, it is only reasonable and just that some means of protection against unreasonable changes, should be provided for a contractor displaced against his will. But when, of his own volition, he abandons his contract, and forces upon the other party the necessity either of personally completing the work, or securing another contractor, the original contractor has no claim to such consideration.
We should be prepared to adopt the construction above given, as sound in principle, if there were no authority in its support, and we have found no decisions in this State upon the question, but there is ample and satisfactory authority for it elsewhere. In Lauman v. Young, supra, there was a contract for the construction of a section of a railroad, which contract provided that the quantity of work to be done, and the amount of compensation at prescribed rates, should be determined by the engineer "who should decide all disputes arising under the contract," and that his decision should be final. The Court said: "In order to oust the jurisdiction of the Courts, it must clearly appear that the subject-matter of the controversy is within the prospective submission," and the submission was held not to embrace a claim for damages for refusing to permit the contractor to proceed with the execution of the work. In explaining the reasons for this conclusion, the Court said: "The words, `all disputes,' are clearly controlled by and limited to the distinctly enumerated grounds of anticipated dispute in the same sentence, which are so defined that these general words have no force or meaning, unless they relate to anticipated disputes arising out of the work to be done, and the compensation to be paid. The engineer was to decide every question that could arise as to the execution of the contract by the contractor. Why particularize if the matter is to be controlled by a general provision? The engineer had no *282
jurisdiction if there was no execution of the contract by the plaintiff." In Dobbling v. York Springs R.R.,
In McGovern v. Bockins, 10 Phil. 438, cited in Dobbling v. York Springs R.R., supra, where there was a similar contract, the Court said: "We cannot conceive that the language of this agreement contemplates that the estimate of the engineer should be given on the rescission of the contract. It would not be a natural construction of it. It was never intended that the engineer should usurp the province of the jury, and upon the rescission of the contract, determine the contractor's damage for the loss of his contract."
In Fuller Co. v. Doyle and the American BondingCompany, 87 F. 687 (Eastern District of Missouri), the language of the contract was almost identical with that before the Court, there being no material difference. It provides that if the contractor should fail to supply a sufficiency of properly skilled workmen, or materials of proper quality, or to prosecute the work with due diligence, the owner might upon securing a certificate from the architect to the fact of such failure, and upon three days notice to the contractor, enter upon the premises and complete the work; and it was held that such a provision contemplates a case where the contractor claims to be complying with his obligation, and not a case where the contractor absolutely abandons the work, and voluntarily surrenders the premises to the owner for its completion. *283
It is quite clear, as was said in Hamilton v. Liverpool London Ins. Co.,
We have examined all the cases cited by the appellees in support of their argument, and one of them does unequivocally sustain them, but the others, we think, can be plainly discriminated from the case at bar.
In DeMattos v. Jordan,
In Tally v. Parsons,
The case of the American Bonding Company v. Gibson County, 127 F. 671, decided in the West. Dist. of Tenn. was upon a contract identical with the present, and with that in Fuller v.Doyle, 87 Fed. Rep, supra. There the contractor did all the work except that covered by the final payment, after which he abandoned the work, and the architect's certificate was held necessary to a recovery by the owner. The Court attempted to discriminate that case from the Fuller case, on the ground that the contractor had nearly completed the work. That fact, however, cannot alter the legal principle governing the construction of the contract. The attempted discrimination is not satisfactory to us, and we prefer to follow the earlier decision in the Doyle case. The rulings upon the testimony, as well as upon the prayers, were all made upon the same erroneous construction of the contract, and the judgment must therefore be reversed.
Judgment reversed with costs to the appellants above andbelow, and new trial awarded. *285