61 Mo. 270 | Mo. | 1875
delivered the opinion of the court.
This was a suit on a promissory note for one hundred and eighteen dollars, given by the defendant to the plaintiffs in February, 1873,.for a balance claimed by plaintiffs to be due to them from the defendant for work and labor done and materials furnished,-in the construction of a sheet-iron and galvanized iron roof upon a livery stable belonging to the defendant in the town of Clinton, Henry county, Mo. The defendant pleaded that said roof was constructed in a negligent, unskillful and unworkmanlike manner, and of inferior materials, in consequence whereof it leaked, and defendant’s hay was wet, and his wall damaged, and he was put to inconvenience in the necessary removal of his stock from one portion of his stable to another, for all of which he claimed damages by way of recoupment, in the sum of $500. The plaintiffs denied the alleged negligence and injury, and the testimony on the issues thus made was conflicting.
There was a verdict and judgment for the plaintiffs for $64.62, from which defendant has appealed to this court.
As to the measure of damages, in the event the jury should find that the work was not done according to contract, they were told that such measure was i: the difference between the value of the roof agreed to be put on and the one actually put on.”
The court refused an instruction asked by the defendant, which included in the estimate of the defendant’s damages the injuries sustained by him from the wetting of the hay, and from having to remove the horses and buggies, but gave another at his request which allowed the jury to set off against the note any damages which they might find the defendant had sustained by reason of the defective construction of the roof.
This last instruction was improper, as it substituted the opinion of the jury for the established rules of law, and was also in conflict with the instruction given by the court of its own motion.
As to whether the instruction asked by the defendant and refused by the court, should have been given, there is some doubt. The damages are consequential, but not too remote, and are set forth in the petition. But the facts by which the propriety of giving such an instruction should be determined seem to be wanting in the record. It is not admitted by the pleadings, and does not appear from the testimony, when the roof was completed, when the various payments were made, or when the rains occurred which injured the hay and caused the removal of the horses and buggies. If the defendant had no knowledge of any defect in the roof at the time of the rains and the consequent injury, he would undoubtedly be entitled to recover to the extent of that damage; but if lie did know that the roof was defective and not impervious to
That portion of the instruction which required only a fair and substantial compliance with the contract, was objectionable and calculated to mislead the jury. The rule as to the measure of damages laid down by the court is a correct one as to building contracts, in all cases where the contract price is a fair valuation for the work, and it has been completed in general conformity to the requirements of the contract, but has been defectively executed in some particulars, and the suit is for the contract price, and defendant does not seek to recover any special consequential damages by way of recoupment.
When the building lias been completed, but differs in plan of construction or in materials employed from that which the builder contracted to erect, and this is the only element of
Courts have no right to make contracts for the parties, and they cannot compel a man to pay for a building for which he did not contract, and which he does not want, and which he would rather have removed from his premises, unless there has been some waiver on his part of strict performance. Builders cannot substitute their own taste or judgment or fancy for the stipulations of their contracts, and compel parties to pay for work done by them in open violation of their contracts, on the ground that it is equally as valuable as that which they have contracted to perform. (Smith vs. Brady, 17 N. Y., 173.)
When the work has not been completed but has been only partly performed, and the suit is therefore not for the contract price but for the value of the labor and materials, the same principle of compensation is to be aimed at, and the statement of the rule will vary accordingly as the work to be done may be worth more or less than the contract price. The opinion of the court in the case of Yeats vs. Ballentine, (56 Mo., 530) is not in conflict with the views here expressed.
As the instructions in this case were contradictory and inapplicable to the facts, the judgment of the circuit court will be reversed and the case remanded.