30 Ind. App. 595 | Ind. Ct. App. | 1903
Appellee brought this action upon a builder’s bond against John Moon as principal and George W. Hedrick, appellant, as surety. A verdict was returned and a judgment rendered thereon in favor of the appellee for $373.35. Moon refused to join in the appeal. Appellant Hedrick assigns as error the action of the court in sustaining demurrers to the second and third paragraphs of his answer and in overruling the motion for a new trial.
The complaint avers that John Moon entered into a contract with appellee to finish, under the direction and to the satisfaction of Homer Y. Place, architect, all the work included in a two-story frame residence agreeably to drawings and specifications made by said architect and signed by the parties aforesaid, and agreeably to the dimensions in said contract, including all the labor and material incident thereto; that the building was to be completed within a time stated, and in default thereof the contractor was to pay to appellee $1.50 for each day after the 1st day of September, 1897, as liquadated damages. Appellee agreed to pay for the work and materials $3,720 in instalments, according to such estimates as the said architect should malee; final payment to be made within sixty days after the contract had been completely performed. The contract further provided that in the event there should be. any claim for material or labor after all payments should be- made by said owner to said contractor for’ such performance*, that the said contractor should refund to the owner
Appellant Hedrick answered 'in three paragraphs, the first being a general denial. In the second paragraph ho admits the execution of the contract entered into betweep plaintiff and defendant Moon, and the execution of the bond as alleged in the complaint, but avers that the plaintiff violated her contract, in this, to wit, that the plans and specifications were so changed that, an entirely different house was constructed from that designated in the original plans and specifications which formed a part of the contract when the defendant signed said bond. The changes are not specified. The answer states that the plans and specifications were in the possession of the plaintiff, and that he was unable to designate the various changes. It is further alleged that the contract was broken by the plaintiff and Moon in this: that the time of the completion of said building was
The contract provided by article third that: “Should any alteration be required in the work shown or described by the drawings and specifications, a fair and reasonable valuation of the work added or omitted shall be made by the architect, and the sum herein agreed to be paid for the work, according to the original specifications, shall be increased or diminished as the case may be. In case such valuation is not agreed to, the contractor shall proceed with the alteration, upon the written order of the architect, and the valuation of the work added or omitted shall be referred to' three arbitrators, — no one of whom shall have been personally connected with the work to which these presents refer, — to be appointed as follows: one by each of the parties to this contract, and the third by the two thus chosen; the decision of any two of whom shall be final and binding, and each of the parties thereto shall pay one-half of the expense of such reference.” The condition of the obligation of the bond is as follows: “That as the above bound John Moon has entered into a contract with the said Mrs. L. W. Robbins to build a two-story double tenement frame residence according to the plans and specifications
While the obligation of sureties is strictissimi juris, the rule of constrxxctioii to be applied in the construction of suretyships is the' same that is to be applied to the construction of contracts ixx general. The provision for.the change of a contract binds the sureties the same as the principals, and by notice of such provisions the sureties are held to have consented in advance to the making of all such changes as are within the terms of the stipulations. Higgins v. Quigley, 23 Ind. App. 348, and cases cited.
The contract and bond each provided for changes in the construction of the building. Permission was thus given in advance by the surety for changes. They are to be considered together. Brown v. Markland, 22 Ind. App. 652. The second paragraph does not show that the changes made were not within the general scope or plan of the building proposed. The paragraph is wanting in a statement of facts. The third paragraph charges a lack of diligence upon the part of the appellee, but there is not sxxch a showing of negligence as might relieve the surety. Neither of these paragraphs sets up material facts which could not have been proved under the general denial; and even if the court erred in sustaining the demurrers, — which we do not concede, — appellant was not harmed by the ruling complained of.
The questions raised by this specification of error are presented, also, under the motion for a new trial.
It is urged hy the appellee that the appeal should be dismissed for, among other reasons, a failure to comply with rule three of this court, requiring marginal notes on each page of the transcript. The transcript of the evidence, containing 350 pages, is without marginal notes. The rulings of the court during the trial of the cause are not indicated by marginal notes. Without the help of a compliance with this rule we have examined the record and read the evidence. From such examination it appears that the merits of the cause were fairly tried and determined by the court below. The case seems to be one in which §610 Burns 1901 may be properly applied.
The judgment is therefore affirmed.