34 Neb. 670 | Neb. | 1892
The plaintiff in error brought suit in the court below against J. A. Cook, as principal, and John Green, as surety, on a bond given for the faithful performance by Cook of his building contract with the plaintiff. The bond is as follows:
*672 “ Know all men by these presents, that we, J. A. Cook, principal, and John Green, sureties, are held and firmly bound unto J. A. Hayden in the sum of one thousand dollars, for which payment, well and truly to be made, we do bind and obligate ourselves, our heirs, executors, administrators, or assigns, each and every of them, firmly by these presents. Sealed with our seals this May 12, A. D. 1888.
“ Whereas J. A. Cook has contracted with J. A. Play-den to execute, construct, and complete a frame story-and-a-half cottage for the sum of eighteen hundred and thirty-seven dollars, by a contract dated May 12, A. D. 1888, hereto annexed: Now, the condition of this obligation is, that if the said J. A. Cook shall duly perform and keep his agreements as in said contract set forth, and shall pay for all material and work in and about said building, so that the same shall not be liable to any mechanics’ or other liens, and shall at all times protect said J. A. Hayden against any and all liens on said work and material, then this obligation is to be void, but if otherwise, the same shall be and remain in full force and virtue.
“J. A. Cook,
Contractor, Lincoln, Neb.
“John Green.
“In presence of
tt__n
The contract price for the building was $1,837. Cook was to furnish all labor and materials. The plaintiff claims damages in the sum of $500 by reason of the failure and refusal of Cook to pay for all the materials used and labor performed in the construction of the building mentioned in said bond, in consequence of which mechanics’ liens were filed against said building.
The defendant Cook is now a non-resident of the state, and was not served with a summons, nor did he appear in the action.
The answer denies that any mechanics’ liens were filed against plaintiff’s building, or that plaintiff has been compelled to pay out the sum mentioned in the petition, or any other sum, in consequence of the failure of Cook to keep and perform his covenants. The answer further avers that “said plaintiff never notified him that he would look to him (this defendant) to make good any loss on account of the contract of said Cook, or that he relied, or expected to rely, upon any obligation made by this defendant, or the said Cook was failing in any manner to comply with his agreement, or that he was failing to furnish any pay for the materials according to his agreement, or that he had failed to pay persons to whom he was indebted for work or materials on account of said contract with said plaintiff, or that liens were filed orto be filed against said premises; but, on the contrary, the said plaintiff paid out moneys to the said Cook when he knew that it was before the time provided by the statute at which said claims for materials became due and collectible, contrary to his duty in that regard, and thereby reduced the funds in plaintiff’s hands that would otherwise have been abundant to have paid off and satisfied all liens against said premises.”
All allegations of the answer were denied by the reply.
At the close of plaintiff’s testimony the defendant Green moved for a nonsuit, on the ground of the insufficiency of the evidence, which was granted, and the suit was dismissed at the costs of the plaintiff. If, under the evidence
The first contention is that there is no proof that a written contract for the erection of the building was ever entered into between Cook, the contractor, and Hayden, the owner of the building. The evidence shows that a contract for the erection of the building mentioned in the bond was prepared according to the direction and understanding of the parties, which contract bears date May 12,1888. For some cause, doubtless an oversight, neither Cook nor Hayden signed it. It does, however, appear that the bond on which the suit was brought was written upon the back of said contract. It will be observed that the bond recites that Cook has contracted with Hayden to construct a frame story-and-a-half cottage for a specified sum, according to a contract dated May 12, 1888. One of the conditions in the bond is that Cook “shall duly perform and keep his agreements as in said contract set forth.” The defendant in error ii-j estopped by these recitals to deny the execution of the contract. The rule is as well settled as anything in the law that sureties are estopped to deny the facts recited in their obligations; in other words, they cannot set up and prove facts to contradict their own bonds. (Brandt on Suretyship & Guaranty, sees. 29, 30; Gudtner v. Kilpatrick, 14 Neb., 347; Adams v. Thompson, 18 Id., 541; Love v. Rockwell, 1 Wis., 331; U. S. v. Bradley, 10 Peters [U. S.], 365; People v. Hoson, 20 Pac. Rep. [Cal.], 369; Rogers v. U. S., 32 Fed. Rep., 890; Collins v. Mitchell, 5 Fla., 364; Green v. Wardwell, 17 Ill., 278; Shaw et al. v. Havekluft et al., 21 Id., 127; Otto v. Jackson, 35 Id., 349.) The same principle was recognized and applied in the case of Gudtner v. Kilpatrick, cited above. That was a suit upon an appeal undertaking. The defense was that no appeal was taken, nor could be, for the reason that the same was prohibited
Otto v. Jackson, supra, is analogous to the case at bar. That was an action upon a guaranty of the faithful performance by tenants of the covenants of their lease. On the trial objection was made to the introduction of the lease in evidence, for the reason that the execution by one of the lessees was not proven. It was held that the guarantors were estopped by their guaranty from denying the execution of the lease. So in this case, we think, Green is estopped to deny that the contract, upon the back of which the bond was written, was neither executed by, nor was it the contract of Cook and Hayden. The bond in express terms refers to and recognizes such instrument as being the contract under which the building was to be constructed, and its terms and conditions are as binding upon the obligors of the bond as though the same were set out at length in the body of the bond.
It is insisted that the surety is released from the obligation of his bond because the terms of the building contract relating to time and manner of making payments were not observed, and for the further reason that certain changes, alterations, and additions were made in the building, during its construction, not called for by the contract, nor plans and specifications, which form a part thereof. The third article of the building contract provides that “should the said party of the second part, at any time during the progress of the said work, require any alterations of, deviations from, additions to, or omissions in the said work, he shall have the right and power to make such change or changes, and the same shall in no way injuriously affect or make void the contract; but the difference, for work omitted, shall be deducted from the amount of the contract by a fair and reasonable valuation; and for additional work required in
It fully appears from the testimony that, during the progress of the work, some changes and additions in the building were made which increased the cost thereof, although not to a considerable extent, while other changes were made without additional expense. But all the alterations and additions which were made are fully provided for and covered by the clause of the contract above quoted, and the making of them did not have the effect to release and discharge the defendant in error from his obligation as surety. (Dorsey v. McGee, 30 Neb., 657.)
After the bond was given Cook constructed a barn for Hayden, but the proofs show that it was erected under a contract separate and distinct from the one for the erection of the dwelling. It is not sought to make the defendant in error responsible for the faithful performance of the barn contract. It is obvious that neither the entering into of such contract, nor the erection of the barn thereunder, in any manner affected the liability of Green on his bond for the damages sustained by the plaintiff by reason of the failure of Cook to carry out the terms of the contract for the erection of the dwelling.
We will next consider the question of payments. The contract provided that payments were to be made on weekly estimates of the architect for labor furnished, less ten per cent, and for all materials as soon as vouchers were obtained from subcontractors or parties who furnish materials. The balance was to be paid at the expiration of ten days after the completion of the work.
The testimony in the bill of exceptions shows that, after the completion of the job, liens were filed against the building for labor and materials used in the construction of the
It is contended that the payments to the contractor were made in violation of the terms of the contract, for the reason they were "paid without the presentation of vouchers of the subcontractors who furnished materials for the construction of the building, and because the same were paid prior to the expiration of sixty days allowed by the statute to subcontractors to file liens, therefore the surety is released. There is nothing in the testimony to show that the several payments made to Cook, which amounted to $887, were to apply on materials, but it does appear that this sum was paid upon estimates furnished by the architect, and in the absence of any evidence tending to establish the contrary, we will presume that the same was paid according to the letter of the contract, which authorized payments to be made for labor furnished, without the production of vouchers therefor. It may be true that Hayden paid the contractor money for materials furnished for which vouchers of the material-men were not produced, and that he did not retain ten per cent of the amount due for wages, as required by the terms of the contract. If such is the case, and the surety did not consent thereto, it would be such a departure from the contract as to discharge the surety. If the defendant in error relies upon the failure of Hayden to observe the provisions of the contract relating to payments, as a release from the obligation of his bond, he should have brought the same into the record by pleadings and proofs. It is nowhere alleged in the answer that payments were
It is finally insisted that the defendant is discharged from his obligation because the plaintiff paid out money to Cook before the expiration of the time allowed by the statue to subcontractors to file their liens. The second section of the mechanic’s lien law authorizes any person or subcontractor to file a lien upon the building in which such material or labor is used, within sixty days from the performing of such labor or furnishing such material; and the same section provides, in effect, that the owner of the building cannot be sued until the time for the filing of liens has expired. The contention is that this section of the statute is a part of the building contract in question, and that it was the duty of Hayden to withhold payment to Cook until after the time had expired for filing liens against the property, and, having failed to perform such duty, he cannot recover from the surety the amount he was required to pay to liquidate such liens. We are unable to perceive that the provisions of the section referred to have any bearing upon the case before us. Of course, as between the owner of the building and the persons who performed the labor or furnished the materials for the construction of the improvement, a payment to the contractor before the time had elapsed for filing liens, although the same was made according to the terms of the contract, would be at the owner’s peril, and would not defeat any lien filed in time. But not so as to the surety, for as to him the only duty which the owner was required to discharge was to
There is testimony tending to support the plaintiff’s cause of action which should have been submitted to the jury, and, such being the case, the motion to nonsuit the plaintiff was improperly sustained. The judgment is reversed and the cause remanded for further proceedings.
Reversed and remanded.