This case arose out of a controversy concerning a construction contract. The defendants entered into а contract to purchase a house to be ereсted by the plaintiff, Allen J. Henggeler. A part of the contract рrice was financed by a loan from the plaintiffs secured by a mortgage on the property. After the controversy devеloped, this action was commenced to foreclоse the mortgage.
The defendants’ amended cross-petition alleged the basement of the house was not constructed in a good and workmanlike manner; that during construction a pаrt of the basement wall “caved in”; Henggeler attempted tо repair the wall and later promised to “make it good”; sаtisfactory repairs were not made and the basement was wet and damp; and the reasonable cost of repairs was in excess of $3,000.
The trial court found the plaintiffs were entitlеd to' recover $2,280 on the loan less a credit of $2,000 because the house was not constructed in a good and workmanlike manner. The plaintiffs appeal.
There is no dispute cоncerning the amount due the plaintiff's on the loan. The only matter in dispute relates to the damages claimed by the defendants because of faulty construction of the house.
As a genеral rule a contractor constructing a building impliedly warrants that the building will be erected in a workmanlike manner and in accоrdance with good us-.
*319
age and accepted praсtices in the community in which the work is done. 13 Am. Jur. 2d, Building and Construction Contraсts, § 27, p. 29. See, also, Robertson Lumber Co. v. Stephen Farmers Coоperative Elevator Co.,
Whilе the house was under construction, mud and water ran into the basеment and it was necessary to brace the walls to prevent them from collapsing. After the defendants moved into the housе, water continued to run into the basement when it rained. The moisturе problem was severe and damaged the furniture and other equipment in the basement.
Although there was some conflict in the evidence, it was clearly sufficient to support the'finding of the triаl court on the cross-petition. The basement of the housе was unsatisfactory in its existing condition and a substantial amount of work was necessary to correct the condition.
Where а construction contract is substantially performed, the damage which the owner suffers because of defective workmаnship or unsuitable materials used is measured by the reasonable cost of remedying the defects. Jones v. Elliott,
The judgment of the District Court is affirmed.
Affirmed.
