109 Mo. App. 622 | Mo. Ct. App. | 1904
This is an action to enforce a mechanic’s lien. The petition alleged, and the answer denied, that plaintiffs furnished the materials specified in their lien account for repairing and plastering a certain hotel building situate upon certain land — describing it — of which the defendant, Mrs. Jones, was the owner under and by virtue of a contract with defendant Hoyt who was the contractor with the defendant, Mrs. Jones, for making said hotel improvement.
The theory of the mechanic’s lien law is founded upon contract. By no other means can one man justly and legally acquire a claim upon the property of another. Every building contract is made with reference to the existing law which thus becomes incorporated with its terms. The owner’s contract with the builder empowers the latter to procure materials from the materialman, who thus, in his secondary position, is placed in a contract relation with the owner. The materialman or subcontractor derives all his claims from the original contract and to the terms of which he must look for the extent and limits of his capacity to fasten a lien on the land. .A mechanic’s lien is only given where the work is done or materials furnished by virtue of a contract with the owner of the improved land, or with his contractor or subcontractor. [R. S. 1899, sec. 4203; Duross v. Broderick, 78 Mo. App. 260, and case there cited; Lumber Co. v. Myers, 87 Mo. App. 671; Richardson v. O’Connell, 88 Mo. App. 12; Range Co. v. Jeffers, 79 Mo. App. 174]
It is thus seen that when it is sought to establish a lien, as here, for materials furnished by the material-
It results that the demurrer interposed by the defendant, Mrs. Jones, at the conclusion of all the evidence should have been sustained instead of overruled. And for this error the judgment must be reversed and cause remanded.