378 Pa. 133 | Pa. | 1954
Opinion by
The Heat and Power Corporation, plaintiff in this case, entered into a contract with the Foust Distilling Company, the defendant, for a “New Boiler Installation” at the Glen Rock Distillery of the defendant company. In a letter from the plaintiff to the defendant dated December 21, 1945, the plaintiff outlined what it would supply and install. In a letter from the defendant to the plaintiff dated August 27, 1946, the defendant stated what it would accept. The plaintiff company began its installation work on January 15, 1947 but on April 30, 1947, it was ordered by the defendant to desist, the defendant complaining that defective equipment was being installed.
The plaintiff thereupon sued the defendant for breach of contract and the defendant counterclaimed against the plaintiff for breach of warranty. The plaintiff recovered a verdict of $39,471.08. The defendant failed in its counterclaim and moved for judgment n.o.v. and a new trial on the plaintiff’s claim, and for a new trial on its counterclaim. The lower court affirmed the verdicts and entered judgments thereon. The defendant appealed.
Although many matters were involved in the lawsuit, only one is the subject of contention in this appeal, namely, item No. 6 of the offer and acceptance.
“6. For the installation of 2 Westinghouse Single Retort Stokers with necessary equipment and damper control, we ask the sum of Eight Thousand, Five Hundred Dollars— $8,500.00
The Foust Distilling Company — No. 3
December 21, 1945
ALTERNATE: For the Flynn & Emrich Stokers on the B. & W. Boilers, we ask the sum of Nine Thousand, Five Hundred Dollars— 9,500.00
For the Detroit Double Retort Stokers, we ask the sum of Ten Thousand, Eight Hundred Dollars—
10,800.00
It will be noted that Flynn & Emrich do not meet the guarantee requirements, and the Detroit Stoker is not adaptable to boilers of the required type and size.”
In its acceptance of August 27, 1946, the defendant referred sketchily to item 6: “Stoker Installation — With Escalator Clause 8,500.00”
Whatever grief the defendant company has come to on account of this business transaction can be traced to this scantily-described item — “stoker installation.” No language dressed its purpose, no words gave the clothing of its identity, no phrase established its intention. What stoker installation did the defendant accept? The plaintiff had offered three distinctly different types of stoker, and the defendant laconically replied: “We will take a stoker installation.” It was inevitable then, when difficulties arose between the contracting parties, that some evidence was needed to show what it was that the defendant had accepted. When this followed, the defendant complained that such evidence offended against the rule that in the absence of fraud, accident or mistake, no
On April 8, 1946, the. president of the plaintiff company, John H. Zink, wrote to the president of the defendant company, Louis Mann, saying: “We are placing the order for the stokers with Flynn & Em-rich, Baltimore, Md., because after talking with Westinghouse on the phone this morning, I do not think it is possible for them to make delivery in time.”
On the. same .day Zink ..again wrote Mann: “We have this day placed our order with the Flynn and Emrich . Company for.vone. ■ (1) of their Stokers at Westminster..and two. (2) at Glenn Rock, in accordance with their original proposal. dated November 26, .1945 and covered by. our 'orders H-5572 and H.-5573...
.. “We agree-with you.:that.beeause. of, strike and other conditions:'at thé.Westinghouse Plant, that they .can not possibly make delivery of the stokers, and the Flynn and Emrich Stokers are ordered on your instructions because of . the .advantages of- their being a local concern,, .and", that. the- average' 150 % - rating will meét yoúr requirements.'. ........... •
; When, the stokers, arrived the defendant complained -that the/plaintiff/had" failed to.-.'live/up to "its" express and.- implied’, .".warranty.:that “.steam-.".pr.essúre;,:ef- - one hundred.-fifty- (15.0) qjoundsv would - be: delivered by the equipment:; furnished”- so' * that • the ."'.'Foust ’Distilling ■Company : “co.uld.".:operate;.fits.':,.'distilling- •• equipment, cookers;; mash tubs; . yeast .tubs -.and" all;other' compon
The plaintiff’ denied these assertions and stated that the Heat and Power Corporation had agreed to install equipment that would supply “The steam necessary for a mash-drying installation engineered by H. K. Ferguson Company which would require merely 8,600 pounds of steam per hour.” Further, that “the equipment being installed would have fully met all requirements,” if the defendant company had not ordered a cessation of all operations.
In this duel of charges and counter-charges, it was imperative that parol evidence be introduced to establish just what the plaintiff and defendant did agree to. Without the parol evidence which the lower court properly permitted the trial would have been a battle fought in a fog of doubt and mists of uncertainty.
The defendant company maintained that the “stoker installations” mentioned in its acceptance of August 27, 1946, meant Westinghouse stokers. The plaintiff company insisted that because of what had transpired between December 21, 1945 (the date of the original offer) and August 27, 1946, “stoker installations” meant Flynn & Emrich stokers. Only parol evidence could clear away the clouds 'of doubt so that the jury could intelligently meet the issue they were to decide.
The situation presented by this, litigation is not novel in the law. In the case of Fischer v. Anderson, 173 Pa. Superior Ct. 175, decided only last year', the defendant agreed' by. written contract to provide “Fin
In the case of Schwarts v. Whelan, 295 Pa. 425, the question arose as to how much plastering was to be done by the plaintiff since the written agreement between the parties did not go into any particulars on this feature of the construction job. The plaintiff introduced parol evidence to show the area of plastering intended by both parties. This Court, in affirming the verdict in the court below, said: “The contract being confessedly ambiguous on the point, and there being no writing or plan to make it certain, both parties had the right to produce parol evidence to resolve the ambiguity.”
As recently as November 9, 1953, in the case of Lipsie v. Dickey, 375 Pa. 230, 234, we were called upon
It would indeed be supererogatory to give further illustrations of a principle so well imbedded in the law. Aside from precedents, the most fundamental logic requires, when parties to a contract write important conditions in disappearing ink, that the court allow the use of such evidentiary restorer as is available to revive to legibility and enforceability the true intent of the parties.
We have considered all the other reasons advanced by counsel for the defendant company for judgment n.o.v. and for a new trial: that there was a variance between the allegata and the probata; that the court erred in refusing to grant a continuance after the plaintiff had introduced the letters herein referred to; and that the verdicts were against the weight of the evidence. We are not convinced that the lower court erred in the disposition of any of these matters. The issues were well stated in the pleadings, the cause was
Judgments affirmed..