164 P. 729 | Or. | 1917
delivered the. opinion of the court.
The sole assignment of errors on behalf of plaintiffs is as follows:
“That the court erred in not rendering judgment for the plaintiffs in a larger amount.”
“In the later cases courts have shown that they are no longer disposed to scrutinize assignments of error with the minuteness which was applied in the earlier decisions”: 2 E. C. L. 163.
The bill of exceptions shows that plaintiffs pointed out to the lower court with precision and in great detail what their contentions were, and these contentions are presented in this court with the same clearness in plaintiffs’ briefs. In view of these other portions of the record we think the assignment of error above quoted sufficiently serves the purpose designed by the rule of this court.
“The general principle applicable to the case of a special contract for erecting a house, when in the progress of the work there have been alterations or additions not originally contemplated nor expressly provided for, seems to be that as far as the work can be traced under the original contract, it shall be paid for under that contract, and that the residue which cannot be brought within the contract shall be paid for as if there were no contract. But the safety of employers, and the good faith proper to be observed in all cases, requires that this rule should be so applied as not to violate the principles above stated; and they seem to indicate further, that extra work either in quantity or quality, unless done under an express agreement, or at least a statement of the price, should not be charged for at a greater rate in reference to the measure and value price of such work, than the contract price bears to the measure and value price of the work contracted to be done. So that if the contract price was a fourth or a fifth less than the price estimated by measure and value, the extra work should not be estimated at more than three-fourths or four-fifths of its price according to measure and value.”
“That both the said Bergsvik and said Froyseth were unacquainted with the nature of the ground and soil or depth necessary for a proper foundation, and that Froyseth being the subordinate, was required frequently during the progress of the work, to stop operations until he could consult with Bergsvik, who was not present upon the work, and that these delays and the extra depth to which plaintiffs were required to excavate prevented the plaintiffs from doing the work or completing it within the time originally contemplated and fixed by the contract.
“That the specifications provide that the defendant shall furnish plaintiffs with stakes at all times to indicate the depth of the grade and excavation, and that this the defendant at all times refused to do, and that the furnishing of the same would have been a material help and assistance to the contractor in the performance of his work, and the refusal of the defendant to*215 so furnish them prevented the plaintiffs to the extent that it was impossible for them to complete the work in the time originally contemplated by and fixed in the contract.
‘ ‘ That the refusal to furnish stakes mentioned in the last finding, and the refusal of the defendant, through its agents, to at any time advise the plaintiffs the depth necessary for the excavation, required the plaintiffs to excavate the material in layers; thereby, the plaintiffs were required to make many small operations of what would ordinarily be one complete operation, and thus prevented the plaintiffs from doing the work within the time originally contemplated and fixed by the contract.”
The testimony showed without contradiction that the method of excavating exacted by defendant’s engineers added greatly to the expense and burden of the work. The findings above quoted have the force and effect of a special verdict. Plaintiffs are entitled to the benefit of any conclusions of law arising from them. We think the conclusion is inevitable that plaintiffs sustained material damage by these burdens imposed upon them and that they are entitled to such damages over and above the contract price as will make them whole. The Circuit Court allowed plaintiffs only the contract price for 6,152 yards of excavation and allowed an increase of 20 per cent there-over for excavating 104 yards. The damages so awarded amount to $41.60, a sum scarcely more than nominal. The finding of the lower court was to the effect that the disadvantageous conditions of which plaintiffs complain applied to the whole excavation. There is abundant evidence to support this finding. It follows that the damages of plaintiffs should be predicated on the entire excavation and not confined to an insignificant fraction thereof. We can find no better rule for admeasuring the damages than that ap
The defendant assigns error on the refusal of the lower court to sustain a motion for a nonsuit. As already indicated, we think the evidence sustained the right of plaintiffs to recover on a quantum meruit for the reasons alleged in their amended complaint. The contention of the defendant on this branch of the case is based chiefly on another ground. The defendant demanded of plaintiffs a bill of particulars prior to
“A party may set forth in a pleading the items *of an account therein alleged, or file a copy thereof, with the pleading verified by his own oath, or that of his agent or attorney, if within the personal knowledge of such agent or attorney, to the effect that he believes it to be true. If he do neither, he shall deliver to the adverse party, within five days after a demand thereof in writing, a copy of the account, verified as in this section provided, or be precluded from giving evidence thereof. The court or judge thereof may order a further account when the one filed or delivered is defective. ’ ’
“I apprehend that it is not the office of a bill of particulars to state the grounds of a plaintiff’s claim, hut simply to point out the items and particulars which he claims, in such a manner as will enable the party to prepare for trial, and if the specification be ambiguous or susceptible of a double interpretation, the defendant should apply to have it made more definite and certain, or the plaintiff would be permitted to give any evidence not clearly excluded hy the terms used, subject only to the duty of the Court to see that the defendant is not misled to his prejudice.”
Under the contract plaintiffs were entitled to a monthly estimate of their work and to payment month by month of 90 per cent of the amount found due under the estimates. In a number of cases they marked estimates “O. K.” over their signature. It is claimed that this circumstance and the acceptance of money under the estimates preclude a recovery in this case. The finding of the lower court on this subject was as follows:
_ “With reference to the estimates hereinbefore mentioned, the engineers in charge for the city, without any participation therein by the plaintiffs, made out statements of the amount of work done during the previous month and these statements were from month to month received by the plaintiffs, but the plaintiffs at no time represented to the defendant that such estimates were received in final payment, and at no time represented to the defendant that the plaintiffs were waiving their claim for the reasonable compensation of the work performed and labor furnished, and the defendant, by paying said amounts to plaintiffs has in no wise prejudiced itself or changed its position because of the acceptance by plaintiffs of said estimates, and the plaintiffs at times marked an O. K. upon the estimates, but that no importance was attached to this O. K. on the part of the city, and the same was not attached by the plaintiffs nor understood by the defendant as being any agreement as to the correctness or finality of said estimates, and the same are not in any wise final, but on the contrary by the specifications*221 herein and by the conduct of the parties, the whole matter was at all times left to final adjustment at the conclusion of the work, and that at such time of final adjustment the plaintiffs and the defendant were unable to agree either as to the basis of the adjustment or the amount owing to plaintiffs.”
The defendant contends that this finding is without support in the evidence. There is testimony of the plaintiff Meager that he complained to Mr. Bergsvik of the manner in which plaintiffs were required to excavate and that Bergsvik said:
“Gro on and do your excavating and a good job of concrete and we will take care of this in some way.”
Plaintiffs claim to have relied on this assurance from defendant’s engineer and to have regarded the monthly estimates as tentative. They frequently complained to defendant’s representatives that much more was demanded of them than they were required by the contract to render. They notified the city’s representatives several times that they would expect additional compensation.
Numerous other objections and exceptions were reserved to the testimony on the part of the defendant but it is not deemed necessary to set them out in the opinion. We are clear that no reversible error was committed by the lower court in the respects complained of.
Our attention is directed by the defendant to an error of $31 in the judgment of the lower court. One of the items making up the amount allowed plaintiffs is an item for force account aggregating $3,359.85. It appears from the forty-second finding of fact that this item should be $3,328.85. The defendant is entitled to have the judgment corrected to the extent of
Modified and Affirmed.