Plaintiff and defendant, both corporations, entered into a contract by which plaintiff - agreed to make, finish and put in place certain fixtures in defendant’s building at St. Louis. The work was- to be dоne according to plans to the entire satisfaction of the ■superintendent and building committee, and to be completed by the first of December, 1878. under a forfeiture of ten dollars for each day’s delay. As a full compensation, defendant agreed to pay $4,800 on the completion of the work and acceptance of the same. The building was without fаult of either party destroyed by an accidental fire on January 2, 1879. At that time the pews in the gallery and pulpit screen had' been attached to the building. The- other fixtures, including the pews fоr lower or audience room, were in the building on the floor and workmen were engaged in putting them in place. The building was in the possession of defend
1. Besides the fact that the work was in progress after the date fixed by the contract for its completion, it also appears that by agreement between the parties the backs of a few of the pews were to be altered in some respects at the cost of the defendant. It does not appear whether the time for completing the work was extended by agreement or by acquiescence. Neither the extension of the time for the completion of the work, nor the agreed changes as to those qoews, affected the contract in its other provisions. The contract in all other respeсts remained in full force. Plaintiff cannot simply because of this delay and these alterations abandon the contract and sue for the value of the work.
2. Some reliance for а recovery is also placed upon an alleged acceptance, and in support of this we are cited to Lord v. Wheeler,
3. Where a contractor undertakes to build a house
On the other hand some of the courts of the states have expressly declined to follow the rule announced in Brumby v. Smith, and others apply rules in like cases inconsistent therewith. In Hollis v. Chapman,
Now in this case the fixtures were, it is true, to be put in place and completed to the satisfaction of the building committee, and to be paid for only when completed. But the contract is based upon the assumption, that the defendant would have its edifice erеcted and ready to receive the work. All this was a condition precedent to the performance of the contract by the plaintiff. The implied contract on the pаrt of the defendant. was to have and keep the building ready to receive these' fixtures and to furnish room therein for them for such length of time as would reasonably be required to put-them in place. The agreement to do all this is as much a part of the contract, as if expressed therein in terms. This the defendant failed to do. Besides this the house was in the possession, сontrol, care • and custody of defendant, and the plaintiff had nothing to do with its protection, further than to be without fault as to its own work. The contract was not, therefore, an absolute one to do the work at all hazards, but it was dependent upon the assumed and implied conditions before stated, conditions which the defendant was to perform and which it did not perfоrm. According to the weight of the AmerU can authority such a contract is severable to the extent
