63 Ct. Cl. 392 | Ct. Cl. | 1927
delivered the opinion of the court:
The plaintiff is suing to recover the sum of $19,527.74, which it claims is due it by the United States.
“ Referring to the attached proposals on wood for various posts and camps, beg to advise that our prices are based on freight rates now in effect. Should these rates be increased or deci’eased during the term of the contract, should we be awarded any of this business, our prices are to be governed accordingly.”
When the bids were opened by the defendant the letter of the plaintiff of date May 14,1920, was found attached to the bid, and the bid so submitted was accepted and the contract awarded in accordance with the bid. Due to a mistake, no specific clause was written into the contract covering the increase or decrease of freight rates as was contemplated by the parties and stipulated for in the bid of the plaintiff, and the plaintiff in signing the contract believed the clause aforesaid was incorporated therein and signed the contract in that belief. After the contract had been executed freight rates
“ Receipt is acknowledged of your communication of April 20th re increased freight rates. The position you take regarding refundment by the Government to you of increased freight rates granted by the Government subsequent to your entering into contract for furnishing wood is absolutely correct.
“ If provision covering this contingency was not made a part of your contract, it was due to an oversight in the office of which, at the time the contract was entered into, I was in charge. Your communication to me dated May 14,1920, sets forth clearly that such a provision should have been made a part of your contract, and if at the present date such provision is not contained in your contract the same should be so amended as to include that provision.”
The plaintiff therefore believing that the increased freight rates would be paid proceeded with the delivery of the wood under said contracts, and by reason of the increase in freight rates was compelled to pay and did pay the sum of $19,527.14 more than it would have been obliged to pay had there been no increase in rates.
The plaintiff made claim upon the United States for the aforesaid amount; payment thereof was refused, and the plaintiff thereupon brought this suit.
It is quite evident that both parties to the contract believed the provision providing for the increase or decrease in freight rates was embodied in the contract when it was signed by them; due to mistake, which was mutual, the provision aforesaid was omitted from the contract. Both parties understood the obligations imposed by the contract to be different from those stated in the written instrument. In such a case the court will reform the contract in accordance with the real intention and understanding of the parties shown by the evidence. We are therefore of opinion that the plaintiff is entitled to have the contract reformed so as to make it speak the intention of the parties to the contract, and that upon such reformation the plaintiff is entitled to recover the amount clamed, to wit, the sum of $19,527.74. See Poole Engineering & Machine Company v. United States, 58 C.