Hector Martinez and Company v. Southern Pacific Transportation Co.Hector Martinez and Company v. Southern Pacific Transportation Co.
Martinez appeals the trial court’s dismissal of his claim under
Martinez’s agent delivered a 2400 Lima Dragline, Model 66, to the Penn Central Railroad, the origin carrier, on February 11, 1974, for shipment from New Philadelphia, Ohio to Eagle Pass, Texas. The dragline was loaded onto fivе separate railroad cars. A single uniform bill of lading, which described the dragline as “used strip mining machinery and parts,” was issued by Penn Central, listing Martinez’s agent in Eagle Pass as the consignee.
The last of the five cars, which were shipped separately, arrived in Eagle Pass on April 2, 1974. Mаrtinez had to make reasonable repairs in the amount of $14,467.00 because the dragline was damaged in transit. These repairs were not completed until June 20, 1974. Martinez also alleges delay damages in the amount of $117,600.00 because the dragline could not be used from Marсh 1, when he contends that the last of the cars should have arrived, until June 20. The claimed sum represents the dragline’s fair rental value during this period.
After filing a claim as prescribed by the bill of lading, Martinez sued Southern Pacific, which as delivering carrier is liable for all recoverablе damages. Martinez framed his original complaint to allege three separate claims under the Carmack Amendment. First, Martinez sought recovery of the cost of repairing the damage to the
Martinez and Southern Pacific had already settled the first two of these clаims, when Southern Pacific filed its Rule 12(b)(6) motion to dismiss the third claim for loss of use. Southern Pacific argues that, because such damages are special, they are not recoverable under the Carmack Amendment absent notice of the possibility of such damages. The trial court denied this motion upon condition that Martinez amend his complaint to allege such notice. When Martinez refused, the district court granted Southern Pacific’s motion under Rule 12(b)(6). This ruling, which had the effect of dismissing all that remained of Martinez’s suit, is the basis of this appeal.
Martinez’s delаy claim involves two very different items. Lost use during the period of March 1 until April 2 resulted from a delay in transit. Lost use from April 2 until June 20 resulted from repair of the damaged goods. Neither the parties nor the district court have focused on the full import of this distinction. Martinez’s claimed loss during repair is not severable from the physical dainage to the dragline but is a part of the same legal claim. Thus Martinez necessarily settled his claim regarding damages for the repair period when he settled his first claim for damages to the dragline. The surviving issue is the appropriate measure of damages for the claimed loss resulting from Southern Pacific’s unreasonable delay’ in transportation.
The Carmack Amendment
1
governs Martinez’s claim for damages resulting from the delay in transit. That amendment incorporates common law principles for damages.
F. J. McCarty Co. v. Southern Pacific Co.,
[3-5] Normally, the remedy is an award of money damages to the aggrieved party as compensation for his economic injury.
2
This rule in effect protects the innocent party’s expectation interest, giving him the “benefit of the bargain.”
3
Martinez’s alleged injury in this case was deprivation of the dragline’s use between March 1, when it should have been delivered, and April 2.
We next assess the reasonable foreseeability of the plaintiff’s actual injury at the time of entry into the contract — here the bill of lading.
Globe Refining Co. v.
Lands
Cotton Oil Co.,
Martinez asserts that his loss resulting from the delay in shipment was reasonably foreseeable when he entered the contract to transport his dragline.
Hadley
held that the damages arising from an inoperative mill were not foreseeable results of delayed shipment of a shaft, without specific notice. It was not obvious that the shaft in
Hadley
was an indispensable element of a mill. In the instant case, however, it was obvious that the dragline is a machine which of itself has a use value. Some cases after
Hadley
have suggested that the injury resulting from loss of a machine’s use are not foreseeable results of delayed transport, because it is not a usual consequence although it is a proximate consequence.
See
11
Williston on Contracts, supra
§ 1344, at 226-27. These decisions are unwarranted extensions of
Hadley
and employ arbitrary and inflexible definitions of foreseeability. Capital goods such as machinery have a use value, which may equal the rental value of the equipment or may be an interest value. Thе latter is ordinarily interest at the market rate on the value of the machine. It might be quite foreseeable that deprivation of the machine’s use because of a carriage delay will cause a loss of rental value or interest value during the delay period.
7
Southern Pacific repliеs that it was as foreseeable that the goods were to be sold as that they were to be used. This contention proves too much because Hadley allows recovery for harms that should have been foreseen. The general rule does not require the plaintiff to show that the actual harm suffered was the most foreseeable of possible harms. He need only demonstrate that his harm was not so remote as to make it unforeseeable to a reasonable man at the time of contracting. Even if the dragline were being shipped for sale it does not follow that delay in shipment would cause no recoverable loss.
Southern Pacific argues that, because only market value damages are foreseeable under common law, damages for lost rental value must be special and therefоre require notice by Martinez. This argument confuses one common law method for computing damages with the underlying common law rule of awarding reasonable compensation for foreseeable injury from a contract’s breach.
The common law employs a number of methods for computing damages recoverable for unreasonable delay in shipment. One of these is the market value test that measures damages by the diminution in the goods’ value between the time of dispatch and the time of actual delivery.
See
11
Williston on Contracts, supra
§ 1342, at 223. That test, however, “is merely a method,” and it “is not applied in cases where . . . another rule will better compute actual damages.”
Great Atlantic & Pacific Tea Co. v. Atchison, T. & Ste. F. Ry.,
There is only one rule, of universal application, . . . and that is to give compensation for the loss suffered. Frequently, this ideal is found impossible of complete attainment; perhaps generally the market value rule is found to be the nearest approach to reaching the actual loss. But the market value rule is inapplicable when, on the facts, it is not the nearest practicable approach to an ascertainment of the actual loss. Each case must be governed by its own facts.
Martinez has stated a claim for damages resulting from the delay in shipment. We reverse the district court’s order of dismissal on this point, and remand for trial. We affirm, however, the district court’s decision to dismiss Martinez’s claim for damages resulting from the delay during repair.
REVERSED AND REMANDED IN PART; AFFIRMED IN PART.
Notes
. The Carmack Amendment,
. In some situations in which money damages cannot adequately compensate the innocent party, the court may order specific performance of the contract.
. Damages may be awarded for the expectation interest, the reliance interest, or the restitution interest of the aggrieved party. Fuller & Perdue, The Reliance Interest in Contract Damages (pts. 1-2), 46 Yale L.J. 52, 373 (1936-1937); J. Calamari & J. Perillo, Contracts § 205, at 328-29 (1970). If it is impossible to calculate a plaintiffs exрectation interest, courts award damages to protect his reliance interest, to restore him to his position before the contract was entered. If reliance damages do not represent a fair measure of recovery, courts calculatе damages on the basis of the restitution interest, to restore the benefit received from the plaintiff’s performance.
. In addition to the foreseeability limitation, damages may also be limited because of uncertainty, e.
g., United States v. Huff,
. J. Calamari & J. Perillo, supra note 3, at 329. As Professor Gilmore admonished, Hadley “has meant all things to all men.” G. Gilmore, The Death of Contract 50 (1974).
. There are two tests for determining special damages. The more restrictive test requires proof both that notice was given of special circumstances and that the defendant impliedly or expressly assented to bearing the risk of these damages.
Globe Refining Co. v. Landa Cotton Oil Co.,
. Unlike loss of use, Martinez would have had to plead notice had he sought to recover for a variety of damages that could not have been foreseeable here such as lost profits, the cost of idle labor hired to operate the dragline, the cost of idle equipment that had been rented to be used with the dragline, or the daily royalties Martinez was paying for the land on which he planned to run his dragline.
Cf. Texas Instruments, Inc. v. Branch Motor Express Co.,
. Diminution in market value is a proper measure of damages from a delay in carriage of food and other non-rentable goods.
E. g., Gulf, C., & Ste. F. Ry. v. Texas Packing Co.,
. This holding should hardly surprise Southern Pacific.
F. J. McCarty Co. v. Southern Pacific Co.,