122 A. 76 | Conn. | 1923
From the finding of facts it appears that the plaintiff and all of the defendants (except Anderson and Larson) furnished materials and rendered services in the construction of a dwelling-house for Anderson and Larson upon a lot of land in West Hartford owned by them, and that the plaintiff and all of the other defendants filed mechanics' liens against the real property; and that the commencement of each lien was the date of the beginning of rendering services or furnishing materials. Each of the lienors was an original contractor with the owners, and there were no other general contractors. The property was sold by judgment *345 of the court for $5,150, and a net sum of $4,855.26 remained for distribution among the lienors after payment of costs and expenses of sale. The aggregate amount due to all the lienors was $6,471.84. The court in its judgment ordered the sum remaining for distribution to be paid and apportioned pro rata among the lienors, and overruled the claim of the appellant that they should be paid in the order of precedence and priority of their incumbrances according to the dates of commencement of the various liens, from which judgment the appellant appealed, assigning the application of the rule of division adopted by the court as error.
Very little in the way of uniform doctrine can be derived from the construction which has been placed upon statutes of the different States relating to mechanics' liens, by reason of the diversity of the terms employed. Some of them settle the question involved in the instant case by express provisions as to priority, others have more general provisions. These latter may be said to fall into two classes: in one, all liens attach from the commencement of the building; in the other, liens attach from the commencement of work or of furnishing materials. As to the former class it has been generally held that lienors prorate their claims and that among them there is no priority. In considering statutes falling in the second class, the construction has ordinarily been that priority exists, and that, as among themselves, lienors are preferred in the order of time at which they severally commenced to render services or furnish materials. The Connecticut statute is included in the second class above defined. The diligence of counsel and investigation by the court has failed to find more than two cases, Choteau, Merle Sandford v. Thompson Campbell,
In Kendall v. Pickard,
The statute of New York relating to mechanic's liens (N.Y. Consol. Laws, 1st Ed., Vol. 3, Chap. 38, Art. 2, § 3, p. 3140), provided the contractors should have a lien on the property improved or to be improved and upon the improvement, from the time of filing a notice of such lien. The Act has been construed to give priority to lienors according to the dates of filing their respective liens. Hall v. Thomas, 110 N.Y.S. 979; Western Sash, D. L. Co. v.Gaul Const. Co., 126 N.Y.S. 1110; Vogel BinderCo. v. Montgomery,
Passing to a review of our own statutes concerning mechanics' liens, and decisions applicable to the question under consideration, we find that the first statute upon the subject was enacted in 1836, Public Acts of 1836, Chap. 76; and § 1 subjects a building *347 and the land whereon it is placed, in any incorporated city, to a lien in favor of a contractor whose claim for services performed or materials furnished in the erection or repair of such building shall exceed $200, and provides that the sum due "shall be a lien on such land and building, and shall take precedence of any other lien or incumbrance, which originated subsequent to the commencement of such building or repairs, and such premises shall be liable to be foreclosed by such contractor or contractors, in the same manner as if held by mortgage."
In 1838 the statute was amended to include buildings located anywhere in the State, and in 1839 a right of lien was extended to subcontractors. In 1855 (Public Acts of 1855, Chap. 76) there was added to § 1 of the law of 1836 above cited, the words: "subject to apportionment as provided in the fifth section of this Act." This fifth section is substantially what we now have in General Statutes, § 5220, relating to liens of subcontractors.
Various changes were made from time to time in the provision of the lien law, but none affecting the question now under consideration until the Revision of 1875, when the words of § 1 of the Act of 1836 were changed by striking out the word "lien," so that the section as revised, reads: "and shall take precedence of any other incumbrance originating after the commencement" etc. No substantial change in this section was made in subsequent Revisions, and it now appears in General Statutes, § 5217. Both of these sections are printed in the footnote.* *348
As we have stated, appellant claims precedence and priority for the various liens according to the time in which each accrued. The appellees claim an apportionment of the available fund pro rata in accordance with the amounts of their several claims, and in support of this contention advance the following reasons: First, that the rule of equity is equality, and that in default of an express provision in unmistakable *349
terms giving priority, this rule should have effect in construing the statute considered. This is the ground of decision adopted by the court, as appears from its memorandum, wherein it is said: "This statute says nothing as to priorities or pro rating, but we think the spirit and intent of the statute, the mischief which it was designed to remedy, and the application of equitable principles, all require that the statute be construed as giving an interest to each lienor in proportion to his claims." This ground is also adopted in the two cases favorable to the contention of the appellees before referred to, Choteau, Merle Sandford v. Thompson Campbell,
Examining prior decisions of this court, we find in the opinion in Chapin v. Persse Brooks Paper Works,
Passing to the last claim of the appellees, that the *352 words relating to apportionment deliberately incorporate in § 5217 the apportionment provided for in § 5220, as limiting the effect of the word "precedence," we would, in addition to what we have said before, now call attention to the basic error which underlies the entire contention of the appellees. It lies in this, that they fail to view the mechanics' lien law as a single enactment covering the entire subject. In view of this last fact, the view which we take of the Act is clear and apparent. Its first section (§ 5217) is concerned with liens in general and defines rights thereunder and states their order of precedence, but further on the law makes a special and different provision for subcontractors whereby they are treated differently from original lienors, and for that reason the statement of the general rights of lienors in § 5217 is properly qualified by the reference to § 5220, wherein the special and superior rights of subcontractors are defined.
Possible inequities arising from the construction which we have given the Act have been suggested; situations equally inequitable can be instanced with reference to the enforcement of the pro rata rule. This practical consideration is, however, evident, a bidding contractor knows the law, sees the plans and specifications, is thereby aware of what work comes before his own part of the job and what comes afterward. He is in a position to safeguard his interests, and he knows what chances he is taking.
There is error, the judgment is reversed and the case remanded to the Superior Court for entry of judgment in accordance with this opinion.
In this opinion the other judges concurred.