*1 tempt of the court’s final for his order apart turn over title
refusal However, Cooperative. Lau-
ment units purged
rins himself of re contempt
turning ownership mutual contracts
Cooperative. 13,1979, On October the trial contempt
court set aside the The order.
appeal the contempt accordingly citation Corp., v. moot. Marshall Whittaker Ber Forge
wick & Fabricating
1141, 1145(3d 1979); Cyclopedia Cir. 15A (3d Supp. Procedure
Federal 87.104 ed.
1981).
XI summary, the trial err in court did not
concluding that their defendants breached fiduciary
contractual and Accord- duties.
ingly, rulings affirm the trial court’s damages.
liability and We also affirm injunction of an barring
issuance the sale of
apartment units GDLC. The
defendant Laurins’ civil contempt citation
moot.
HARTFORD ACCIDENT AND INDEM- COMPANY, Appellant,
NITY
v. COLUMBIA,
DISTRICT et OF
al., Appellees. COLUMBIA, al., OF
DISTRICT et
Cross-Appellants,
HARTFORD ACCIDENT AND INDEM- COMPANY, Cross-Appellee.
NITY 80-581,
Nos. 80-748. Appeals.
District Columbia Court
Argued 6,May
Decided Feb.
Weiss, performed electrical work on the project. In accordance l-804a, amended, Pub.L.No.93-89, as 305, Weiss, Stat. contractor, furnished a bond se- *3 persons protect cured from sup- Hartford plying labor and material under contract.2 complaint a In June 1978 Heller filed against claiming Weiss and Hartford Heller’s property was vandalized as a result provide adequate of Weiss’ failure securi- George C., B. Reynolds, Washington, D. addition, ty job at site. Pelland, with whom Washington, Francis J. sought recovery of costs incurred as a result C.,D. brief, was on the for Hartford Acc. performance An delays. amended com- and Co. Indem. 24, 1979, plaint, August filed added a claim Christopher Kerns, Washington, C., M. D. for the unpaid balance of contract. The Columbia, the District of et al. $31,179against trial court awarded Weiss (in- and Hartford for the contract balance NEWMAN, Before Judge, Chief and $5,700 $1,949 cluding damages, vandalism FERREN, MACK and Judges. Associate $15,258 change, conduit $8,272, 4” original # contract MACK, Judge: Associate $2,500 balance); for the of a This action brought was under D.C.Code estimate; $1,200 for off-site l-804b1 in the name of the District Delay damages costs. totalling of Columbia for and on behalf of Heller $24,169 against were awarded Weiss while (Heller) Electric Inc. against Weiss only delay damages in were awarded Construction (Weiss) Inc. and Weiss’ surety, against Hartford. Both Hartford and Hel- Hartford Indemnity Accident and Company judgment. ler from the We affirm (Hartford). part in part. and reverse in In 1975the District of Columbia entered While raises several issues on a public into contract with Weiss for the appeal, primarily alleged it is construction of the Wheatley Playground permitting court erred in the amended Heller, Addition. as a subcontractor of to relate back to the date of the (b) Every part: Section l-804b states in relevant suit instituted under this section brought in shall be the name of the District of Rights § l-804b. of laborers and material- person suing, for the use of the in Columbia payment men to sue on bonds—Prior notice Superior of the District of Colum- required of claim in certain cases—Time limi- bia, irrespective controversy of the amount in brought tations —Suit to be name in of Dis- suit, shall be com- in such but no such suit trict of Columbia. year expiration one after (a) Every menced after the person who has furnished labor day on of the was which the last labor prosecution or material in the of the work by performed supplied provided him. contract, or material for in such payment liable The District of Columbia shall which a bond furnished payment any expenses paid this costs or Act and who has not been full any expiration period therefor before ninety such suit. of a days day after the on which last of effect, provides payment “an al 2. In bond performed the labor was done or him or remedy ordi liens ternative narily mechanics’ supplied material was or furnished him private made, available construction for which such claim shall have right amount, projects.” J. W. Bateson & Co. Board to sue on such bond for the the U.S. 586, Trustees, thereof, unpaid 55 L.Ed.2d at S.Ct. balance prose- time of cute said action to institution such suit judgment and execu- final justly tion for the sum or sums due him .... notification complaint; (2) July 1979 Heller received original hold- ing delay damages; liable for termi Weiss was its subcontract with denying permission to Hartford filed amended promptly nated. Heller and Weiss to amend their answer add for the balance complaint adding a claim compulsory counterclaim. Thus, the new due under the subcontract.
Heller on
claims that
the “same transaction”
claim arose from
denying
trial court erred in
complaint—namely, the subcon
the initial
failing
interest on certain claims and
In view of
and Heller.
tract between Weiss
supervisory
time
amendment'
made
the fact that
and unabsorbed overhead.
trial,
May
several months before
time to pre
notice and
ample
Hartford had
I.
claim.
the new
pare its defense
allegation
initially
We address
Hartford’s
*4
Hepp,
v.
Protection Co.
Rural Fire
allowing Hel-
that
the trial court erred in
355,
(9th
1966). Accordingly, we
362
Cir.
24,
August
ler’s
1979 amended
amendment to
relating
find the
back of the
unpaid
balance on the subcontract
original complaint to have
the
the
date of
filing of
to relate back to the date of the
proper.
been
29,
the
1978.3
complaint—June
initial
15(c) provides for
Super.Ct.Civ.R.
Hartford,
relying on Lite-Air Prod
relating
the
of an
to the
back
amendment
ucts,
Deposit
Mary
&
Co. of
Fidelity
v.
Inc.
“[wjhenever
original pleading
date of the
801, 804(E.D.Pa.1977)
land,
F.Supp.
437
the
amend
claim or defense asserted
J. Carlin Construction
United States v. P.
conduct,
pleading
ed
arose out of the
trans
1001,
Co.,
(E.D.N.Y.1965),
F.Supp.
254
1002
attempted
action or occurrence set forth or
the trial court erred
next claims that
original pleadings”4
set
be
forth in the
surety liable for
holding
payment bond
added). Further,
amended
(emphasis
resulting
subcontractor
damages to the
initial
complaint relates back where “the
delay
performance.
from a
that
complaint put the defendant on notice
interpreted the
While some courts have
range
a certain
of matters was in contro
(the
counterpart
federal
Act6
Miller
complaint falls
versy and the amended
recovery from
seq.)
denying
as
range.”
Airways
Jackson
l-804a et
§
within that
v.
1366,
Co.,
(N.D.
adopt
Parking
F.Supp.
damages,
1382
delay
297
Ga.1969).5
found in United
of the Act
interpretation
v. Piracci Construc-
Mariana
States f/u/b
complaint alleged jur
The June 1978
(D.D.C.1975).
Co., Inc.,
F.Supp.
405
904
Superior
pursuant to
isdiction of the
be
that decision to
We find the rationale of
l-804b and 11-921
D.C.Code
§§
was de-
The
bond
persuasive.
put
that Hel
Weiss and Hartford
notice
supplying
signed
protect
subcontractors
seeking damages
ler was
for breach of the
project.
government
prime
labor and material
a
contract and subcontract.
Sup-
Flynn’s
Elec.
United States f/u/b
Camden
3.
It is
that no labor or
Hartford’s contention
Co.,
year
F.Supp.
performed by
ply
27
within one
Home Indem. Ins.
work was
Co. v.
complaint,
filing
(E.D.Pa.1965);
R.
re-
E. &
of the amended
as
States f/u/b
United
Thus,
l-804b(b).
quired by
Guy
§
H. James Constr.
Constr.
Co.
(M.D.Tenn.1972).
generally
com-
the count is
unless the amended
F.Supp.
barred
See
plaint
Columbia, D.C.App.,
relates back to the date
Strother v. District of
complaint.
affirmatively
(1977),
initial
which
A.2d
issue of whether
resolved the narrow
Super.Ct.Civ.R. 15(c),
is
on Fed.
which
based
legal capaci-
seeking
amendment
ty
liberally.
15(c),
applied
Dawn
R.Civ.P.
brings
plaintiff
suit relates back
in which
Co., Inc., D.C.Mun.App.,
Equipment
v. Stern
original filing.
date of the
(1957).
“Leave to file an omitted counterclaim
beyond the proper time limitations should
While the amended
does not
granted
court,
be
where the
in its discre-
specify
preparing
the
of
the
costs
estimate
tion, determines that the
omission
the
material,
deposition
of
of
storing
or
the
‘oversight, inadvertence,
result of
or excus-
president,
prior
four months
Heller’s
taken
justice
able neglect,’ or
so
where
demands.”
trial,
appellant
appellee’s
notified
of
in
Borst,
Bronson
404
D.C.App.,
A.2d
damages
tention to
for these items.
seek
(1979) quoting
Super.Ct.Civ.R.
from
Co.,
Darby,
Fisher &
Inc. v.
D.C.
See Jess
13(f).
Randolph
also
In-
See
v. Franklin
(1953); Randolph
cf.
Mun.App.,
other would result enrich-
ment. agree
We posting Heller that the Wheatley supervisory time to other
projects bookkeeping purposes for only does recovery unjust
not bar on the basis Accordingly,
enrichment.9 we remand the trial court for determination of the Larry BUMPER, Matter days number of additional supervisory Appellant. expended time by Heller. No. 80-966. conclusion, to the Appeals. District of Columbia Court of brought by (No. 80-748), we affirm the trial court’s holding that extended over- Nov. Submitted head damages are not recoverable Decided Feb. Hartford. We remand to the trial court for entry with respect interest
to the telephone vandalism claim and the
change order and determination of the
number of supervisory days incurred aas
result of the delay performance.
As (No. 80-
581), we affirm the trial court’s actions
permitting Heller’s amended
relate back to the date of
original complaint awarding and in dam-
ages work, prepara- entrance estimate, of a water
materials, vandalism and costs. With 4,” to “BCD No. we remand $14,858.
reduction of the award We find
no abuse of discretion in the trial court’s permission
denial of to Hartford and Weiss
to amend their answer to include a counter-
claim.
So ordered.
FERREN, Judge, concurring Associate
part dissenting part:
I generally opinion concur in the
court respect. but dissent in one In United
States f/u/b Mariana v. Piracci Construc (D.D.C.1975),
tion F.Supp. noted that claims for proved certainty
must be “with reasonable
and specificity.” Id. at 907 n.7. Given this compensa- hours. 9. Heller contends that it received no for these
