Hempstead County Hunting Club, Inc. v. Southwestern Electric Power Co.Hempstead County Hunting Club, Inc. v. Southwestern Electric Power Co.
11 This case involves three questions of law certified to this court by the United States District Court for the Western District of Arkansas in accordance with our Supreme Court Rule 6-8 (2010). See Hempstead Cnty. Hunting Club, Inc. v. Southwestern Elec. Power Co.,
(1) If the state-law claims of the Hemp-stead County Hunting Club were not brought in the first instance before the Arkansas Public Service Commission (“PSC”), is court review of such сlaims precluded by Arkansas Code Annotated sections 23-1-108, 23-3-119, 23-3-206, 23-18-502(e), and 23-18-525 (Repl.2002), or by the common law of Arkansas concerning the exhaustion of administrative remedies?
(2) When a utility applies for, receives, and commences construction under a Certificate of Environmental Compatibility and Public Need (“CECPN”), has thе utility voluntarily submitted to the jurisdiction of the PSC pursuant to Arkansas Code Annotated section 23-18-504(b) (Repl.2002) and thereby waived its right to claim exemption under section 23-18-504(a)(5)?
(3) Is a public utility seeking to build a major utility facility under the exemption set out in Arkansas Code Annotated section 23-18-504(a)(5) required to obtaina Certificate of Cоnvenience and Necessity (“CCN”) under Arkansas Code Annotated section 23-3-201(a)?
As to the first question, we conclude that under Arkansas law, Hempstead was required to bring its claims before the PSC in the first instance; therefore, court review of the claims is precluded until Hempstead exhausts its administrative remedies. As a result of this conclusion, we do not reach the second and third certified questions, as reformulated.
|?,In compliance with our per curiam order, Hempstead filed a brief in which it alleged that, under Arkansas law, (1) Arkansas courts have jurisdiction to declare that SWEPCO is required to obtain a CECPN or CCN; (2) SWEPCO waived the nonrate exеmption from the CECPN requirement through its actions; and (3) even if SWEPCO is not required to obtain a CECPN, a CCN is still required. SWEPCO filed a brief in response.
I. Background
On May 13, 2010, this court handed down its decision in Hempstead Cnty. Hunting Club, Inc. v. Ark. Pub. Serv. Comm’n,
The day this court’s mandate issued, SWEPCO filed a notice of exemption (“Notice”) with the PSC stating that the construction and operation of the Turk Plant would proceed under the exemption frоm the CECPN requirement pursuant to
II. Certified Questions
Under the first question, Hempstead raises three points. First, it alleges that the Utility Facility and Economic Protection Act,
Hempstead states that the federal district court has jurisdiction pursuant to
Except as expressly set forth in §§ 23-18-505, 23-18-506, and 23-18-524, no court of this state shall have jurisdiction to hear or determine anyissue, case, or controversy concerning any matter which was or could have been determined in a proceeding before the Arkansas Public Service Commission under this subchapter or to stop or delay the financing, construction, operation, or maintenance of a majоr utility facility except to enforce compliance with this subchapter or the provisions of a certificate issued under this subchap-ter.
lsArk.Code Ann. § 28-18-525.
Hempstead asserts that the PSC’s jurisdiction is exclusive “except to enforce compliance with this subchapter.” Hempstead focuses on this phrase in аrguing that the federal district court has jurisdiction to compel SWEPCO to comply with the CECPN requirements. Hempstead acknowledges that the legislature granted the authority to administer the Utility Act to the PSC. It attempts to distinguish the present state-law claims as ones over which the court must interpret and enforce the Utility Act, rаther than ones upon which the PSC must administer the CECPN law.
This argument is unpersuasive. We have not previously had cause to interpret
| ^Hempstead next alleges that the district court has concurrent authority to enforce the CCN Statute. It states that if the court determines that SWEPCO is not required to obtain a CECPN, the court may exercise its authority to “enforce the CCN statute” by requiring that SWEPCO obtain a CCN. Hempstead concedes that the CCN Statute does not contain thе express grant of jurisdiction to the courts to enforce the CCN Statute, but instead states that where the legislature gave the PSC the authority in
We have held that a court of equity does not have concurrent jurisdiction with the PSC in public-utility litigation where there is a clear, adequate, and complete remedy by an application to the PSC. See Okla. Gas & Elec. Co. v. Lankford,
17Finally, Hempstead alleges that our precedent supports its position that the district court’s authority is not excluded by the common-law doctrine of exhaustion of remedies. SWEPCO asserts in response that the court must first determine whether the review of the CECPN and CCN claims is precluded because they were not first presented to the PSC. Hempstead relies on this court’s decisions in Southwestern Gas & Elec. Co. v. Hatfield,
Hempstead’s reliance on Hatfield and Coxsey is misplaced. This court observed in Coxsey that the issue in Hatfield was before the PSC because it involved the sale of a utility, which required the PSC’s approval. Coxsey,
|sIn reaction to Turner, the general assembly passed Act 758 of 1985, codified at
(1) It is the specific intent of [this enactment] to vest in the [PSC] the authority to adjudicate individual disputes betweеn consumers and the public utilities which serve them when those disputes involve public rights which the [PSC] is charged by law to administer.
(2) Public rights which the [PSC] may adjudicate are those arising from the public utility statutes enacted by the General Assembly and the lawful rules,regulations, and orders entered by the [PSC] in the execution of the statutes.
[ gArk.Code Ann. § 23 — 3—119(f).
It is clear that
The doctrine of exhaustion of administrative remedies provides that no one is entitled to judicial relief for a supposed or threatened injury until the prescribed statutory administrative remedy has been exhausted. Austin v. Centerpoint Energy Arkla,
Should Hempstead file a complaint with the PSC and disagree with the PSC’s disposition of its claims, at that point, it may seek judicial review under ArkCode Ann. §§ 23-2-421 to -425. Only when аn applicant has exhausted its administrative remedies does the state court system come into play. Ark. Dep’t of Health & Human Servs. v. Smith,
| uHaving decided the first certified question, we now turn' to the second and third certified questions. In light of our conclusion on the first question, the determination of the issues presented in the second and third questions are necessarily within the purview of the PSC. Under our
Notes
. On October 27, 2010, the district court granted Hempstead’s motion for preliminary injunction in part, halting construction on work authorized by a permit under the federal Clean Water Act,