230 Mass. 456 | Mass. | 1918
The record recites that the defendant’s exceptions “are intended only to raise the question whether the letter from the architects to the plaintiff of March 16, 1912, could be found to be a final certificate under the'terms of the contract and whether it precludes the defendant from recouping for damages.”
The auditor found that the defendant had suffered damages because the building had not been constructed in all details as required by the contract, but he apparently did not make any assessment because he ruled, that “the defendant was precluded by the final certificate from recoupment for such damages.” • The tenth article reads, “It is further mutually agreed between the parties hereto that no certificate given or payment made under this contract, except the final certificate or final payment, shall be conclusive evidence of the performance of this contract, either wholly or in part, and that no payment shall be construed to be an acceptance of defective work or improper materials.”
The uncontradicted evidence, to the admission of which neither party objected, shows that during construction many changes were made, and “extras” ordered which were the subject of discussion between the architects and. the plaintiff, and that during the period preceding the date of the action the amounts in dispute had not been settled or referred to arbitration as provided for in article twelve. The defendant however occupied the building at some time previous to the date of a letter that one of the architects wrote enclosing’a letter which he proposed sending to the plaintiff, to which the defendant replied, “Your letter of acceptance” to the plaintiff “is correct in accordance with the understanding, . . .” and thereupon the letter was forwarded which is relied on as being the final certificate required under articles nine and ten. The material portions state, that “the building . . . which you have just completed for the . . . company is accepted subject, however, to the provision that the various items mentioned in our conversation with your Mr. Baffrey and with Mr. Freeman are satisfactorily attended to at once.” The items are then enumerated, and before bringing suit the plaintiff as the defendant concedes complied with these requirements. But, notwithstanding the letter, the correspondence thereafter between the defendant and the plaintiff and between the plaintiff and the architects unequivocally shows the defendant as constantly asserting that the
While it is obvious that neither party understood that the letter had ended their difficulties leaving nothing more to be done, and that the final payment had become due, the letter, which at most is only a qualified or conditional acceptance of the building, does not specify the amount of the payment, or furnish any data from which it could be computed.
By article nine, "the final payment shall be made within forty-five days after the completion of the work included in this contract, and all payments shall be due when certificates for the same are issued.” The forty-five days do not begin to run until the final certificate of payment is furnished, and it is settled by Norcross Brothers Co. v. Vose, 199 Mass. 81, under a contract the same in form, that a letter containing acceptance of the building upon condition that the contractor is to remedy certain defects of workmanship or of materials, is not of itself a final certificate which can be treated as conclusive evidence of performance. Nor does the contract read that the final payment is to be made when the architects have accepted the building, and that such acceptance shall be conclusive upon the parties. If it did, a statement signed by them showing acceptance might be sufficient. Leverone v. Arancio, 179 Mass. 439, 442. Glacius v. Black, 50 N. Y. 145, 150. The architects also even if they were not to take evidence are empow
The parties under the express terms of the contract were not required to make adjustments by which all disputes should be settled and the amount of the final payment fixed. It is implied from the instrument as a whole, that as the result of the architects’ honest judgment the certificate or decision, which is to be final, shall also be complete. Chism v. Schipper, 22 Vroom, 1,13. Hudson v. McCartney, 33 Wis. 331, 345. The contractor is entitled to know how much is finally coming to him concerning which as the plaintiff contends there can be no further controversy, and the owner has the right to be informed of the amount he has to pay within the time prescribed, so that he can make the necessary arrangements and avoid being subjected to the costs and annoyance of litigation to which he may have no defence. Beharrell v. Quimby, 162 Mass. 571. Hathaway v. Stone, 215 Mass. 212. Wilson v. Borden, 39 Vroom, 627. Sharpe v. San Paulo Railway, L. R. 8 Ch. 597, 609. The architects also under article three are in the first instance to determine what sums should be allowed for alterations, as well as whether any deductions are to be made for imperfect or incompleted work or unsuitable materials, and if neither party dissented their decision is final. Norcross v. Wyman, 187 Mass. 25. Hebert v. Dewey, 191 Mass. 403.
It is plain that, material alterations having been made, it was the duty of the architects to act as required. But the record shows that when the action was begun the amounts claimed by the plaintiff for changes or alterations, or “extras” ordered, had neither been approved by the architects nor submitted to arbitration under article twelve as suggested by them. The provision as to alterations did not relieve the plaintiff from its agreement to perform the work according to the plans and specifications as they had been modified. It would seem to be reasonably clear that under this condition of affairs the defendant ought not to be deprived of the protection of the contract.
The construction of the contract, and of the letter .when read in connection with the contract, was a question for the court, and not for the jury to whom it was submitted. The plaintiff has offered as a final certificate only the letter, which as previously said is not in form or substance the final certificate called for under the contract. We are therefore of opinion that the defendant’s second request, that “Article nine of the contract requires an architect’s final certificate,” should have been given, and the instructions under which the jury were permitted to find that the letter of acceptance was such a certificate were erroneous.
It may be added that while the letter of acceptance was sent with its assent, the question, how far, if at all, the letter operated as a waiver by the defendant of the right to insist upon the plaintiff’s procuring a certificate as a condition precedent to maintaining an action for the unpaid balance of the contract price, and whether, if a waiver were found, the defendant can recoup for defective workmanship or materials, are questions not raised by the record, and not argued by counsel.
Exceptions sustained.