35 Mo. 482 | Mo. | 1865
delivered the opinion of the court.
This was a suit by the sub-contractor against the contractor and the owner, to enforce a mechanic’s lien against a house in St. Louis, under the mechanics’ lien law applicable to St. Louis county. (Sess. Acts. 1857, p. 668.) It appears from the petition that there was an interval of eight days only between the notice of claim given by the plaintiff to Hynes the owner, and the filing of the lien in the Land Court, whereas the act (§ 18) expressly requires ton days’ notice before filing. The objection was taken by motion in arrest, but was overruled by the court below. In Schubert v. Crowley, 33 Mo. 564, the same question was considered by this court, where it was held the objection was well taken.
The judgment will be reversed ; and, as it may be possible the facts of the case may justify an amendment of the petition so as to show sufficient notice of claim, the cause will be remanded;