37 Wash. 477 | Wash. | 1905
In 1902, the respondent, Heffernan, contracted with the Port of Portland to build and equip for it a tug.boat, to be known as the “John McCracken,” according to plans and specifications furnished him by that corporation. The respondent sublet a part of the work to the defendant Ballard Dry Dock & Ship Building Company. The contract was in writing, and expressed in the form of a letter addressed to the respondent by the defendant, and an acceptance of the proposition therein contained by the respondent. In the letter the Ballard Dry Dock & Ship Building Company offered “to build the hull of the steamer John McCracken, according to the drawings submitted and specifications attached, including all terms and conditions therein, for the sum of eight thousand six hundred dollars. . . .” Attached to the letter were the specifications of the hull, as furnished the respondent by the Port of Portland; these having been submitted to the company by the respondent at the time of the negotiations leading up to the contract. The contract was dated July 23, 1902. The specifications provided, under the title, “General Conditions,” among other things, that the “hull house and equipment are to be furnished by the hull contractor,” and that the hull should be ready for machinery September 15, 1902, and completed ready for trial, October 15, 1902. Then followed, under the title “Specifications of Hull,” specifications for the construction and equipment of a steam sea-going vessel, complete with the exception of the engines and boilers.
“First — That no liability shall attach to the surety hereunder unless, in the event of any default on the part of the principal in the performance of any of the terms, covenants or conditions of the said contract, the obligee shall promptly upon knowledge thereof, and in any event not later than thirty days after the occurrence of such default, deliver to the surety at its office in the city of Baltimore, written notice thereof with a statement of the principal facts showing such default and the date thereof; nor unless the said obligee shall deliver written notice to the surety at its office aforesaid before making to the. principal the final payment provided for under the contract herein referred to.”
The ship building company failed to carry out its contract, and the respondent was compelled to build and equip the hull at his own cost. In doing so he paid for labor and materials the sum of $1,616.50 in excess of the contract price, and $1,029.15 as demurrage to the Port of Portland because of his failure to deliver the vessel on the contract time, making a total of $2,645.65 more than the contract price. .This action was brought- to recover from the ship building company and the appellant the amount so paid. Judgment went against them for the amount claimed, and this appeal is from that- judgment.
The other contention is that appellant was relieved from its liability because of the failure of the respondent to give it timely notice of the breach of the contract on the part of the ship building company. By the terms of the contract, as we have said, the ship building company agreed to have the vessel ready for machinery by September 15, 1902, and completed ready for trial by October 15, 1902. It did not have the vessel ready for machinery at the first date named, nor did it have the boat completed and ready for trial at the latter date. Hotice was sent the appellant of these failures on October 17, 1902. The appellant contends that this notice was too late to comply with the con
The judgment of the trial court will he reversed and the cause remanded with instructions to enter a judgment against the defendant, the Ballard Dry Dock & Ship Building Company, and the appellant, The United States Fidelity and Guaranty Company, for the sum of $1,616.50, together with interest thereon from the 1st day of March, 1904, at the legal rate. The appellant will recover its costs on this appeal.
Mount, C. J., Hadley, and Dunbar, JJ., concur.
Rudkin,Root, and Crow, JJ., took no part.