This case represents an initiative by Heery International, Inc. (“Heery International”) and Hellmuth, Obata & Kassab-aum, P.C. (“HOK”) (sometimes collectively referred to as “Heery”) to circumvent Montgomery County’s (the “County”) administrative dispute resolution process for claims relating to local public works contracts. They seek to truncate that process on the ground that the process and the County’s designated administrative adjudicator are “palpably without jurisdiction” to decide the particular dispute in this case. Heery shall not succeed.
I.
On 1 December 1989, Heery Program Management, Inc. entered into a contract with the County to provide construction management services relating to a proposed detention center in Clarksburg, Maryland. Nine years later, on 9 October 1998, that contract was assigned to the related entity of Heery International. Approximately one year earlier, HOK entered into a separate contract with the County to provide architectural and engineering services relating to the design of the detention center.
Believing that it furthered the goal of facilitating construction of the detention
In a letter dated 17 July 2003, the County made a formal demand on Heery International and HOK for payment in the amounts of $2,450,959 and $3,804,163, respectively. These amounts represented damages the County allegedly suffered as a result of lost productivity and delay caused by Heery International and HOK’s mismanagement of the trade contractors. The letter also demanded that Heery International and HOK, pursuant to provisions in their respective contracts with the County, provide a legal defense and indemnify the County with regard to claims totaling over $13 million lodged by some of the trade contractors. 1 Moreover, the letter demanded an additional $915,168 for the actual legal costs incurred by the County, up to that point, in defense of the trade contractors’ claims.
The letter concluded by stating that, if the claims were not resolved within thirty days, the County would file its claims with the County’s Director of the Department of Public Works and Transportation (“DPW & T”), as provided for by both Heery International’s and HK’s contracts and the Montgomery County Procurement Regulations (“Procurement Regulations”). 2 The relevant provision of the Heery International contract 3 stated:
“8. DISPUTES. Any dispute arising i under this contract which is not disposed of by agreement must be decided under The Montgomery County Code and The Montgomery County Procurement Regulations.”
Heery International and HOK, in letters dated 13 August 2003 and 12 August 2003, respectively, denied responsibility for the County’s substantive claims. They also denied that the County’s claims were subject to the dispute resolution process outlined in the Montgomery County Code (“County Code”) and Procurement Regulations. Although acknowledging that their respective contracts with the County authorized the use of the County administrative contract dispute resolution process, Heery International and HOK claimed that
the County Code and the Procurement
On 14 August 2003, the County submitted its claims to its Director of DPW & T. Four days later, Heery filed a complaint in the Circuit Court for Montgomery County seeking declaratory and equitable relief preventing the County or the Director from pursuing any remedy through the administrative dispute resolution process outlined in the County Code and Procurement Regulations. The County responded with a motion to dismiss, asserting that any question of an administrative agency’s jurisdiction should be decided in the first instance during the pertinent administrative process. On 3 November 2003, the Circuit Court denied Heery’s request for equitable relief, and entered a declaratory judgment that “the administrative agency is not ‘palpably without jurisdiction’ to adjudicate the underlying dispute.” The court also denied Heery’s request for a stay of the administrative proceedings, concluding instead that they were required to exhaust their administrative remedies before seeking judicial review or intervention.
Heery noted an appeal to the Court of Special Appeals. Before the intermediate appellate court could decide the case, this Court, on its initiative, issued a writ of certiorari,
Did the trial court err in holding that the Montgomery County Department of Public Works and Transportation was not “palpably without jurisdiction” to adjudicate a dispute brought by the County against a contractor?
II.
Chapter 11B of the County Code, in conjunction with the County’s Procurement Regulations, outlines the administrative dispute resolution process for disputes arising between contractors and the County. 4 Mont. Co.Code § 11B (2004); Mont. Co. Proc. Regs. § 14.2 (2004). Section 11B-35 of the County Code states that a “contractor must submit any dispute arising under a contract to the Director [of the Office of Procurement].” Mont. Co.Code § llB-35(a). The County Code defines a “contractor” as “any person that is a party to a contract with the County.” Id. § HB-l(f). Moreover, the Procurement Regulations define a “dispute” as a “timely complaint filed by a contractor disagreeing with a decision made by an authorized government official regarding the contract.” Mont. Co. Proc. Regs. § 2.4.40.
When a dispute arises between a contractor and the County, the Procurement Regulations mandate that the contractor and the contract administrator must attempt to resolve the claim.
Id.
§ 14.2.2.1. If the parties are unable to resolve the dispute, the contractor must submit the dispute to the Director of the Office of
During the contract dispute appeal process, the CAO reviews the dispute de novo. Id. § 14.2.2.9. If, based on the paper record, the CAO is able to determine whether the claim has merit, the CAO may, within 80 days, either deny the claim or order an appropriate remedy. Id. § 14.2.2.9(a)-(b). If the CAO is unable to decide a claim on the paper record, the CAO may conduct a hearing or designate a hearing officer to hear the claim. Id. § 14.2.2.9(c). During the hearing process, the parties may take advantage of discovery and other procedures outlined in the Procurement Regulations intended to insure a fair adversarial hearing. Id. § 14.2.3. If the CAO designates a hearing officer to hear the dispute, the hearing officer must make recommended findings of fact and conclusions, which are then submitted to the CAO. Id. § 14.2.2.9(c). The CAO then has 30 days to render a written decision on the appeal. Id. Once the CAO renders a written decision, that decision is final for administrative purposes and subject to judicial review in the Circuit Court for Montgomery County. Id. § 14.2.2.9(d).
III.
Heery claims that, because the County Code and Procurement Regulations do not authorize the County to utilize its administrative dispute resolution process to litigate a claim that it asserts against a party with which it has contracted, the agency is acting clearly outside the bounds of its jurisdiction by entertaining the County’s claim. Therefore, Heery deems itself entirely justified in seeking to sidestep what it perceives as an unauthorized administrative process.
We have long held that “[w]here an administrative agency has primary or exclusive jurisdiction over a controversy, the parties to the controversy must ordinarily await a final administrative decision before resorting to the courts for resolution of the controversy.”
State v. Bd. of Contract Appeals,
Although the “palpably without jurisdiction” standard, described as such, was first recognized in Maryland case law in
The Court in
MTA
reaffirmed the principle that administrative remedies ordinarily must be exhausted, absent certain extraordinary circumstances.
The Court also disagreed with the MTA’s characterization of the dispute:
The MTA in the present case has couched the statutory interpretation issue in terms of the Commission’s “authority” or “power” or “jurisdiction,” and has charged that the Commission is attempting to “expand” its jurisdiction and proceed in an unauthorized manner. Nevertheless, many, if not most, statutory interpretation issues arising in administrative proceedings could be phrased in terms of the agency’s “authority,” “power” or “jurisdiction” to take a certain type of action in a specific case. A party’s argument that an agency will be exceeding its authority if it ultimatelyinterprets the statute and decides the case contrary to that party’s position, does not excuse the failure to await a final agency decision.
Id.
The possibility that extraordinary circumstances could provide a basis for absolving the usual obligation to exhaust available administrative remedies was not foreclosed.
Id.
at 235,
In
Montgomery County v. Ward,
This Court declined to rule on the merits and vacated the judgment, determining instead that Ward’s employer was not entitled to resort to a judicial forum while the administrative process was pending.
Id.
at 527-29,
We faced a similar question of statutory interpretation in
State v. Board of Contract Appeals,
Although the cases discussed above held that the particular issues of statutory interpretation should be decided in the first instance by the administrative agency charged with interpreting the particular statute, the Court also indicated that an agency may be “palpably without jurisdiction” if a party challenges the underlying fundamental subject matter jurisdiction of the agency. The
Ward
Court, for instance, expounded on the concept of jurisdiction for purposes of administrative exhaustion, holding that, in order to invoke the “palpably without jurisdiction” standard, the agency’s actions must concern the agency’s “fundamental ‘jurisdiction.’ ” 331 Md. at
527,
In
Board of License Commissioners v. Corridor Wine, Inc.,
[sjimply because a statutory provision directs a court or an adjudicatory agency to decide a case in a particular way, if certain circumstances are shown, does not create an issue going to the court’s or agency’s subject matter jurisdiction. There have been numerous cases in this Court involving the situation where a trial court or an adjudicatory agency has jurisdiction over the subject matter, but where a statute directs the court or agency, under certain circumstances, to exercise its jurisdiction in a particular way, or to rule in favor of a respondent, or to dismiss the case, and the tribunal erroneously refuses to do so because of an error of statutory interpretation or an error of fact. In these situations, this Court has regularly held that the matter did not concern the subject matter jurisdiction of the trial court or the agency.
Id.
at 417-18,
In
Freedom Express/Domegold,
the Court added further clarity to the concept of “fundamental jurisdiction” for purposes of challenging the normal expectation of administrative exhaustion.
Whether the County Code and Procurement Regulations in the present case contemplate a claim initiated by the County against a contractor “is a typical statutory interpretation or application issue to be determined by a final administrative decision and to be judicially reviewed” only after the administrative remedy has been exhausted.
Id.
at 13,
IV.
Heery, however, persists that they should not be forced to suffer through a futile administrative process when there exists clear case law supporting the notion that the agency’s consideration is without color of authority. On this score, Heery offers by analogy as conclusive the holding in
University of Maryland v. MFE, Inc.,
A.
In
MFE,
the University of Maryland informed one of its contractors, MFE, that the University was asserting a claim against the contractor for costs related to delay and design deficiencies in the construction of a campus library building. MFE denied responsibility, and the University submitted the claim to the State administrative process. Pursuant to that process, the director of the University’s Department of Procurement and Supply determined that the State was entitled to be indemnified for costs relating to MFE’s deficiencies. The administrative regulations
This Court, taking the case from the intermediate appellate court before it decided the matter, declined to consider the timeliness issue.
Id.
at 92,
The dispute in
MFE
implicated the administrative process outlined in Md.Code (1985, 2001 Repl.Vol.), §§ 15-201 — 15-223 of the State Finance and Procurement Article (“State Procurement Statute”). Under this statutory scheme, a “person who has been awarded a procurement contract may submit a contract claim to the procurement officer.” § 15-217(a)(2). The Court observed that there is “no provision in § 15-217 or, to our knowledge, in any other part of the subtitle, permitting the State unit to file either a protest or a contract claim.”
MFE,
As detailed in
MFE,
the Legislature’s determination not to provide expressly for State initiation of its claims via the administrative process was not inadvertent.
Id.
The basis of the law at issue was the American Bar Association’s Model Procurement Code for State and Local Governments (“Model Code”), which attempted to “bring greater coordination, simplicity, and uniformity to State purchasing and procurement processes, to consolidate and integrate the existing diverse
laws and regulations, and to recommend which processes should be in the law and which should be in regulations.”
Id.
The second draft of the Model Code, introduced concurrently in 1978 in the Maryland House of Delegates and Senate, allowed for the administrative adjudication of claims both against and by a contractor.
Id.
at 95-96,
During the same 1978 legislative session, a different bill creating a Board of Contract Appeals for the Maryland Department of Transportation was enacted and became law. That law gave the Board jurisdiction “over ‘all disputes other than labor disputes arising under a contract
The amended bill that failed in the 1978 session was reintroduced in 1979. The Court in
MFE
put great weight on the fact that, during its consideration, the assistant attorney general representing the Department of General Services expressed concern to counsel to the House Constitutional and Administrative Law Committee and the Governor’s office, among others, about the lack of an administrative remedy for contract claims brought by the State.
Id.
at 97-98,
The bill was reintroduced once more in the 1980 legislative session with the same language as the failed bills from the 1978 and 1979 sessions.
Id.
This time, however, it passed. The bill also repealed and superseded the Department of Transportation contract dispute process enacted in 1978.
Id.
Prior to the 1980 enactment, the ABA published recommended regulations to accompany its Model Procurement Code that unequivocally provided for administrative resolution of claims against a contractor by the government.
Id.
at 99-100,
The
MFE
Court held that the Maryland Legislature’s conscious and consistent refusal to amend its procurement laws provided conclusive proof that the Legislature did not intend to embrace administrative claims initiated by the State against a contractor.
Id.
at 102,
B.
Had Heery been able to demonstrate that the
MFE
decision was completely and clearly analogous to the circumstances of the present case, we would be more inclined to intervene in the administrative process here.
See, e.g., Perdue Farms, Inc. v. NLRB,
C.
Despite Heer/s contentions, we can not find at this stage that the County administrative process is “palpably without jurisdiction,” based on an analogy to the MFE decision. Heery has failed to demonstrate that the County ordi nance and its legislative history are so strikingly similar to the State statute at issue in MFE as to find that the County agency’s consideration of the County’s claims is clearly and unequivocally without authority.
Although the County Code and Procurement Regulations contain language and structure similar to the State Procurement Statute in
MFE,
there are several differences that erode our confidence that the two enactments are sufficiently identical as to warrant judicial intervention in the administrative process in the posture of this case as it reaches us. The State statute in
MFE
contained permissive language allowing the contractor the option of submitting a claim to the procurement officer or pursuing another remedy.
See
Md.Code (1985, 2001 Repl.Vol.), § 15-217(a)(2) of the State Finance and Procurement Article (stating that “[a] person who has been awarded a procurement contract
may
submit a contract claim to the procurement officer” (emphasis added)). The County Code in the present case, however, contains a mandatory provision under which a contractor
“must
submit any dispute arising under a contract to the Director.” Mont. Co.Code § 11B-35(a) (emphasis added). In addition, the County’s Procurement Regulations contain a provision allowing the County to implead a contractor into the administrative process; the State statute in
MFE
did not. Mont. Co. Proc. Regs. § 14.2.2.8. Such a provision partakes of the characteristics of the “cure” suggested by the assistant attorney general in the legislative history in
MFE,
and may indicate that the Montgomery County Council (“County Council”) here contemplated that its code and regulations allow for administrative adjudications of claims brought by the County against a contractor.
10
Heery also has made no showing that its involvement in the County administrative dispute resolution process will result in
any irreparable injury cognizable by this Court. Likewise, Heery failed to demonstrate that the County administrative process fails to provide an adequate remedy or judicial review of an assertedly erroneous ruling.
See Soley,
Our task in the present case is to determine whether the County administrative process is clearly and unequivocally without authority. Based on this record, we are unable to reach this conclusion. Heery’s desire to avoid the uncertainty of the administrative process must yield, for the moment, to the deep-rooted principle that ordinarily the administrative process must be exhausted before a party may expect judicial review.
JUDGMENT OF THE CIRCUIT COURT FOR MONTGOMERY COUNTY AFFIRMED. COSTS TO BE PAID BY APPELLANT.
Notes
. Included in both Heery International and HOK's contracts with the County were provisions requiring that each indemnify and provide legal defense for the County in regard to "any loss, cost, damage and other expenses, including attorney's fees and litigation expenses, suffered or incurred due to the contractor's negligence or failure to perform any of its contractual obligations.” The contracts also stated that, at the County’s request, "the contractor must defend the County in any action or suit brought against the County arising out of the contractor's negligence, errors, acts or omissions under this contract.”
. At oral argument, counsel for the County conceded that, although the contracts provided that any dispute would be decided under the County ordinance’s administrative dispute resolution process, the provisions in the contracts did not enlarge the jurisdiction of the County administrative agency beyond that supported by the language of the ordinance and regulations.
. The HOK contract includes near-identical language.
. There are no material differences in the 2004 Code and Regulations and the versions in place at the time of occurrence of the operative facts in this case.
. A demurrer was a pleading in which a party asserted that, as a matter of law, relief could not be granted on the facts alleged in the complaint. Paul V. Niemeyer & Linda M. Schuett, Maryland Rules Commentary 206 (3rd ed.2003). The demurrer's modern counterpart, the motion to dismiss for failure to state a claim upon which relief can be granted, is codified in Maryland Rule 2-322(b)(2).
. Maryland appears to be one of a small group of jurisdictions that continue to use the descriptive "palpably without jurisdiction" for the threshold principle. Based on a national search, only 17 judicial opinions were found that utilize the "palpably without jurisdiction” language in an administrative context (including the present one). More than half of those opinions are from this Court. Of the ten opinions that have used this phrase in the last twenty years, eight of these opinions are from this Court, with the other two from Idaho courts.
See, e.g., Regan v. Kootenai County,
These cases all derive their use of the exact phrase from the following passage in Professor Davis's 1958 edition of his Administrative Law Treatise:
The law embodied in the [Supreme Court] holdings clearly is that sometimes exhaustion is required and sometimes not. No court requires exhaustion when exhaustion will involve irreparable injury and when the agency is palpably without jurisdiction; probably every court requires exhaustion when the question presented is one within the agency’s specialization and when the administrative remedy is as likely as the judicial remedy to provide the wanted relief. In between these extremes is a vast array of problems on which judicial action is variable and difficult or impossible to predict.
Kenneth Culp Davis, Administrative Law Treatise, § 20.01 (1958) (emphasis added).
It is curious to note, however, that the exact wording, i.e. "palpably without jurisdiction,” noticeably is absent from subsequent editions of the treatise. The 2002 edition, for example, fails to make use of the "palpably without jurisdiction” descriptive phrase, even though it discusses and expands upon the “three-part test proposed in the 1958 treatise” for when administrative exhaustion is not required. Richard J. Pierce, Jr., Administrative Law Treatise, § 15.2 (4th ed.2002) (revised edition of Kenneth Culp Davis & Richard J. Pierce, Jr., Administrative Law Treatise, § 15.2 (3rd ed.1994)).
Although Professor Davis and his subsequent collaborators apparently abandoned this choice of language beginning with the 1983 edition (one year after this Court first utilized the "palpably without jurisdiction” standard in
MTA,
. Although some of the discussion in our cases merely “assumes, without deciding,” the existence as part of Maryland administrative law of the "palpably without jurisdiction" exception to the normal requirement of administrative exhaustion, the evolution of the standard indicates its availability in the appropriate case.
Compare MTA,
. The timeliness issue asserted by the University in
MFE
concerned whether the use of a fax machine and telephone follow-up satisfied the
regulation governing notice and filing of an administrative appeal.
. These two amendments involved amending the State Procurement Statute "to add the State as ‘one of the parties entitled to demand a
negotiation and seltlement of disputes' and adding a new [provision] permitting the State, in any appeal to the BCA by a contractor, to assert any counterclaim it may have against the contractor and any third-party claim arising out of the facts.”
MFE,
. It is clear that the County Code authorizes (and perhaps mandates) a contractor initially to bring a claim against the County using the administrative process. Nowhere in the County Code or Procurement Regulations, however, is there express language authorizing or mandating the use of the administrative process for claims brought affirmative ly by the County. At the circuit court hearing on the County’s motion to dismiss, counsel for the County acknowledged that such language was absent from the County Code. He explained that this was because the County "never contemplated the situation” where the County would have to bring a claim against a contractor. Under the County’s normal expectation in contract-related disputes, counsel explained further, the County would retain funds when there is a dispute, forcing unpaid contractors to initiate claims under the administrative process against the County. Counsel for the County further indicated that although the County took the position that the administrative process allowed for claims initiated by the County, this case was the first time in the nine years since the process was enacted that the County utilized it to bring a claim against a contractor. Nonetheless, we conclude that enough uncertainty about the agency’s jurisdiction exists on this record to prevent us from ruling in Heery's favor at this stage in the dispute. Our disposition, however, is without prejudice to Heery's maintenance of a jurisdictional challenge in the course of the administrative proceedings and any subsequent judicial review. All we decide, at this juncture, is that the County process is not "palpably without jurisdiction” to consider the County’s claims.
. It is also worth noting that in MFE, unlike here, the parties availed themselves of the relevant administrative process. In MFE, the University utilized its internal review process and MFE appealed that result to the BCA, which dismissed MFE's appeal for untimeliness. A comparison of the relative procedural postures alone distinguishes MFE from the present case.
