61 Mo. App. 64 | Mo. Ct. App. | 1895
The plaintiff is a plasterer by trade, and he sues the defendant for work done and materials furnished in building a house. At the close of his evidence the court compelled him to submit to a nonsuit, upon the ground that the defendant in the first instance had not ordered the work to be done, and had refused, during the continuance of the work and after its completion, to obligate himself to pay for it.
An inspection of the evidence makes it quite clear that the plaintiff did the work, for which he sued, without a direct request on the part of the defendant. The only question is whether the facts and circumstances, as shown by the plaintiff’s evidence, were sufficient to authorize the jury to infer a previous request.
The plaintiff’s evidence shows substantially these facts: The defendant entered into a contract with the firm of Anderson & Brothers for the erection of a dwelling house. The plaintiff became a subcontractor for the plastering under the original contractors. The house was to be constructed according to certain plans and specifications. The building contract provided that reference should be had to the plans only for the dimensions of the work. On the plans, one room in the- attic was marked unfinished, but the plans called for studding and “furring,” which indicated that the room was to b© plastered. When the plaintiff was notified by the contractors that the building was ready for the plasterers, he sent a gang of his men to work. They commenced work on the room in the attic, and, when the plaintiff went to the building a few days afterwards, he found that the laths had been put on and the room partly plas
Whether the plastering of the room was included in the contract with Anderson & Brothers is a matter of no consequence. Conceding that it was not included, the plaintiff should have protected himself by special contract with defendant, or left the work undone.
In our opinion the nonsuit was properly granted, and therefore the judgment will be affirmed.