29 Barb. 410 | N.Y. Sup. Ct. | 1859
The referees have found, upon the new trial, that 6100 cubic yards of hard pan were excavated, under a new and separate agreement, by which ther plaintiff was to receive a reasonable compensation for his services in making such excavation, which they find to he forty cents per cubic yard. This agreement, upon the new finding, was a valid one. The plaintiff, according to this finding, after unexpectedly encountering this hard material, gave notice to one of the defendants that he could not go on and excavate this material at the price named in the contract, and must abandon the work, unless the defendants would allow more than the contract price for such material. The defendant Lauman, to whom this notice was given, then told the plaintiff to quit that portion of the work until some arrangement could be made in regard to it; and the plaintiff did quit it for about two weeks, when it was resumed under the new
The question of the right of the defendants to pay ten per cent of the contract price of the work in the stock of the rail road company, is now presented in an aspect materially different from that in which it was presented by the former report. We then held that inasmuch as the defendants had not refused to transfer the stock, but had, on the contrary, offered to do so in a manner not objected to by the plaintiff, they had not forfeited, the right to pay the amount specified in such stock. Ho question as to the value of the stock arose on the former trial; the only question then being, whether the defendants had offered a sufficient amount in stock at its nominal or par value. It now appears, from the report of the referees, that at the time the offer, such as it was, to pay in stock was made, such stock was worth only ninety cents on the dollar, of nominal value; and that at the time of the last trial it was utterly worthless, having no value whatever.
The defendants, on that occasion, offered the plaintiff $18.93 • in money, and an order on the treasurer of the company, at
It is obvious that an obligation to pay a definite sum in grain or any other personal property would not be performed by a tender of property of that description, so injured or decayed as to be utterly valueless. It seems to me, therefore, as the obligation cannot now be performed by the transfer of the stock specified, the amount is necessarily recoverable in money. It was no part of the intention, in making the agreement, that the plaintiff should lose the ten per cent, and the law will provide a remedy to prevent such a loss. In the case of Moore v. Hudson River R. R. Co., (12 Barb. 156,) the plaintiff agreed to take the stock at par.
The stipulation in. the agreement, that all matters in dispute, as to any matter connected with, or growing out of, the
T. R. Strong, Smith and Johnson, Justices.]
The engineers’ estimate of twenty-five cents per cubic yard, for the hard material, is not conclusive upon the plaintiff, as to value or price. If there was no agreement as to price, he was entitled to what it was reasonably worth to make the excavation. The estimate may afford some evidence of a price fixed, but it is not conclusive; and the referees have found that no price was agreed upon, but that the plaintiff was to have what it was worth.
The monthly estimates were not conclusive as to the amount of work done, and the receipt of payment thereon did not operate as a final settlement and adjustment of the work from month to month.
Several other questions were raised, though not much pressed upon the argument; but it seems to me there is nothing in any of them which would warrant a reversal of the judgment.
On the whole, I am of the opinion that the judgment must be affirmed.