Hellman v. Farrelly

116 N.Y.S. 809 | N.Y. App. Div. | 1909

Ingraham, J.:

Upon the first trial of this action the court dismissed tbe complaint upon tbe pleadings and upon tbe plaintiff’s opening. On appeal to this court the judgment entered upon such dismissal was reversed and a new trial ordered (Hellman v. City Trust, Safe Deposit & Surety Co., 111 App. Div. 876). We there held that: “In tbe circumstances disclosed it evidently appeared to be to tbe interest of tbe surety to have the provision with respect to reserving part of the amount earned waived, and likewise with respect to the time of performance; ” that “ having consented to these modifications at tbe instance of its principal, and tbe plaintiff having acted *152thereon manifestly to his prejudice, if the consent and waiver were now to be repudiated, the defendant is estopped from contending that these modifications with respect to performance discharge it from all liability.” Upon the new trial before a referee judgment was awarded to the plaintiff. The referee found that on the 7th of December, 1898, the plaintiff entered into a contract in writing with one Blake, a copy of which is annexed to the amended complaint, and that by that contract Blake undertook to-excavate the rock upon certain real property for a price fixed which was based upon the estimated amount of rock to be excavated as 23,823 cubic yards and that the sum of one dollar and twenty cents per cubic yard was a proper sum to pay for such excavation, and that Blake as principal and the City Trust, Safe Deposit and Surety Company of Philadelphia as surety executed a bond conditioned Upon the performance of the conditions and covenants by Blake on bis part to be performed under said contract ; that the plaintiff made various payments to Blake as the work progressed; that from the inception of the work-performed under said contract by Blake, the said City Trust, Safe Deposit and Surety Company of Philadelphia knew that the sums periodically paid by the plaintiff to Blake were ascertained and computed by the plaintiff from the certificates of the engineer by multiplying the number of cubic yards specified in said certificates by the sum of one dollar and twenty cents and that such several certificates did not specify the amount earned by said Blake during the periods covered by them respectively in money, and that early in the progress of said work the said corporation specifically requested the said Heilman to continue making such payments to Blake for each cubic yard excavated and removed as shown by the certificates of the said surveyors-; that at the time of making such request the said corporation knew that there was a question whether the amount of material to be excavated had not been underestimated, and it made such request with the full knowledge that payments at that rate might result in the advancement to Blake for the time being of a larger proportion of the contract price than had actually been earned by him, hut in the belief that if such payments were made to the said Blake it might enable him to assemble the plant and employ the labor essential to the carrying out of such contract on Ms part; that, “the time of the performance of said contract on the part of Law*153rence E. Blake, as provided by its terms, was with the full knowledge and approval and consent of the City Trust, Safe Deposit and Surety Company of Philadelphia, extended from time to time, and-at the request of the City Trust, Safe Deposit and Surety Company, and with the consent of this plaintiff, said Lawrence E. Blake was permitted to and requested to continue performance of said contract on his part for the benefit of all concerned, and did with the acquiescence, knowledge and consent of said company continue to perform the same until on or about the twelfth day of May, 1900.” . He further found that Blake, on or. about the 12th of May, 1900, wholly abandoned-performance of said contract and refused and neglected to proceed therewith and to supply a sufficiency of materials or workmen to complete the same and to continue its progress, and thereupon the City Trust, Safe Deposit and Surety Company and Blake were notified of said default by the plaintiff and of the plaintiff’s intention to complete the same; that the plaintiff then entered into a contract to complete the same, which was submitted for approval by the City Trust, Safe Deposit and Surety Company of Philadelphia before the work was done thereunder, and said work was completed pursuant to its terms without objection on the part of the said the City Trust, Safe Deposit and Surety Company of Philadelphia, and that the cost of that work under said contract was $38,844.76, or $10,344.76 in excess of the contract price, which is an amount in excess of the bond given by the defendant, winch was $10,000and, as a conclusion of law, that the plaintiff performed all the terms and conditions under said contract on his part to be done and performed, except in so far as performance of the conditions thereof was waived by the said the City Trust, Safe Deposit and Surety Company, and judgment was awarded to the plaintiff against the trust company for the sum of $10,000.

The opinion of the referee, I think, satisfactorily disposes of all the points raised by the defendant upon this appeal. It is a mistake to assume that ■ the liability of the defendant is based upon a . modification of the original contract between plaintiff and Blake. By the contract Blake undertook to do this work for the sum of $28,500. Tliis'contract was not based upon the amount of rock to be excavated. The bond given by the defendant was on condition *154that Blake should duly and faithfully perforin and fulfill all conditions of said contract on his part to be kept and performed, and should keep harmless and protect the obligee (plaintiff) from and against all loss by reason of the non-fulfillment by Blake of the covenants contained in the said contract to be performed by him as aforesaid. The bond also contains a provision that; it is issued upon the express condition that all the covenants and agreements contained in the said contract made by the said obligee and on his part to be kept and performed for the protection of the said obligee and of said surety, should be strictly kept and performed by the said obligee. By the contract the plaintiff was required to make certain payments upon the certificate of the engineers as the work progressed, reserving fifteen per cent of the amount of each certificate until the work was .fully performed, which sum was to be paid to Blake when the certificate that the entire work was fully completed was submitted. If. the plaintiff had refused to pay the various sums that became due from time to time there would have been a breach of the contract which would have discharged, the surety. There is nothing in the contract to show that a payment in excess of the amount required to be paid to Blake was a breach of a covenant or agreement made by the plaintiff for his protection or for that of the surety, but if such covenant was within this provision of the bond, then payments made to Blake by the plaintiff at the express request of the surety and to enable Blake to carry out the contract would not discharge the surety. The plaintiff was justified in construing the contract and making the payments as requested by Blake and the surety. It seems to me that it is not a question of" the modification of the original contract, because neither of the parties agreed that it should be so "modified as to impose an obligation upon the plaintiff to pay anything in excess of what he undertook to pay under the original contract; but in carrying out the contract and making payments from time to time the plaintiff was justified in acceding to the request of Blake and his surety and acting upon such request and consent, and the surety was then estopped from insisting that such, payments were .a violation of the contract, or discharged it from the obligation that' it had assumed. There is no evidence that these increased payments occasioned any loss to the defendant, or that if the plaintiff had reserved the fifteen per cent and had paid only *155the amount that was earned by Blake under the contract, Blake would have been able to perform the contract, or that the amount that the plaintiff had to pay for its completion would have been any less than that which he was required to pay. The statement is made in the plaintiff’s brief that the plaintiff had been allowed to abrogate and set aside every term of the contract that he was bound to perform, when the evidence shows that the plaintiff not only performed every obligation that he assumed under the contract, but paid to the principal an amount in excess of that which he was required to pay and which, upon no principle, could have substantially injured the defendant. Sullivan, the manager of the defendant,, was not called as a witness, and there was no contradiction of any of the evidence offered by the plaintiff as to liis active participation in inducing plaintiff to make the payments to Blake, and the evidence is undisputed that from the beginning Sullivan was insisting that plaintiff should make payments to Blake in excess of that provided for by the contract; that Sullivan had said that he deemed the fifteen per cent reserve a very onerous requirement and that, if it would help him along,, the plaintiff should exercise his discretion, from time to time, in making Blake allowances out of the reserve; that these excessive payments were made by the plaintiff reluctantly and only upon the assurance of Sullivan that it would be perfectly proper to make the payments. All of these payments were made on the demand of Blake, all made with the knowledge and acquiescence or request of Blake’s surety (defendant), and under such circumstances it is clear that the defendant is now estopped from asserting that these payments made at its request and for its benefit are a violation of the plaintiff’s contract which discharges the surety.

I think the judgment was right and it should be affirmed.

Patterson, P. J., McLaughlin, Laughlin and Clarke, JJ., concurred.

Judgment affirmed, with costs.