258 S.W.2d 488 | Ky. Ct. App. | 1953
The only question on this appeal is whether appellants are entitled to a mechanic’s and materialman’s lien for the value of materials and services performed by them as subcontractors in the construction of a house owned by the appellees. The answer to the question depends on when appellants last furnished the materials and services for which the statute gives a lien.
Appellants agreed to do the plastering on appellees’ house under a contract with the general contractor. They commenced work in November, 1950, and during that month completed the lathing and applied the first coat of plaster. They were then compelled to stop work because of cold weather and lack of heat in the house. "On the’‘following January 14 the general contractor notified appellants that heat had been placed in the building and that the'plastering could be completed.- On January- 19 appellants sent two tvorkmen to the house to make arrangements to complete the job. In addition to their tools, the men" took with them four bags of gauging plaster’to be used in completing the job. Although temporary heat had been placed in the building, the men found that a vat of lime and water to be used in making the plaster was still frozen solid. They proceeded to break up the lime arid ■ 'transfer it into smaller containers so as to facilitate its thawing. They also erected the scaffolding which was - necessary in applying the final coat of plaster. This work required about one-half day and one of the" men returned later to tend the fire. The gauging plaster referred to above was left in the building, but the record-is .silent as to its subsequent disposition.
Several days later, and before the lime had sufficiently- thawed for use, appellees informed appellants that th'e general contractor had been released from 'the job. They later' informed appellants that other persons had been employed to finish the plastering.
"On February 13 appellants gave appellees written notice of their intention to’ claim a mechanic’s and materialman’s lien under KRS 376.010(3) in the amount of $516.67, and the following day filed a statement of lien as required by the statute.
Subsection 3 of the statute requires that notice of the subcontractor’s intention to claim á lien must be given to the owner “within thirty-five days after the last item of material or labor is furnished”. It is admitted that if the work performed or the materials furnished by appellants on January 19 amounted to furnishing materials or labor within the meaning of the statute, then the notice given to appellees was in time; but, if those services and materials were not sufficient to create a lien, the notice was not given in time.
. This Court has held that the mechanic’s and materialman’s statute should be liberally construed. Stidham'v. Little’s
The' Chancellor was of the opinion -4md we:think correctly so — that.this case falls- within the rule laid down in Avery & Sons v. Woodruff-& Cahill, 144 Ky. 227, 137. S.W.-1088, 1090,-36 L.R.A.,N.S., 866. The- question in that case was whether the furnishing of lumber which did not become a part'of the building but which was consumed- in the use for which it was furnished, that is, in making concrete forms, was sufficient to create a materialman’s lien under the statute. The court allowed the lien,.and said in the opinion:
. “It-is sufficient if their use was necessary, and they were in fact used or consumed in the making of the improvements.”
It will be noted that the foregoing rule makes the lien contingent upon the existence of two conditions; first, the labor or materials must.be necessary; and second, as regards the materials, they must in fact be used or consumed in the making of the improvements. The Chancellor denied the lien in this case because it was not shown that any of the labor performed or materials furnished on January 19 was applied to or used in. the construction of the house. We think, he reached the right, result. There is no evidence that the .scaffolding constructed, by the workmen or the gauging piaster left by them was consumed or used ,,in. finishing the job.
We are not holding that the owner may intentionally defeat the materialman’s lien by his wilful refusal to use needed materials which have been furnished in good faith under prior agreement. In the absence of bad faith, however, we are of the opinion the rule laid down in the Avery case is sound and should be followed.
The judgment is affirmed.