11 This case involves three questions of law certified to this court by the United States District Court for the Western District of Arkansas in accordance with our Supreme Court Rule 6-8 (2010). See Hempstead Cnty. Hunting Club, Inc. v. Southwestern Elec. Power Co.,
(1) If the state-law claims of the Hemp-stead County Hunting Club were not brought in the first instance before the Arkansas Public Service Commission (“PSC”), is court review of such claims precluded by Arkansas Cоde Annotated sections 23-1-108, 23-3-119, 23-3-206, 23-18-502(e), and 23-18-525 (Repl.2002), or by the common law of Arkansas concerning the exhaustion of administrative remedies?
(2) When a utility applies for, receives, and commences construction under a Certificate of Environmental Compatibility and Public Need (“CECPN”), has the utility voluntarily submitted to the jurisdiction of the PSC рursuant to Arkansas Code Annotated section 23-18-504(b) (Repl.2002) and thereby waived its right to claim exemption under section 23-18-504(a)(5)?
(3) Is a public utility seeking to build a major utility facility under the exemption set out in Arkansas Code Annotated section 23-18-504(a)(5) required to obtaina Certificate of Convenience and Necessity (“CCN”) under Arkansas Cоde Annotated section 23-3-201(a)?
As to the first question, we conclude that under Arkansas law, Hempstead was required to bring its claims before the PSC in the first instance; therefore, court review of the claims is precluded until Hempstead exhausts its administrative remedies. As a result of this conclusion, we do not reach the second and third certified questions, as reformulated.
|?,In compliance with our per curiam order, Hempstead filed a brief in which it alleged that, under Arkansas law, (1) Arkansas courts have jurisdiction to declare that SWEPCO is required to obtain a CECPN or CCN; (2) SWEPCO waived the nonrate exemption from the CECPN requirement through its actions; and (3) even if SWEPCO is not rеquired to obtain a CECPN, a CCN is still required. SWEPCO filed a brief in response.
I. Background
On May 13, 2010, this court handed down its decision in Hempstead Cnty. Hunting Club, Inc. v. Ark. Pub. Serv. Comm’n,
The day this court’s mandate issued, SWEPCO filed a notice of exemption (“Notice”) with the PSC stating that the construction and operation of the Turk Plant would proceed under the exemption from the CECPN requirement pursuant to Ark. Code Ann. § 23-18-504(a)(5). SWEPCO elected not to recovеr the costs of the facility through rates that are subject to regulation by the PSC and instead planned to use capacity in the Turk Plant to provide retail electric services to consumers in Texas and Louisiana, which is regulated by the Texas and Louisiana utility commissions, and wholesale services subject to federal jurisdiction. Hempstead was served with a copy of the Notice but filed no response with the PSC, nor did |4it file any other claim for relief concerning the construction or operation of the Turk Plant with the PSC. The PSC issued an order on August 5, 2010, directing the secretary of the PSC to close the docket on this matter, “there being nо further action to be taken in this matter at this time.”
II. Certified Questions
Under the first question, Hempstead raises three points. First, it alleges that the Utility Facility and Economic Protection Act, Ark.Code Ann. §§ 23-18-501 to - 530 (Repl.2002 & Supp.2009) (“Utility Act”), unambiguously grants courts the authority to enforce the Utility Act. Second, Hempstead states that Ark.Code Ann. §§ 23-3-201 to -206 (Repl.2002 & Supp. 2009) (“CCN Statute”) grants courts concurrent authority to enforce the CCN statute. Finally, it asserts that prior decisions of this court support the authority of the district court to resolve Hempstead’s state-law claims, which are not excluded by the common-law doctrine of exhaustion of remedies.
Hempstead states that the fеderal district court has jurisdiction pursuant to Ark.Code Ann. § 23-18-525 (Repl.2002) to enforce compliance with the Utility Act by requiring SWEPCO to obtain a CECPN permit. The statute provides as follows:
Except as expressly set forth in §§ 23-18-505, 23-18-506, and 23-18-524, no court of this state shall have jurisdiction to hear or determine anyissue, case, or controversy concerning any matter which was or could have been determined in a proceeding before the Arkansas Public Service Commission under this subchapter or to stop or delay the financing, construction, operation, or maintenance of a major utility facility except to enforce compliancе with this subchapter or the provisions of a certificate issued under this subchap-ter.
lsArk.Code Ann. § 28-18-525.
Hempstead asserts that the PSC’s jurisdiction is exclusive “except to enforce compliance with this subchapter.” Hempstead focuses on this phrase in arguing that the federal district court has jurisdiction to compel SWEPCO to cоmply with the CECPN requirements. Hempstead acknowledges that the legislature granted the authority to administer the Utility Act to the PSC. It attempts to distinguish the present state-law claims as ones over which the court must interpret and enforce the Utility Act, rather than ones upon which the PSC must administer the CECPN law.
This argument is unpersuasive. We havе not previously had cause to interpret section 23-18-525. The first rule in considering the meaning and effect of a statute is to construe it just as it reads, giving the words their ordinary and usually accepted meaning in common language; when the language is plain and unambiguous, there is no need to resort to rules of statutory construction. Kesai v. Almamd,
| ^Hempstead next alleges that the district court has concurrent authority to enforce the CCN Statute. It states that if the court determines that SWEPCO is not required to obtain a CECPN, the court may exercise its authority to “enforce the CCN statute” by requiring that SWEPCO obtain a CCN. Hempstead concedes that the CCN Statute does not contain the express grant of jurisdiction to the courts to enforce the CCN Statute, but instead statеs that where the legislature gave the PSC the authority in Ark.Code Ann. § 23-3-206(a) (Repl.2002) to act on a complaint alleging that a public utility is constructing or operating a facility in violation of the statute, the legislature did not intend to grant exclusive authority to the PSC. Hempstead relies on the following statutory language to illustrate thе legislature’s intent not to give the PSC exclusive jurisdiction under section 23-3-206: “Nothing in this act shall be construed to in any way restrict the jurisdiction of any court of equity.” Ark.Code Ann. § 23-l-108(a) (Repl.2002).
We have held that a court of equity does not have concurrent jurisdiction with the PSC in public-utility litigation where there is a clear, adequate, and complete remedy by an application to the PSC. See Okla. Gas & Elec. Co. v. Lankford,
17Finally, Hempstead alleges that our precedent supports its position that the district court’s authority is not excluded by the common-law doctrine of exhaustion of remedies. SWEPCO asserts in response that the court must first determine whether the review of the CECPN and CCN claims is precluded because they were not first presented to the PSC. Hempstead relies on this court’s decisions in Southwestern Gas & Elec. Co. v. Hatfield,
Hempstead’s reliance on Hatfield and Coxsey is misplaced. This court observed in Coxsey that the issue in Hatfield was before the PSC because it involved the sale of a utility, which required the PSC’s approval. Coxsey,
|sIn reaction to Turner, the general assembly passed Act 758 of 1985, codified at Ark.Code Ann. § 23-3-119®. Act 758 clearly expressed the legislature’s disapproval of our holding in Turner and placed primary jurisdiction over disputes such as those raised in Turner in the PSC. See Ozarks Elec. Coop. Corp. v. Harrelson,
(1) It is the specific intent of [this enactment] to vest in the [PSC] the authority to adjudicate individual disputes between consumers and the public utilities which serve them when those disputes involve public rights which thе [PSC] is charged by law to administer.
(2) Public rights which the [PSC] may adjudicate are those arising from the public utility statutes enacted by the General Assembly and the lawful rules,regulations, and orders entered by the [PSC] in the execution of the statutes.
[ gArk.Code Ann. § 23 — 3—119(f). Section 23-3-119 also provides that the PSC shall have quasi-judicial jurisdiction, with authority “to adjudicatе public rights and claims in individual cases [that] is in addition to the [PSC] ’s traditional legislative authority to act generally, and prospectively, in the interest of the public.” Ark.Code Ann. § 23 — 3—119(f)(3); see also Harrelson,
It is clear that section 23-3-119 does not, as Hempstead urges, pertain only to billing disputes in which customers seek billing credits. We have not, at least since the 1985 amendment to section 23-3-119, given this statute such a strict reading. See Harrelson, supra. SWEPCO is clearly a public utility, and issuing a CECPN or CCN is within the laws and regulations that the PSC has jurisdiction to administer. Thus, the question is whether the relief that Hempstead seeks is within the “prospеctive relief’ authorized under subsection 119(d). While we have not ruled on what this phrase fully encompasses, prospective relief would clearly include in-junctive relief, with which the PSC could have ordered SWEPCO to stop the construction of the Turk Plant until a CECPN or CCN was obtained under Ark.Code Ann. § 23-18-525 or ArkCode Ann. § 23-3 — 119(d). Under section 23-3-119, Hemp-stead | inwas required to first bring a complaint for declaratory and prospective relief before the PSC, and to exhaust all of its administrative remedies before the PSC prior to seeking judicial relief.
The doctrine of exhaustion of administrative remedies provides that no one is entitled to judicial relief for a supposed or threatened injury until the prescribed statutory administrative remedy has been exhausted. Austin v. Centerpoint Energy Arkla,
Should Hempstead file a complaint with the PSC and disagree with the PSC’s disposition of its claims, at that point, it may seek judicial review under ArkCode Ann. §§ 23-2-421 to -425. Only when an appliсant has exhausted its administrative remedies does the state court system come into play. Ark. Dep’t of Health & Human Servs. v. Smith,
| uHaving decided the first certified question, we now turn' to the second and third certified questions. In light of our conclusion on the first question, the determination of the issues presented in the second and third questions are necessarily within the purview of the PSC. Under our
Notes
. On October 27, 2010, the district court granted Hempstead’s motion for preliminary injunction in part, halting construction on work authorized by a permit under the federal Clean Water Act, 33 U.S.C. § 1344.
