142 S.W. 629 | Tex. App. | 1911
Appellant brought this suit against appellee to recover $500 special damages on account of about two months' delay in shipping a printing press from Dallas to Montgomery, Tex., setting out with sufficient certainty the various items of damages alleged to have been suffered by him on account of such delay, after notice to appellee. He did not allege that appellee was informed of any facts that would put it on notice as to such damages, at the time of the shipment or prior thereto, but did allege that a portion of said printing press was promptly delivered, and that thereupon appellant notified appellee of the failure to deliver the remaining portion, and that without the same, the portion delivered was useless, and also of the purpose for which said printing press was ordered, and the damages that he would suffer if the remaining portion of said press was not promptly delivered; that thereafter, from time to time, he notified appellee as to the damages he was suffering, and would continue to suffer, by reason of the failure to make such delivery. Appellant sued for the damages alleged to have accrued to him after suchnotice was given to appellee. The trial court sustained a demurrer to the petition, and, appellant declining to amend, his suit was dismissed. From the judgment sustaining such demurrer and dismissing said suit, this appeal is prosecuted.
1. Appellant's allegations were not that appellee failed to deliver said press after its arrival at Montgomery, but that the delay was in the shipment, so that the alleged facts do not bring this case within the rule laid down in Bourland v. Ry. Co.,
In Railway Co. v. Belcher,
These decisions, as well as similar decisions in other jurisdictions, and the statements of text-writers in accordance therewith, are based upon the case of Hadley v. Baxendale, 9 Exch. 353, from which we make the following excerpt: "Where two parties have made a contract, which one of them has broken, the damages which the other party ought to receive in respect of such breach of contract should be such as may fairly and reasonably be considered either as rising naturally — i. e., according to the usual course of things, from such breach of contract itself — or such as may reasonably be supposed to have been in the contemplation of both parties at the time they *630 made the contract, as the probable result of the breach of it. Now, if the special circumstances under which the contract was actually made were communicated by the plaintiff to the defendants, and thus known to both parties, the damages resulting from the breach of such contract, which they would reasonably contemplate, would be the amount of injury which would ordinarily follow from a breach of such contract under these special circumstances so known and communicated. But, on the other hand, if these special circumstances were wholly unknown to the party breaking the contract, he, at the most, could only be supposed to have had in his contemplation the amount of injury which would generally arise, and in a great multitude of cases not affected by any special circumstances from such a breach of contract."
This is but another method of stating the doctrine of proximate cause, where damages are claimed on account of a breach of contract. The breach must be the proximate cause of the injury; that is, the injury must be such as was the natural and probable result of the breach under the circumstances — and, therefore, such as under the circumstances known to the party committing the breach ought reasonably to have been foreseen by him.
With the general proposition announced in Hadley v. Baxendale, we have no quarrel, but, in our opinion, the expression in that case that damages recoverable on account of a breach of a contract must be "such as may reasonably be supposed to have been in the contemplation of both partiesat the time they made the contract, as the probable result of the breach of it," has been applied to cases not within the reason of the rule thus laid down.
As was said by Mr. Justice Williams in Bourland v. Railway Co.,
In applying the rule above referred to to the facts in the Bourland Case, the court said: "None of the reasons exist for which such notice has been required in other cases." What are these reasons? In the Belcher Case,
It is a maxim of the common law that where the reason ceases the law ceases. Under the laws of Texas, none of the above reasons, except the last one, could exist for requiring such notice. The railroad company could not have declined to accept the shipment; it could not have enforced a stipulation against its own negligence; it could not have charged more or less than the rate fixed by the Railroad Commission for that class of freight. The notice given after the freight was shipped and before it was delivered did not impose an additional contract upon it. It required it to do no more than it had previously contracted to do, and that was to forward the freight with reasonable promptness, and notice of the special damages that would accrue to the consignee by reason of continued delay in such shipment, given after the shipment had begun, would just as effectually enable the railway company to guard against further breach of its contract, as would such notice given at the time the contract was made, have enabled it to guard against any breach of such contract. To our minds, damages arising from the breach of a contract, after notice is given of the *631 consequences of such breach, are just as much within the contemplation of the party breaching said contract, as if such notice had been given at or before the contract was made, where no additional contractual obligations are sought to be imposed by reason of such notice.
Upon the authority of the Supreme Court of this state, which is binding upon us, but for no other reason as we see it, we affirm the judgment of the trial court in this case.
Affirmed.